16-Civ-A3 Elementary Environmental Engineering · December 2019
Question 3 of 5: Peak discharge in an urban stormwater system
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format: National Exam 16-Civ-A3 Municipal and Environmental Engineering, December 2019 — 3 hours, open book, 100 marks. Five questions: answer Question 1 (mandatory) plus any three of Questions 2–5. All five are solved here as a study resource.
Reference texts: Davis & Cornwell, Introduction to Environmental Engineering (5th ed.); Mays, Water Resources Engineering (2nd ed.); Metcalf & Eddy, Wastewater Engineering: Treatment and Resource Recovery (5th ed.); Mihelcic & Zimmerman, Environmental Engineering: Fundamentals, Sustainability, Design. Canadian practice: EGBC/MMCD municipal design guidelines.
Question 3: Peak discharge in an urban stormwater system (25 marks)
Given. Three subcatchments draining to three inlets; Pipe 1 (L=500 ft, r=1 ft, s=0.005 ft/ft, n=0.011) connects the Inlet 1/2 junction to Inlet 3; Pipe 2 carries the total onward. 50-yr Baltimore IDF (Figure 1).
Given — subcatchment data and read IDF intensities (50-yr)
Inlet
A (acres)
C
tc (min)
i (in/hr)
1
1.5
0.5
5
9.9
2
1.5
0.7
7
8.9
3
2.5
0.6
15
6.9
Find. Peak runoff at each inlet and the peak flow plus velocity in Pipes 1 and 2.
Approach. Apply the rational method $Q=CiA$ at each inlet using its own $t_c$; for the pipes accumulate the contributing $\sum CA$, take the intensity at the controlling (longest) time of concentration, then use Manning at the assumed 80%-perimeter section for velocity.
Storm-sewer schematic: subcatchments 1–2 drain to the Inlet 1/2 junction; Pipe 1 conveys to Inlet 3 (subcatchment 3); Pipe 2 carries the combined flow to outfall.
Inlet 1 (Part 1). With $t_c=5$ min, the 50-yr curve of Figure 1 gives $i\approx9.9$ in/hr (the curve leaves the left-hand axis just below the 10 in/hr gridline). In US customary units $Q\,[\text{cfs}]=C\,i\,[\text{in/hr}]\,A\,[\text{acre}]$ (the unit factor is 1.008 ≈ 1). $Q_1 = 0.5\times9.9\times1.5 = \boxed{7.43\ \text{cfs}}$.
Inlet 3 (Part 3). $t_c=15$ min $\Rightarrow i\approx6.9$ in/hr (the 50-yr curve sits clearly above the 6 in/hr gridline at 15 min). $Q_3 = 0.6\times6.9\times2.5 = \boxed{10.35\ \text{cfs}}$.
Pipe 1 flow (Part 4). Pipe 1 carries the combined runoff of subcatchments 1 and 2. The controlling time of concentration is the longer of the two, $t_c=7$ min, so $i=8.9$ in/hr. With $\sum CA = 0.5(1.5)+0.7(1.5)=1.80$, the peak flow is $Q_{p1}=i\sum CA = 8.9\times1.80 = \boxed{16.0\ \text{cfs}}$.
Pipe 1 velocity (Part 4). With $r=1$ ft, the full circumference is $2\pi r=6.28$ ft; the wetted perimeter is $P=0.8(6.28)=5.03$ ft, i.e. a wetted central angle $\theta=0.8(2\pi)=5.03$ rad. Flow area $A=\pi r^2-\tfrac12 r^2(\alpha-\sin\alpha)=3.14-0.15=2.99\ \text{ft}^2$ (dry cap angle $\alpha=2\pi-\theta=1.257$ rad), so $R=A/P=2.99/5.03=0.595$ ft. Manning (US): $V=\dfrac{1.486}{n}R^{2/3}s^{1/2}=\dfrac{1.486}{0.011}(0.595)^{2/3}(0.005)^{1/2}=\boxed{6.75\ \text{ft/s}}$. The corresponding section capacity $Q=VA=6.75\times2.99=20.2$ cfs exceeds the 16.0 cfs inflow, so Pipe 1 is adequate; travel time $t=L/V=500/6.75=74\ \text{s}=1.23$ min.
Pipe 2 (Part 5). Pipe 2 carries all three subcatchments, $\sum CA = 1.80+0.6(2.5)=3.30$. The controlling $t_c$ is the longest path to Inlet 3: local subcatchment 3 gives 15 min, whereas the routed path is $7+1.23\approx8.2$ min — so 15 min governs and $i=6.9$ in/hr. Peak flow $Q_{p2}=6.9\times3.30 = \boxed{22.8\ \text{cfs}}$. Taking Pipe 2 as the same section and slope, $V_2\approx\boxed{6.75\ \text{ft/s}}$ and its capacity is only $\approx20.2$ cfs — less than the 22.8 cfs peak, so the 1-ft-radius pipe on $s=0.005$ is under-sized at this point and must be enlarged (or laid steeper) in design.
Peak discharges and velocities
Element
Peak flow
Velocity
Inlet 1
7.43 cfs
—
Inlet 2
9.35 cfs
—
Inlet 3
10.35 cfs
—
Pipe 1
16.0 cfs (cap. 20.2 — adequate)
6.75 ft/s
Pipe 2
22.8 cfs (cap. 20.2 — under-sized)
6.75 ft/s
Check: the source figure boxes each subcatchment (“Subwashed 1/2/3”) with its own $A$, $C$ and $t_c$, so the assignment 1→Inlet 1, 2→Inlet 2, 3→Inlet 3 is read directly from the drawing; Pipe 1 runs from the Inlet 1/2 junction to Inlet 3 and Pipe 2 onward to outfall. Pipe 2’s length and slope are not dimensioned; its slope is taken equal to Pipe 1 (0.005) so that the velocity carries over. The intensities were read off the printed Baltimore 50-yr curve against its labelled decade gridlines: 9.9, 8.9 and 6.9 in/hr at 5, 7 and 15 min (each to about $\pm$2%). A $\pm$5% reading error moves every discharge by the same $\pm$5% and does not change any conclusion — Pipe 2 stays above the 20.2 cfs section capacity for any reading above 6.1 in/hr at 15 min. Velocities of 6.8 ft/s are within the acceptable 2–10 ft/s range for storm sewers.