16-Civ-B7 Transportation Planning and Engineering · May 2013
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Paper format. 98-Civ-B7 Highway Engineering, National Examinations May 2013 — a three-hour open-book examination; any non-communicating calculator is permitted. The cover page states that a total of five solutions is required, that only the first five as they appear in the answer book will be marked, and that all questions are of equal value. The grading scheme on the last page confirms 20 marks per question: Q1 (a) and (b) 10 marks each; Q2 (a) through (e) 4 marks each; Q3 (a) to (j) 2 marks each; Q4 (a) and (b) 10 marks each; Q5 (a) and (b) 10 marks each; Q6 (a) through (e) 4 marks each; Q7 20 marks. All seven printed questions are worked here, because this set is a study resource rather than a timed attempt; on exam day a candidate submits only the first five, in order. The paper also states that any data not given but required may be assumed, and that assumptions should be recorded with the answer — several questions below need that licence, and each assumption is flagged where it is made.
Reference texts. N.J. Garber and L.A. Hoel, Traffic and Highway Engineering, 5th ed. (geometric design, sight distance, vertical curves, earthwork, pavement design); AASHTO, Guide for Design of Pavement Structures (1993) (rigid and flexible thickness design, reliability, drainage and load-transfer coefficients); Transportation Association of Canada, Geometric Design Guide for Canadian Roads (Canadian design-domain values for sight distance and vertical curvature); Asphalt Institute, Mix Design Methods MS-2, 7th ed. (mixture volumetrics, VMA, VFA, absorbed binder); B.M. Das, Principles of Geotechnical Engineering, 9th ed. (compaction, Proctor testing, zero-air-voids line, CBR); M.S. Mamlouk and J.P. Zaniewski, Materials for Civil and Construction Engineers, 4th ed. (concrete and asphalt materials); A.M. Neville, Properties of Concrete, 5th ed., and CSA A23.1 (air entrainment, curing, joints in concrete pavement).
Check — assumptions carried through this paper. Three items are not supplied by the exam and are assumed under the paper’s own Note 2 (“any data, not given but required, can be assumed”), each stated again at the point of use: (i) Question 5 gives the mass of the Proctor mould but not its volume, so the ASTM D698 / AASHTO T99 standard 101.6 mm mould volume of 944 cm3 is used; (ii) Question 6 does not name a design speed, so the available stopping sight distance is computed from the Canadian/AASHTO eye and object heights of 1.08 m and 0.60 m; (iii) Question 7 lists the modulus of subgrade reaction as “1.0 MPa”, which is dimensionally incomplete — it is read as 1.0 MPa/m and the sensitivity of the answer to that reading is reported with the result.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. An equal-tangent parabolic crest curve joining a rising 4 % grade to a falling 3 % grade, with the intersection point and the curve length both fixed.
| Item | Value |
|---|---|
| Approach grade, g1 | +4 % |
| Departure grade, g2 | −3 % |
| Station and elevation of PVI | 15+00 (chainage 1500 m), 400.00 m |
| Length of vertical curve, L | 1000 m |
| Station interval | 100 m |
Find. The station and elevation of the PVC and PVT; the curve elevation at every 100 m station; the stopping sight distance the curve actually provides; the station and elevation of the high point; and the rate of change of grade.
Approach. An equal-tangent parabola is fully described by its PVC elevation, the entering grade and the constant second derivative A/(100L); every part of the question is then a substitution into the single elevation equation, except the sight distance, which comes from the standard crest formula with Canadian eye and object heights.
| Station | x from PVC (m) | Elevation (m) |
|---|---|---|
| 10+00 (PVC) | 0 | 380.000 |
| 11+00 | 100 | 383.650 |
| 12+00 | 200 | 386.600 |
| 13+00 | 300 | 388.850 |
| 14+00 | 400 | 390.400 |
| 15+00 | 500 | 391.250 |
| 15+71.43 (high point) | 571.43 | 391.429 |
| 16+00 | 600 | 391.400 |
| 17+00 | 700 | 390.850 |
| 18+00 | 800 | 389.600 |
| 19+00 | 900 | 387.650 |
| 20+00 (PVT) | 1000 | 385.000 |
The five answers describe one object consistently: a very long, very flat crest whose K value of 143 is close to double the K = 74 that a 110 km/h Canadian rural highway requires for stopping sight distance (S = 220 m), and still half again the K = 95 required at 120 km/h. The 1000 m length is therefore not driven by sight distance at all — about 515 m would serve the 110 km/h control and 665 m the 120 km/h one — so it must come from drainage, from appearance, or from matching an existing profile. That is worth noticing because a crest this flat drains poorly near the high point: the longitudinal gradient is flatter than 0.5 % from chainage 1500 to 1643, a 143 m stretch, and the designer would need to check that the cross-fall and the gutter grade still move water away.
| Quantity | Value |
|---|---|
| (a) PVC | Station 10+00, elevation 380.00 m |
| (a) PVT | Station 20+00, elevation 385.00 m |
| (b) Elevations at 100 m stations | 380.000, 383.650, 386.600, 388.850, 390.400, 391.250, 391.400, 390.850, 389.600, 387.650, 385.000 m |
| (c) Available stopping sight distance | S = 306.6 m (S < L, so the correct branch) |
| (d) High point (zero grade) | Station 15+71.43, elevation 391.429 m |
| (e) Rate of change of grade | −0.007 % per metre (−0.7 % per station); K = 142.9 m/% |