Question 3 of 6: Overload probability, delay components, person delay and queue length
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Examinations, May 2014 — 98-Civ-B10
Traffic Engineering. Three-hour, open-book examination; any non-communicating
calculator is permitted. Six questions are printed and five complete solutions are
required, all questions being of equal value (20 marks each). The printed grading scheme
is Q1 (a) to (d) 5 marks each; Q2 (a) to (e) 4 marks each; Q3 (a) to (e) 4 marks each;
Q4 (a) and (b) 10 marks each; Q5 (a) to (e) 4 marks each; Q6 (10 + 5 + 5) marks. The paper
states that if doubt exists as to the interpretation of a question the candidate should
submit with the answer paper a clear statement of any assumptions made, and that any data
required but not given can be assumed. All six questions are worked below.
Reference texts. Garber, N. J. and Hoel, L. A.,
Traffic and Highway Engineering, 5th ed. — Ch. 4 (traffic engineering
studies: volume studies, peak-hour factor), Ch. 6 (fundamental principles of traffic flow:
Poisson arrivals, deterministic and stochastic queueing, M/M/1 and M/M/N channels),
Ch. 8 (intersection control: cycle length, phasing, change and clearance intervals,
progression and time–space diagrams) and Ch. 10 (capacity and level of service at
signalised intersections). This is the principal reference for the subject.
Webster, F. V. and Cobbe, B. M., Traffic Signals, Road Research Laboratory
Technical Paper No. 56 — the optimum-cycle and three-term delay formulae used
throughout Questions 1 to 3. Transportation Research Board, Highway Capacity Manual
— saturation-flow adjustment factors and the pedestrian-green requirement.
Transportation Association of Canada, Manual of Uniform Traffic Control Devices for
Canada (MUTCDC) and Geometric Design Guide for Canadian Roads — Canadian
signal-timing, clearance-interval and crosswalk practice. Institute of Transportation
Engineers, Traffic Engineering Handbook — controller types and coordinated
timing plans.
Check: the four values assumed under the paper's own
NOTE 2 (“any data required, but not given, can be assumed”). They are
declared here once and used consistently in every question.
Bus passenger-car equivalent $E_B = 2.0$ pcu (HCM value for buses on
level terrain). The paper gives bus occupancies but no pcu equivalent; note that
the pcu-based and vehicle-based flow ratios in Question 1 agree exactly for any choice of
$E_B$, so this assumption does not affect Questions 2 or 3.
Pedestrian walking speed $S_p = 1.2$ m/s (HCM 2000 / MUTCDC design
value; the more recent 1.1 m/s would lengthen the pedestrian interval by about 1 s).
Lost time convention: the whole intergreen (amber + all-red) is taken
as lost, so effective green equals displayed green. This is the conservative reading and
needs no assumed start-up lost time. Webster's alternative, $L = n\ell + R$ with
$\ell \approx 2$ s, would give $L = 10$ s instead of 12 s and lengthen each green by about
1 s.
Delay model: Webster's three-term formula, with the first two terms
reported separately in Question 3(b) as the uniform and overflow components.
Question 3: Overload probability, delay components, person delay and queue length (20 marks)
Given. The timing plan settled in Question 2 — $C = 75$ s,
$G_{NS} = 34$ s, $G_{EW} = 29$ s, $I = 6$ s — together with:
Approach
Lane demand $q$ (pcu/h)
Green $g$ (s)
$x$
Persons/h
North-bound
415
34
0.509
1975
South-bound
362
34
0.444
1580
East-bound
250
29
0.359
1000
West-bound
350
29
0.503
1400
Saturation flow $s_0 = 1800$ pcu/h/lane; pedestrian demand 140 per hour in each of the
four crosswalks; arrivals assumed Poisson, which is the standard model for an isolated
signal.
Find. For each approach, the probability that a cycle's arrivals
exceed what the green can discharge; the uniform and overflow components of delay and their
flow-weighted totals; the total person-hours of delay to vehicle occupants; the average
pedestrian delay; and the average queue standing at the end of red.
Approach. Treat each cycle as an independent Poisson trial with mean
$qC$ arrivals against a fixed discharge capacity $sg$; split Webster's delay into its
deterministic and stochastic parts; convert vehicle delay to person delay through the
occupancies of Question 1; and get the queue directly from the deterministic
arrival–departure diagram.
Question 3(e) — deterministic cumulative arrival and departure curves for the north-bound lane. The queue at the end of red is the vertical gap between the two curves at t = r.
Part (a) — set up the overload trial.
“Discharge overload” means more vehicles arrive during a cycle than the green can
release, so the residue carries over. Per lane the mean arrivals per cycle and the whole
number of vehicles that a green can discharge are
$$m = \frac{q\,C}{3600}, \qquad n = \left\lfloor \frac{s_0\,g}{3600} \right\rfloor,$$
and with Poisson arrivals the overload probability is the upper tail
$$P(\text{overload}) = P(X > n) = 1 - \sum_{k=0}^{n} \frac{e^{-m} m^{k}}{k!}.$$
North-bound, $m = 415(75)/3600 = 8.65$ vehicles per cycle against $n = 1800(34)/3600 = 17$
discharged, so the tail beyond 17 is required.
