16-Civ-B8 Management of Construction · December 2013
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Paper format. National Exams, December 2013 — 98-Civ-B8 Management of Construction (the paper now catalogued as 16-Civ-B8). Three hours, closed book; one of two approved calculator models permitted. Six questions of equal value (20 marks each); the rubric states that any five constitute a complete paper and that only the first five presented in the answer book will be marked. All six are worked here, because this set is a study resource rather than an exam script. The paper splits three calculative questions (scheduling, engineering economics, estimating) against three descriptive ones (claims, project control, safety).
Reference texts.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. Ten activities A to J with fixed durations in weeks and a finish-to-start dependency list, reproduced from the exam table. Every activity occupies one mechanical excavator for the whole of its duration, and once started it cannot be interrupted (no splitting).
| Activity | Duration (weeks) | Depends on |
|---|---|---|
| A | 3 | — |
| B | 2 | A |
| C | 2 | A |
| D | 3 | A |
| E | 4 | B |
| F | 5 | C |
| G | 4 | D |
| H | 1 | C, E |
| I | 3 | G |
| J | 2 | F, H, I |
Find. (a) the unconstrained project duration and the critical path from a full forward and backward pass; (b) the shortest project duration that can be achieved when no more than two excavators are available at any time.
Approach. Do a forward pass to get every early start and early finish and hence the project duration, a backward pass to get late starts and total floats and hence the critical path; then treat part (b) as a resource-constrained problem, first proving a lower bound on the duration from the total excavator-weeks of work, then exhibiting a feasible schedule that attains it.
| Activity | Duration | ES | EF | LS | LF | Total float |
|---|---|---|---|---|---|---|
| A | 3 | 0 | 3 | 0 | 3 | 0 (critical) |
| B | 2 | 3 | 5 | 6 | 8 | 3 |
| C | 2 | 3 | 5 | 6 | 8 | 3 |
| D | 3 | 3 | 6 | 3 | 6 | 0 (critical) |
| E | 4 | 5 | 9 | 8 | 12 | 3 |
| F | 5 | 5 | 10 | 8 | 13 | 3 |
| G | 4 | 6 | 10 | 6 | 10 | 0 (critical) |
| H | 1 | 9 | 10 | 12 | 13 | 3 |
| I | 3 | 10 | 13 | 10 | 13 | 0 (critical) |
| J | 2 | 13 | 15 | 13 | 15 | 0 (critical) |
The two-week stretch is the price of the resource limit. It also destroys the original critical path as a management tool: D, G and I remain critical, but B, C, E and F have had their float consumed by the sequencing decision rather than by logic, so a delay to F now delays the project even though F carried three weeks of float in part (a). This is why resource-levelled schedules are usually re-analysed with the levelling decisions written back into the network as artificial links, so that the reported floats mean what the site team thinks they mean.
| Quantity | Value |
|---|---|
| Unconstrained project duration (CPM) | 15 weeks |
| Critical path | A – D – G – I – J |
| Activities with float | B, C, E, F, H (3 weeks total float each) |
| Peak excavator demand at early start | 3 machines (weeks 3 to 10) |
| Total work content | 29 excavator-weeks |
| Minimum duration with two excavators | 17 weeks |
| Extension caused by the resource limit | 2 weeks |