NivaarExam PrepOfficial exam papers ↗

16-Civ-A3 Elementary Environmental Engineering · December 2019

Question 3 of 5: Peak discharge in an urban stormwater system

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format: National Exam 16-Civ-A3 Municipal and Environmental Engineering, December 2019 — 3 hours, open book, 100 marks. Five questions: answer Question 1 (mandatory) plus any three of Questions 2–5. All five are solved here as a study resource.

Reference texts: Davis & Cornwell, Introduction to Environmental Engineering (5th ed.); Mays, Water Resources Engineering (2nd ed.); Metcalf & Eddy, Wastewater Engineering: Treatment and Resource Recovery (5th ed.); Mihelcic & Zimmerman, Environmental Engineering: Fundamentals, Sustainability, Design. Canadian practice: EGBC/MMCD municipal design guidelines.

Question 3: Peak discharge in an urban stormwater system (25 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. Three subcatchments draining to three inlets; Pipe 1 (L=500 ft, r=1 ft, s=0.005 ft/ft, n=0.011) connects the Inlet 1/2 junction to Inlet 3; Pipe 2 carries the total onward. 50-yr Baltimore IDF (Figure 1).

Given — subcatchment data and read IDF intensities (50-yr)
InletA (acres)Ctc (min)i (in/hr)
11.50.559.9
21.50.778.9
32.50.6156.9

Find. Peak runoff at each inlet and the peak flow plus velocity in Pipes 1 and 2.

Approach. Apply the rational method $Q=CiA$ at each inlet using its own $t_c$; for the pipes accumulate the contributing $\sum CA$, take the intensity at the controlling (longest) time of concentration, then use Manning at the assumed 80%-perimeter section for velocity.

Inlet 1Inlet 2Inlet 3A=1.5 acC=0.5Tc=5 minA=1.5 acC=0.7Tc=7 minA=2.5 acC=0.6Tc=15 minPipe 1L=500 ft, r=1 ft, s=0.005Pipe 2→
Storm-sewer schematic: subcatchments 1–2 drain to the Inlet 1/2 junction; Pipe 1 conveys to Inlet 3 (subcatchment 3); Pipe 2 carries the combined flow to outfall.
  1. Inlet 1 (Part 1). With $t_c=5$ min, the 50-yr curve of Figure 1 gives $i\approx9.9$ in/hr (the curve leaves the left-hand axis just below the 10 in/hr gridline). In US customary units $Q\,[\text{cfs}]=C\,i\,[\text{in/hr}]\,A\,[\text{acre}]$ (the unit factor is 1.008 ≈ 1). $Q_1 = 0.5\times9.9\times1.5 = \boxed{7.43\ \text{cfs}}$.
  2. Inlet 2 (Part 2). $t_c=7$ min $\Rightarrow i\approx8.9$ in/hr. $Q_2 = 0.7\times8.9\times1.5 = \boxed{9.35\ \text{cfs}}$.
  3. Inlet 3 (Part 3). $t_c=15$ min $\Rightarrow i\approx6.9$ in/hr (the 50-yr curve sits clearly above the 6 in/hr gridline at 15 min). $Q_3 = 0.6\times6.9\times2.5 = \boxed{10.35\ \text{cfs}}$.
  4. Pipe 1 flow (Part 4). Pipe 1 carries the combined runoff of subcatchments 1 and 2. The controlling time of concentration is the longer of the two, $t_c=7$ min, so $i=8.9$ in/hr. With $\sum CA = 0.5(1.5)+0.7(1.5)=1.80$, the peak flow is $Q_{p1}=i\sum CA = 8.9\times1.80 = \boxed{16.0\ \text{cfs}}$.
  5. Pipe 1 velocity (Part 4). With $r=1$ ft, the full circumference is $2\pi r=6.28$ ft; the wetted perimeter is $P=0.8(6.28)=5.03$ ft, i.e. a wetted central angle $\theta=0.8(2\pi)=5.03$ rad. Flow area $A=\pi r^2-\tfrac12 r^2(\alpha-\sin\alpha)=3.14-0.15=2.99\ \text{ft}^2$ (dry cap angle $\alpha=2\pi-\theta=1.257$ rad), so $R=A/P=2.99/5.03=0.595$ ft. Manning (US): $V=\dfrac{1.486}{n}R^{2/3}s^{1/2}=\dfrac{1.486}{0.011}(0.595)^{2/3}(0.005)^{1/2}=\boxed{6.75\ \text{ft/s}}$. The corresponding section capacity $Q=VA=6.75\times2.99=20.2$ cfs exceeds the 16.0 cfs inflow, so Pipe 1 is adequate; travel time $t=L/V=500/6.75=74\ \text{s}=1.23$ min.
  6. Pipe 2 (Part 5). Pipe 2 carries all three subcatchments, $\sum CA = 1.80+0.6(2.5)=3.30$. The controlling $t_c$ is the longest path to Inlet 3: local subcatchment 3 gives 15 min, whereas the routed path is $7+1.23\approx8.2$ min — so 15 min governs and $i=6.9$ in/hr. Peak flow $Q_{p2}=6.9\times3.30 = \boxed{22.8\ \text{cfs}}$. Taking Pipe 2 as the same section and slope, $V_2\approx\boxed{6.75\ \text{ft/s}}$ and its capacity is only $\approx20.2$ cfs — less than the 22.8 cfs peak, so the 1-ft-radius pipe on $s=0.005$ is under-sized at this point and must be enlarged (or laid steeper) in design.
Peak discharges and velocities
ElementPeak flowVelocity
Inlet 17.43 cfs—
Inlet 29.35 cfs—
Inlet 310.35 cfs—
Pipe 116.0 cfs (cap. 20.2 — adequate)6.75 ft/s
Pipe 222.8 cfs (cap. 20.2 — under-sized)6.75 ft/s
Check: the source figure boxes each subcatchment (“Subwashed 1/2/3”) with its own $A$, $C$ and $t_c$, so the assignment 1→Inlet 1, 2→Inlet 2, 3→Inlet 3 is read directly from the drawing; Pipe 1 runs from the Inlet 1/2 junction to Inlet 3 and Pipe 2 onward to outfall. Pipe 2’s length and slope are not dimensioned; its slope is taken equal to Pipe 1 (0.005) so that the velocity carries over. The intensities were read off the printed Baltimore 50-yr curve against its labelled decade gridlines: 9.9, 8.9 and 6.9 in/hr at 5, 7 and 15 min (each to about $\pm$2%). A $\pm$5% reading error moves every discharge by the same $\pm$5% and does not change any conclusion — Pipe 2 stays above the 20.2 cfs section capacity for any reading above 6.1 in/hr at 15 min. Velocities of 6.8 ft/s are within the acceptable 2–10 ft/s range for storm sewers.