Part (a) — evaluate the tail on each approach.
Carrying out the summation gives the following.
Approach
$m$ (arrivals/cycle)
$n$ (discharged)
$P(X > n)$
North-bound
8.65
17
0.0036
South-bound
7.54
17
0.00084
East-bound
5.21
14
0.00034
West-bound
7.29
14
0.0081
The largest value is west-bound, and it is instructive: that approach does not have the
heaviest flow, but it has the shortest green, so its ratio $m/n$ is the worst. Overall,
$$\boxed{\;P(\text{overload}) \le 0.8\ \% \text{ on every approach — roughly one cycle in 120 on the worst}\;}$$
which is an acceptable level of cycle failure for an urban signal.
Part (b) — separate the uniform and overflow components.
The first term of Webster's formula is the delay a perfectly regular arrival stream would
suffer, and the second is the extra delay caused by the randomness of real arrivals:
$$d_1 = \frac{C\,(1 - \lambda)^2}{2\,(1 - \lambda x)}, \qquad
d_2 = \frac{x^2}{2\,q\,(1 - x)}, \qquad
d_3 = 0.65\left(\frac{C}{q^2}\right)^{1/3} x^{\,2 + 5\lambda}.$$
For the north-bound lane, $d_1 = 14.57$, $d_2 = 2.28$ and the empirical correction
$d_3 = 0.65$ s/pcu. The four approaches give:
Approach
$d_1$ uniform (s/pcu)
$d_2$ overflow (s/pcu)
$d_3$ correction
$d$ total
North-bound
14.57
2.28
0.65
16.20
South-bound
14.03
1.76
0.39
15.39
East-bound
16.38
1.45
0.29
17.54
West-bound
17.51
2.62
0.87
19.26
Weighting each column by the approach demand in pcu/h,
$$\boxed{\;\bar d_1 = 15.50,\quad \bar d_2 = 2.08,\quad \bar d_3 = 0.57,\quad
\bar d = 15.50 + 2.08 - 0.57 = 17.0\ \text{s/pcu}\;}$$
The uniform term supplies about 88 % of the delay: at these degrees of saturation the
intersection is dominated by the deterministic effect of stopping at red, not by
randomness.
Part (c) — convert vehicle delay into person delay.
Every occupant of a delayed vehicle is delayed with it, so the person-hours lost per hour
on an approach are
$$H_i = \frac{d_i \times (\text{persons per hour})_i}{3600}.$$
North-bound: $16.20(1975)/3600 = 8.89$ person-hours per hour. The remaining approaches give
6.76 (SB), 4.87 (EB) and 7.49 (WB), so
$$\boxed{\;H_{\text{total}} = 8.89 + 6.76 + 4.87 + 7.49 = 28.0\ \text{person-hours per hour}\;}$$
Note the ranking: the north-bound approach has neither the longest delay nor the worst
saturation, yet it dominates the person delay because of its 15 buses.
Part (d) — average delay to pedestrians.
A pedestrian arriving at random in the cycle waits nothing if the crossing is already open
and waits the remainder of the non-crossing time otherwise. Averaging over a uniform arrival
instant gives the standard result
$$d_p = \frac{(C - g_p)^2}{2C}.$$
Pedestrians on the north and south legs cross on the 29 s E–W green:
$d_p = (75 - 29)^2/150 = 14.11$ s. Pedestrians on the east and west legs cross on the 34 s
N–S green: $d_p = (75 - 34)^2/150 = 11.21$ s. With 140 pedestrians per hour in each of
the four crosswalks the demands are equal, so
$$\boxed{\;\bar d_p = \tfrac{1}{2}(14.11 + 11.21) = 12.7\ \text{s per pedestrian}\;}$$
equivalent to $4(140)(12.66)/3600 = 1.97$ person-hours of pedestrian delay per hour, which
is worth quoting beside the 28.0 vehicle person-hours when the plan is defended.
Part (e) — queue standing at the end of red.
On the deterministic diagram above, vehicles accumulate at the arrival rate throughout the
red and none departs, so the queue at the instant green begins is simply
$$Q_r = q\,r, \qquad r = C - g.$$
The N–S approaches see $r = 75 - 34 = 41$ s and the E–W approaches
$r = 75 - 29 = 46$ s, giving
$$\boxed{\;Q_{NB} = 4.7,\quad Q_{SB} = 4.1,\quad Q_{EB} = 3.2,\quad Q_{WB} = 4.5
\ \text{veh per lane}\;}$$
or about 9.5 vehicles across the two north-bound lanes. At roughly 8 m of kerb per queued
car that is a standing queue of about 38 m in the worst lane — well within a normal
block length, so no spill-back check is needed.