NivaarExam PrepOfficial exam papers ↗

16-Civ-B8 Management of Construction · May 2018

Question 2 of 6: Estimating — trench excavation, footing forms and footing concrete

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Exams, May 2018 — 16-Civ-B8, Management of Construction. Three hours, closed book; one approved Casio or Sharp calculator. Six questions are printed, each worth 20 marks; "any five questions constitute a complete paper" and only the first five appearing in the answer book are marked. All six are solved here so the set works as a complete study resource.

Reference texts. Hendrickson, Project Management for Construction, 2nd ed. (scheduling, cost control, earned value); Halpin & Senior, Construction Management, 4th ed. (precedence networks, estimating, contractor cash flow, bonding); RSMeans, Building Construction Cost Data (crew daily output and bare-cost lines); Fraser et al., Global Engineering Economics, 5th Canadian ed. (present worth, unequal lives); CCDC 2 (2020) Stipulated Price Contract and the MMCD tendering documents (bid packages, bonds, holdback); Hinze, Construction Safety, 2nd ed. and the WorkSafeBC Occupational Health and Safety Regulation (site safety practice in Canada).

Question 2: Estimating — trench excavation, footing forms and footing concrete (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. The take-off data, the trench section and the two RSMeans lines reproduced on the paper.

ItemValue
Overall plan (centre-line)80 m wide × 70 m deep (50 m upper block + 20 m bottom strip)
Re-entrant bay in the top edge25 m deep × 20 m wide (scaled)
Internal wallsone 80 m divider; one 25 m spine
Trench width / depth1.35 m / 1.05 m
Footing0.75 m wide × 0.45 m thick
Working day8 hours
Excavation line (0.29 m3 backhoe, 0.3–1.2 m deep)115 m3/day; labour 3.02, equipment 1.74, total 4.76 per m3
Forms in place, continuous wall footings — 2 uses40.88 m2/day; material 7.00, labour 17.70, equipment 0.67, total 25.37 per m2
Forms — 1 use (for comparison)34.84 m2/day; total 34.59 per m2
Concrete production / cost5 m3/h; 20,000 dollars lump, material included

Find. For each of the three tasks — excavation, formwork and concrete — the quantity in its own unit, the duration in working days at the stated outputs, and the bare cost; then the estimate total.

[Figure not reproduced: Figure 2.1 — foundation plan redrawn to wall centre-lines. The trench follows every heavy line: the external outline, the 80 m divider and the 25 m spine between the two upper rooms. See the official exam paper.]

Ground levelConcrete footing200 mm wall300 mm750 mm300 mmtrench width 1350 mm600 mm450 mm1050 mm
Figure 2.2 — trench cross-section. The 1.35 m trench carries a 0.75 m wide by 0.45 m thick footing with 300 mm of working space each side; the 200 mm wall above it is excluded from this estimate.

Approach. Measure one centre-line length for the whole trench, then price the three tasks off that single length — volume for excavation, two-sided contact area for the forms, and footing volume for the concrete — taking durations from the RSMeans daily outputs and the stated concrete production rate.

