Question 5 of 10: Retaining wall for highway slope stabilisation in clay
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. Professional Engineers Ontario /
Engineers Canada National Examinations, December 2014 — 98-Civ-B3 Geotechnical
Design. Three hours, OPEN BOOK, any non-communicating calculator. Section A carries five
discussion questions of 7 marks each (answer any four); Section B carries five design
questions of 24 marks each (answer any three); the examinable total is
4 × 7 + 3 × 24 = 100 marks. All ten questions are worked below, because the
set is a study resource rather than a timed attempt.
B. M. Das, Principles of Foundation Engineering, 9th ed. — bearing
capacity (Ch. 3), stress increase in a soil mass (Ch. 6), retaining walls (Ch. 8), pile
foundations (Ch. 11).
B. M. Das, Principles of Geotechnical Engineering, 9th ed. — lateral
earth pressure (Ch. 13), shear strength (Ch. 12), slope stability (Ch. 15), subsurface
exploration (Ch. 17).
Canadian Geotechnical Society, Canadian Foundation Engineering Manual
(CFEM), 4th ed. — the governing Canadian practice document for site investigation,
bearing resistance, deep foundations and earth-retaining structures.
R. F. Craig, Craig's Soil Mechanics, 8th ed. — earth pressure theory
and slope stability.
D. P. Coduto, Foundation Design: Principles and Practices, 2nd ed. —
in-situ testing and SPT correlations.
J. E. Bowles, Foundation Analysis and Design, 5th ed. — bearing
capacity factors and retaining-wall stability tables.
Sources of charts and assumed values (page-1 Note 6). Note 6 of this
paper requires the candidate to identify the source of every design chart and every
assumed value. Each chart reading and each assumption below is therefore named where it is
used, and the values assumed in the absence of data are collected here:
Q6 — adhesion factor α from Das,
Principles of Foundation Engineering, Table 11.6 (Terzaghi, Peck & Mesri
form, α against $c_u/p_a$); $\lambda$ from Vijayvergiya & Focht
(1972) as tabulated by Das, Table 11.7.
Q7 — overburden correction $C_N$ from Liao & Whitman
(1986); $\phi'$ from Wolff (1989) and from Hatanaka & Uchida (1996), both reproduced
in Das, Ch. 2; settlement-controlled bearing pressure from Meyerhof (1965) as given by
Das, Ch. 5, used only as a serviceability check because the question forbids direct
correlations of bearing capacity to penetration index. Table I prints the blow counts as
field values $N_f$; with no hammer data they are converted as $N_{60} = N_f$, i.e. a
safety hammer at the reference 60 per cent energy ratio with borehole, sampler and
rod-length factors of 1 (Das, Ch. 2, hammer-efficiency and correction-factor tables).
Q8 — embankment influence factor from Osterberg (1957),
reproduced as Das Fig. 6.24; the closed form of that chart is used so the reading carries
no chart-scaling error.
Q9 — Meyerhof general bearing-capacity equation with the shape
factors of De Beer (1970) and the depth factors of Hansen (1970), as set out in Das,
Ch. 3.
Q10 — Coulomb active earth-pressure coefficient, Das
Eq. 13.31; unit weight of the mass-concrete wall assumed
$\gamma_c = 24\ \text{kN/m}^3$ (CFEM 4th ed., normal-density concrete), the only value
the figure does not supply.
Question 5: Retaining wall for highway slope stabilisation in clay
(7 marks)
Parameters to be considered. The design of a slope-stabilising wall in
clay is controlled by a wider set of parameters than a conventional backfill-retaining
wall, because the wall must change the stability of a soil mass that is already marginal.
The parameters are:
Geometry — existing and final slope angles, wall height, the depth and
shape of the critical slip surface from a back-analysis of the existing slope, and the
available right-of-way.
Stratigraphy and strength — the clay profile, the depth to a competent
stratum or bedrock into which the wall can be keyed, undrained strength $c_u$ for the
construction case, and drained parameters for the long term. In a stiff fissured clay these
must be the fully softened values, and on any pre-sheared surface the residual values.
Groundwater and seepage — the piezometric surface, perched water, and the
pore pressures on the slip surface. Water is both a load and a strength reducer and is the
dominant design variable in a clay slope.
Loads — highway live load surcharge, the weight of the pavement structure,
snow-clearing and maintenance vehicles, guardrail impact, and the down-slope creep pressure
from the mass above the wall.
Seismic — the design spectral accelerations from the National Building
Code of Canada for the site, and the resulting pseudo-static horizontal coefficient for a
Mononobe–Okabe check.
Serviceability and environment — tolerable movement of the pavement,
frost penetration depth and frost-susceptibility of the retained soil, freeze–thaw and
de-icing salt exposure of the concrete (CSA A23.1 class C-2 or C-4), and drainage
provision.
Constructability — access on a steep slope, the stability of any temporary
excavation, and whether traffic must be maintained during construction.
Type of wall proposed, and the justification. For a highway cut or
sidelong fill on a steep clay slope I would propose a discrete bored-pile (soldier
pile or contiguous / tangent pile) wall, socketed below the critical slip surface, with a
reinforced-concrete capping beam and, if the height requires it, one row of ground
anchors.
The justification is that the governing limit state here is global stability,
not the local overturning or sliding of a wall stem. A gravity or cantilever wall resists
only the earth pressure acting on its own back face; it does nothing for a slip surface that
passes beneath its base, and its own weight is an additional driving load on the slope. A
mechanically stabilised earth wall is worse still on this site, because it requires a wide
excavation into the slope and a large volume of imported granular fill, both of which
destabilise the slope during construction. By contrast a pile wall keyed 3 to 5 m below the
critical circle adds a real resisting shear force across that surface, and it is built
top-down from the existing bench with no bulk excavation, so the slope is never
temporarily unsupported. The piles can be installed with a small track rig on a narrow
bench, which suits difficult access, and the wall face can be finished with shotcrete or
precast panels between the piles. Where the retained height is modest and access is good, a
cantilever reinforced-concrete wall with a deep shear key is a reasonable and cheaper
alternative, and a soil-nailed wall is a good choice in a cut where the clay is stiff and
can stand unsupported for the height of one nail lift.
Hazard scenarios. The design must be checked against, at minimum:
Deep-seated global instability passing beneath or behind the wall — the
single most important check, and the one a conventional wall-stability calculation does not
cover.
Build-up of water pressure behind the wall from a blocked or under-designed
drain. This is historically the commonest cause of retaining-wall failure, and it must be
addressed by a granular drainage blanket or geocomposite drain, weep holes, and a
maintainable outlet.
Long-term softening of the clay from peak towards fully softened strength, and
progressive failure along a strain-softening slip surface.
Seismic loading, including the inertial force on the wall and the increased
active thrust.
Construction-stage instability — the temporary excavation, surcharge from
plant, and the period before the capping beam or anchors are stressed.
Toe erosion or scour where a watercourse runs at the base of the slope, and
future excavation in front of the wall (service trenches) removing passive resistance.
Frost heave and freeze–thaw, including ice-lensing pressures on the wall
face if a frost-susceptible soil is retained without drainage.
Downslope creep of the mass above the wall, which imposes a lateral load
independent of the classical active wedge.
Differential settlement of the wall and the adjoining pavement, and the
resulting bump at the wall.
Durability — corrosion of anchors and reinforcement under de-icing salt
exposure, and the consequence of an anchor losing its capacity late in the design life.