NivaarExam PrepOfficial exam papers ↗

16-Civ-B3 Geotechnical Design · December 2014

Question 5 of 10: Retaining wall for highway slope stabilisation in clay

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. Professional Engineers Ontario / Engineers Canada National Examinations, December 2014 — 98-Civ-B3 Geotechnical Design. Three hours, OPEN BOOK, any non-communicating calculator. Section A carries five discussion questions of 7 marks each (answer any four); Section B carries five design questions of 24 marks each (answer any three); the examinable total is 4 × 7 + 3 × 24 = 100 marks. All ten questions are worked below, because the set is a study resource rather than a timed attempt.

Reference texts (98-Civ-B3 / 16-Civ-B3 Geotechnical Design).

Sources of charts and assumed values (page-1 Note 6). Note 6 of this paper requires the candidate to identify the source of every design chart and every assumed value. Each chart reading and each assumption below is therefore named where it is used, and the values assumed in the absence of data are collected here:

  • Q6 — adhesion factor α from Das, Principles of Foundation Engineering, Table 11.6 (Terzaghi, Peck & Mesri form, α against $c_u/p_a$); $\lambda$ from Vijayvergiya & Focht (1972) as tabulated by Das, Table 11.7.
  • Q7 — overburden correction $C_N$ from Liao & Whitman (1986); $\phi'$ from Wolff (1989) and from Hatanaka & Uchida (1996), both reproduced in Das, Ch. 2; settlement-controlled bearing pressure from Meyerhof (1965) as given by Das, Ch. 5, used only as a serviceability check because the question forbids direct correlations of bearing capacity to penetration index. Table I prints the blow counts as field values $N_f$; with no hammer data they are converted as $N_{60} = N_f$, i.e. a safety hammer at the reference 60 per cent energy ratio with borehole, sampler and rod-length factors of 1 (Das, Ch. 2, hammer-efficiency and correction-factor tables).
  • Q8 — embankment influence factor from Osterberg (1957), reproduced as Das Fig. 6.24; the closed form of that chart is used so the reading carries no chart-scaling error.
  • Q9 — Meyerhof general bearing-capacity equation with the shape factors of De Beer (1970) and the depth factors of Hansen (1970), as set out in Das, Ch. 3.
  • Q10 — Coulomb active earth-pressure coefficient, Das Eq. 13.31; unit weight of the mass-concrete wall assumed $\gamma_c = 24\ \text{kN/m}^3$ (CFEM 4th ed., normal-density concrete), the only value the figure does not supply.

Question 5: Retaining wall for highway slope stabilisation in clay (7 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Parameters to be considered. The design of a slope-stabilising wall in clay is controlled by a wider set of parameters than a conventional backfill-retaining wall, because the wall must change the stability of a soil mass that is already marginal. The parameters are:

Type of wall proposed, and the justification. For a highway cut or sidelong fill on a steep clay slope I would propose a discrete bored-pile (soldier pile or contiguous / tangent pile) wall, socketed below the critical slip surface, with a reinforced-concrete capping beam and, if the height requires it, one row of ground anchors.

The justification is that the governing limit state here is global stability, not the local overturning or sliding of a wall stem. A gravity or cantilever wall resists only the earth pressure acting on its own back face; it does nothing for a slip surface that passes beneath its base, and its own weight is an additional driving load on the slope. A mechanically stabilised earth wall is worse still on this site, because it requires a wide excavation into the slope and a large volume of imported granular fill, both of which destabilise the slope during construction. By contrast a pile wall keyed 3 to 5 m below the critical circle adds a real resisting shear force across that surface, and it is built top-down from the existing bench with no bulk excavation, so the slope is never temporarily unsupported. The piles can be installed with a small track rig on a narrow bench, which suits difficult access, and the wall face can be finished with shotcrete or precast panels between the piles. Where the retained height is modest and access is good, a cantilever reinforced-concrete wall with a deep shear key is a reasonable and cheaper alternative, and a soil-nailed wall is a good choice in a cut where the clay is stiff and can stand unsupported for the height of one nail lift.

Hazard scenarios. The design must be checked against, at minimum: