Question 4 of 6: Engineering Economics — maximum justified investment in a new surface
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Exams, May 2014 — 98-Civ-B8 Management of Construction (the paper now catalogued as 16-Civ-B8). Three hours, closed book; one of two approved calculator models permitted. Six questions of equal value (20 marks each); the rubric states that any five constitute a complete paper and that only the first five presented in the answer book will be marked. All six are worked here, because this set is a study resource rather than an exam script.
Reference texts.
Halpin, D. W. and Senior, B. A., Construction Management, 4th ed., Wiley — unit-price estimating and crew productivity, precedence diagramming with lags, labour relations, project control.
Hendrickson, C. and Au, T., Project Management for Construction, 2nd ed. — Ch. 5 (cost estimation from productivity data), Ch. 10 (scheduling with activity relationships and resource constraints).
Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide) — §6.5 Develop Schedule (leads, lags, critical path, float), §7 Cost Management.
RSMeans, Building Construction Cost Data — front matter on crew tables, daily output, labour-hours per unit and the overhead-and-profit columns.
Fraser, N. M. et al., Global Engineering Economics: Financial Decision Making for Engineers, Canadian ed., Pearson — Ch. 3–4 (present worth, uniform series, deferred annuities).
Canadian Construction Documents Committee, CCDC 2 — Stipulated Price Contract (2020) — GC 6.5 delays and extensions of time; and Society of Construction Law, Delay and Disruption Protocol, 2nd ed. — concurrency, time-slice and as-built but-for analysis.
Hinze, J. W., Construction Safety, 2nd ed.; WorkSafeBC, Occupational Health and Safety Regulation (Parts 4, 8, 11, 18, 20) and the BC Ministry of Transportation Traffic Management Manual for Work on Roadways.
Question 4: Engineering Economics — maximum justified investment in a new surface (20 marks)
Given. The do-nothing case costs $3,500 per year indefinitely; resurfacing changes that cost profile for ten years only, after which the two alternatives are identical again.
Given data — annual maintenance cost under each alternative
Period
Do nothing
With new surface
Annual saving
Years 1–5
$3,500
$650
$2,850
Years 6–10
$3,500
$1,100
$2,400
After year 10
$3,500
$3,500
nil
Interest rate
$i = 5\%$ per year
Find. The largest first cost $P$ that the resurfacing can carry and still be economically justified — that is, the present worth of the maintenance savings it produces.
Cash-flow diagram of the incremental (savings) stream. Only the ten years in which the two alternatives differ appear; the identical $3,500 per year thereafter cancels between them and needs no discounting.
Approach. Work with the incremental cash flow — the difference between doing nothing and resurfacing — so the identical post-year-10 maintenance cancels; then value the two uniform savings blocks as a five-year annuity plus a five-year annuity deferred by five years, and set the maximum justifiable investment equal to their combined present worth, the point at which net present worth is exactly zero.
Form the incremental savings stream. Comparing the resurfaced pavement against doing nothing, the annual benefit is the avoided maintenance:
$$A_1 = 3500 - 650 = \$2\,850/\text{yr (years 1--5)}, \qquad A_2 = 3500 - 1100 = \$2\,400/\text{yr (years 6--10)}.$$
From year 11 onward both alternatives cost $3,500 per year, so the difference is zero and no perpetuity term is needed — a point worth stating explicitly, because the mention of $3,500 returning after ten years tempts candidates into capitalising a stream that cancels.
Evaluate the two interest factors at 5 %. The five-year uniform-series present-worth factor and the five-year single-payment present-worth factor are
$$(P/A,\,5\%,\,5) = \frac{1 - (1.05)^{-5}}{0.05} = 4.3295, \qquad (P/F,\,5\%,\,5) = (1.05)^{-5} = 0.7835.$$
Present worth of the first block. The years 1–5 savings are an ordinary annuity valued at time zero:
$$P_1 = A_1 (P/A,\,5\%,\,5) = 2850 \times 4.3295 = \$12\,339.$$
Present worth of the deferred block. The years 6–10 savings are the same shape of annuity, but its own “time zero” sits at the end of year 5, so it must be discounted back one further five-year step:
$$P_2 = A_2 (P/A,\,5\%,\,5)(P/F,\,5\%,\,5) = 2400 \times 4.3295 \times 0.7835 = \$8\,141.$$
Forgetting the second factor — treating the $2,400 as though it also began in year 1 — is the single most common error on this question and overstates the answer by about $2,250.
Maximum justifiable investment. The resurfacing is worth doing as long as its first cost does not exceed the present worth of what it saves, so the break-even first cost is
$$P_{\max} = P_1 + P_2 = 12\,339 + 8\,141 = \boxed{\$20\,480}$$
(more precisely $20,480.43). At that price the net present worth is exactly zero and the investment earns precisely the 5 % required return; below it the resurfacing is justified, above it the money is better left in the alternative earning 5 %.
Independent cross-check by two other decompositions. Discounting the ten annual savings one at a time, $\sum_{t=1}^{5} 2850(1.05)^{-t} + \sum_{t=6}^{10} 2400(1.05)^{-t}$, reproduces $20,480.43 exactly. So does re-cutting the stream horizontally instead of vertically — a uniform $2,400 for ten years plus an extra $450 for the first five:
$$PW = 2400\,(P/A,\,5\%,\,10) + 450\,(P/A,\,5\%,\,5) = 2400(7.7217) + 450(4.3295) = \$20\,480.$$
Three routes to the same figure is the confidence the exam answer should carry.
Check: the calculation prices maintenance savings only, as the question directs. A real resurfacing decision would also weigh the salvage or residual condition of the surface at year 10, user-delay and vehicle-operating-cost savings on a high-traffic section, and the possibility that the do-nothing alternative is not in fact sustainable for ten years. It also assumes end-of-year cash flows and a constant 5 % real rate, and that the $3,500 baseline is itself stable rather than escalating — if maintenance costs escalate, the savings grow and the justifiable investment rises.