  1. Measure the trench centre-line once. Every quantity in this question is a constant cross-section multiplied by the same length, so the length is measured first and used three times. The external outline is a 80 m × 70 m rectangle with a bay cut into the top edge; a re-entrant bay does not change the perimeter of the top run (\(30 + 20 + 30 = 80\) m) but does add the two 25 m returns:$$L_{\text{ext}} = 2(80 + 70) + 2(25) = 300 + 50 = 350 \text{ m}$$Adding the internal walls — the full-width divider and the spine from the divider up to the soffit of the bay, \(50 - 25 = 25\) m:$$L = 350 + 80 + 25 = \boxed{455 \text{ m of trench}}$$
  2. Excavation quantity. The trench is \(0.30 + 0.75 + 0.30 = 1.35\) m wide and \(0.600 + 0.450 = 1.05\) m deep, so$$V_{\text{exc}} = L \times w \times d = 455 \times 1.35 \times 1.05 = \boxed{645 \text{ m}^3} \;(644.96 \text{ m}^3)$$The depth falls inside the 0.3–1.2 m band of the RSMeans line, so that line may be used without adjustment.
  3. Excavation duration and bare cost. The 0.29 m3 backhoe crew produces 115 m3 per eight-hour day, and the bare cost is the labour plus equipment columns (there is no material in an excavation line):$$t_{\text{exc}} = \frac{644.96}{115} = 5.61 \text{ days},\qquad C_{\text{exc}} = 644.96 \times \$4.76 = \boxed{\$3{,}070.02}$$Splitting that between the columns gives labour \(644.96 \times \$3.02 = \$1{,}947.79\) and equipment \(644.96 \times \$1.74 = \$1{,}122.23\), which add back to the total — the arithmetic check on a Means line. Allow six working days on the programme.
  4. Formwork quantity. The forms are the two vertical faces of the footing over its full 450 mm depth; the wall forms are explicitly excluded and the footing has no end forms of consequence on a continuous run:$$A_{\text{form}} = 2 \times 0.45 \times 455 = \boxed{409.5 \text{ m}^2 \text{ of contact area}}$$
  5. Formwork duration and bare cost. Because the material is used twice, the "2 use" line applies — the material column drops from 12.80 to 7.00 per m2 since each panel is amortised over two pours, and the crew output rises from 34.84 to 40.88 m2 per day because the second use needs no fabrication:$$t_{\text{form}} = \frac{409.5}{40.88} = 10.02 \text{ days},\qquad C_{\text{form}} = 409.5 \times \$25.37 = \boxed{\$10{,}389.02}$$Pricing the same area on the single-use line would cost \(409.5 \times \$34.59 = \$14{,}164.61\), so re-using the material saves \(\$3{,}775.59\) — about 27 percent of the formwork bill, and the reason the question specifies two uses.
  6. Concrete quantity, duration and cost. Only the footing is concreted:$$V_{\text{con}} = 455 \times 0.75 \times 0.45 = \boxed{153.6 \text{ m}^3}$$At 5 m3 per hour over an eight-hour day the placing rate is 40 m3 per day, so$$t_{\text{con}} = \frac{153.56}{40} = 3.84 \text{ days}$$The concreting cost is given as a lump sum of \(\$20{,}000\) with material included, which works out at \(\$20{,}000 / 153.56 = \$130.24\) per m3 — a plausible supplied-and-placed rate, which is the sanity check that the lump sum is being read correctly.
  7. Assemble the estimate. Adding the three bare costs,$$C_{\text{total}} = \$3{,}070.02 + \$10{,}389.02 + \$20{,}000 = \boxed{\$33{,}459.04}$$and, if the three tasks are run strictly in sequence, \(5.61 + 10.02 + 3.84 = 19.5\) working days, say twenty. In practice the three would be lapped along the trench, so the sequential figure is an upper bound on the foundation programme.
Foundation estimate — quantity, duration and bare cost (455 m of trench)
TaskQuantityOutput usedDuration (days)Bare cost (CAD)
Trench excavation645.0 m3115 m3/day5.613,070.02
Footing formwork (2 uses)409.5 m240.88 m2/day10.0210,389.02
Footing concrete153.6 m340 m3/day3.8420,000.00
Total——19.46 (if sequential)33,459.04

Check: two readings of the plan must be stated, as the exam invites. (i) The width of the re-entrant bay is the one dimension the drawing does not label. Scaling the printed plan gives two upper rooms of about 30 m each, so a 20 m bay is adopted. The result is insensitive to it: whatever the split, the three horizontal runs across the top still project to 80 m in total, so the bay width does not enter the centre-line girth. Only the 25 m dimension matters, and it is printed on the drawing. (ii) The plan dimensions are taken as wall centre-lines. If they were instead the outside faces of the 1.35 m trench, the centre-line girth would shorten by about \(4 \times 1.35 = 5.4\) m, some 1.2 percent. At the combined rate of \(\$29.58\) per metre for excavation and forms that is roughly \(\$160\) on a \(\$33{,}459\) estimate — worth stating, but it changes no decision.