16-Civ-B8 Management of Construction · December 2018
Question 3 of 6: Project Control — expense S-curve, owner payments, overdraft and interest
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Exams, December 2018 — 16-Civ-B8, Management of Construction. Three hours, closed book; one approved Casio or Sharp calculator. Six questions are printed, each of equal value (20 marks); "any five questions constitute a complete paper" and only the first five appearing in the answer book are marked. All six are solved here so that the set works as a complete study resource.
Reference texts. Hendrickson, Project Management for Construction, 2nd ed. (network scheduling, project control, cash flow); Halpin & Senior, Construction Management, 4th ed. (arrow and precedence networks, estimating, contractor financing, bonding); RSMeans, Building Construction Cost Data (crew tables, daily output, bare-cost lines); Fraser et al., Global Engineering Economics, 5th Canadian ed. (present worth, deferred annuities); CCDC 2 (2020) Stipulated Price Contract, CCDC 3, 4 and 14, and the CCDC 220/221 bond forms (delivery methods, bonding); the British Columbia Builders Lien Act, SBC 1997 c.45 (liens and holdback).
Question 3: Project Control — expense S-curve, owner payments, overdraft and interest (20 marks)
Given. The cumulative budgeted expense of a six-month project, read off the printed S-curve, together with the commercial terms that govern how money comes back in.
Given data — cumulative budget and commercial terms
5 % of each progress claim, released with the last payment
Owner's payment delay
1 month after the month in which the work is done
Interest on borrowed money
12 % per annum, i.e. 1 % per month
Project duration
6 months of work; final payment in month 7
Find. (a) the cumulative expense curve plotted against the cumulative owner payments actually received; (b) the total interest chargeable on the money the contractor must borrow, and the overdraft limit the contractor must arrange.
Approach. Differentiate the cumulative budget to get each month's expense, apply the markup to obtain the monthly invoice, withhold the retention and shift each payment one month to obtain the receipts, then run a month-by-month cash ledger charging interest on the balance brought forward.
Recover the monthly expenses from the cumulative curve. The S-curve is cumulative, so each month's spend is the first difference:
$$e_m = C_m - C_{m-1}$$
which gives $29,000, $11,000, $14,000, $32,000, $26,000 and $15,000 for months 1 to 6, summing to $127,000. The shape is the ordinary S: a heavy mobilisation month, a quiet pair of months while the work is set up, the steep central months 4 and 5 when production peaks, and a tapering finish.
Convert expense to the value of work billed. The contractor claims cost plus a 10 % markup, so the monthly invoice is
$$b_m = e_m\,(1+0.10)$$
giving $31,900, $12,100, $15,400, $35,200, $28,600 and $16,500. The contract value is therefore
$$V = 127{,}000 \times 1.10 = \$139{,}700$$
of which $12,700 is the gross markup the contractor expects to keep before financing costs.
Apply the retention and the payment delay. The owner holds back 5 % of every claim and pays the remaining 95 % one month in arrears, so the cash arriving in month $m$ is
$$r_m = 0.95\,b_{m-1}$$
The accumulated holdback,
$$R = 0.05 \times 139{,}700 = \$6{,}985$$
is released with the final payment. Month 1 therefore brings in nothing at all, months 2 to 6 bring in $30,305, $11,495, $14,630, $33,440 and $27,170, and month 7 brings $15,675 of final progress payment plus the $6,985 holdback, that is $22,660. The receipts total $139,700, matching the contract value exactly — the check that the retention has been released and nothing has been double-counted.
Figure 3.1 — (a) the required plot: cumulative expenses (the given budget S-curve), the cumulative value of work billed at cost plus 10 % markup, and the cumulative owner payments actually received. The vertical gap between the expense curve and the receipt curve is the money the contractor must finance; it is widest at the end of month 4.
Run the cash ledger. Interest is charged on the balance brought forward from the previous month, and then the month's expenses go out and the month's receipt comes in:
$$B_m = B_{m-1} - I_m - e_m + r_m,\qquad I_m = i\,\max\left(0,\,-B_{m-1}\right),\qquad i = \frac{12\%}{12} = 1\%\ \text{per month}$$
where the interest term applies only while the balance is negative. Month 1 opens at zero, so no interest is charged; the balance closes at −$29,000. Month 2 is charged 1 % of $29,000, that is $290, spends $11,000 and receives $30,305, closing at −$9,985. Continuing month by month produces the ledger below.
Contractor's cash ledger — all figures in dollars
Month
Balance b/f
Interest at 1 %
Expense
Owner payment
Balance c/f
1
0.00
0.00
29,000
0
−29,000.00
2
−29,000.00
290.00
11,000
30,305.00
−9,985.00
3
−9,985.00
99.85
14,000
11,495.00
−12,589.85
4
−12,589.85
125.90
32,000
14,630.00
−30,085.75
5
−30,085.75
300.86
26,000
33,440.00
−22,946.61
6
−22,946.61
229.47
15,000
27,170.00
−11,006.07
7
−11,006.07
110.06
0
22,660.00
+11,543.87
Total
—
1,156.13
127,000
139,700.00
—
(b) Interest chargeable and the overdraft limit. Summing the interest column,
$$\sum I = 290.00+99.85+125.90+300.86+229.47+110.06=\boxed{\$1{,}156.13}$$
(The ledger is carried at full precision and only displayed to the cent, so adding the six rounded charges exactly as printed gives $1,156.14; the exact total is $1,156.13 and that is the figure the closing identity below uses. A one-cent rounding residue in a compounded column is normal and is not an error — but it is worth stating rather than leaving a reader to find it.)
The deepest point of the ledger, at the end of month 4, sets the facility the contractor must have in place:
$$\boxed{\text{Overdraft limit required} \approx \$30{,}100}$$
The ledger proves itself. Receipts exceed expenses by exactly the markup, $12,700, so the balance standing after the final payment must equal the markup less the financing cost:
$$11{,}543.87 = 12{,}700.00 - 1{,}156.13 \;\checkmark$$
Financing has therefore consumed 9.1 % of the gross markup, leaving a net profit of $11,543.87 on a $139,700 contract — about 8.3 % of the contract value.
Interpret the result for practice. Two features of the profile matter more than the arithmetic. The peak overdraft of $30,086 occurs at the end of month 4, not at the end of the job, because month 4 is the heaviest spending month while the receipt arriving in it is only 95 % of the very light month-3 invoice; the contractor must arrange the facility before that month, not discover the need during it. And the 5 % holdback does not reduce what the contractor is ultimately paid — it only delays it — yet that delay costs real money: re-running the same ledger with no retention gives $977.20 of interest and a $29,000 peak, so the holdback adds about $179 of interest and $1,086 to the required facility.
Figure 3.2 — closing cash balance at the end of each month. The deepest bar, −$30,085.75 at the end of month 4, is the overdraft limit that must be arranged; the account only turns positive when the holdback is released in month 7.
Check: assumptions stated explicitly. (i) The printed curve is read as the contractor's budgeted expense, so the markup is added to it to obtain what the owner is billed; the alternative reading, in which the curve is already the contract value, would make the expenses $127,000/1.10 and reduce every figure by about 9 %. The question's own wording, "the S-curve of expenses against the expected owner payments", supports the reading used. (ii) Expenses are treated as paid at the end of each month and interest is charged on the balance brought forward, which is the convention that makes the closing balance equal markup less interest exactly. (iii) The final payment, including release of the holdback, is taken in month 7, one month after the last month of work, consistent with the stated one-month delay.