NivaarExam PrepOfficial exam papers ↗

16-Civ-B8 Management of Construction · May 2018

Question 5 of 6: Cash Flow — the BCWS curve, and the interest on a contractor's overdraft

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Exams, May 2018 — 16-Civ-B8, Management of Construction. Three hours, closed book; one approved Casio or Sharp calculator. Six questions are printed, each worth 20 marks; "any five questions constitute a complete paper" and only the first five appearing in the answer book are marked. All six are solved here so the set works as a complete study resource.

Reference texts. Hendrickson, Project Management for Construction, 2nd ed. (scheduling, cost control, earned value); Halpin & Senior, Construction Management, 4th ed. (precedence networks, estimating, contractor cash flow, bonding); RSMeans, Building Construction Cost Data (crew daily output and bare-cost lines); Fraser et al., Global Engineering Economics, 5th Canadian ed. (present worth, unequal lives); CCDC 2 (2020) Stipulated Price Contract and the MMCD tendering documents (bid packages, bonds, holdback); Hinze, Construction Safety, 2nd ed. and the WorkSafeBC Occupational Health and Safety Regulation (site safety practice in Canada).

Question 5: Cash Flow — the BCWS curve, and the interest on a contractor's overdraft (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Part (a) — the BCWS curve. BCWS, the budgeted cost of work scheduled (called planned value in current PMBOK usage), is the time-phased baseline budget: the project budget spread over the programme according to when each activity is scheduled to be performed. It is built by loading every activity in the schedule with its budgeted cost, distributing that cost across the activity's duration, and accumulating the result week by week. Plotted cumulatively against time it is the familiar S-curve of Figure 5.1: flat at the start while the site mobilises and only a few low-value activities are open; steep through the middle third, when the maximum number of trades are working concurrently and the expensive structural and mechanical activities run; and flattening again at the end, when the remaining work is finishing, commissioning and deficiency correction, all of which consume calendar time out of proportion to their value. Its purposes are threefold. It is the baseline against which the two other earned-value curves are read — schedule variance \(SV = BCWP - BCWS\) and cost variance \(CV = BCWP - ACWP\), so a project running behind shows its BCWP curve below the BCWS curve. It is the owner's cash-flow forecast, since progress certificates track the work performed. And it is the contractor's own planning tool, because the slope of the curve at any date is the rate at which resources and money must be available. A BCWS curve that is nearly straight, or that rises steeply from day one, is normally a sign that the cost loading has been spread evenly by default rather than derived from the schedule.

020406080100020406080100Percent of planned project durationCumulative budgeted cost (percent)BCWS (planned value)slow start: mobilisationsteep middle: peak resourcestail: finishing and commissioning
Figure 5.1 — typical BCWS (planned value) curve: cumulative budgeted cost against time, showing the characteristic S shape.

Part (b) — Given. Monthly invoices for work performed, a one-month payment lag, five percent retention held on each certificate and released with the final payment, and a one percent per month financing rate on the contractor's overdraft.

End of monthInvoice (CAD)Retention held at 5 percent (CAD)Payment received (CAD)
140,0002,000—
2110,0005,50038,000
3160,0008,000104,500
4460,00023,000152,000
5540,00027,000437,000
6710,000released513,000
7——775,500
Total2,020,000—2,020,000

Find. The payment received in each month, the cumulative cost and income curves, the peak overdraft, and the total interest charged on the money the contractor must borrow.

Approach. Build the receipt column from the invoice column by applying the one-month lag and the retention, then roll the overdraft forward month by month, charging one percent on the balance carried into each month before that month's spending and receipts are applied.

  1. Part (b), step 1 — convert invoices into receipts. The invoice raised at the end of month \(m\) is paid at the end of month \(m+1\) less five percent, so$$R_{m+1} = 0.95\,I_m$$which gives \(38{,}000\), \(104{,}500\), \(152{,}000\), \(437{,}000\) and \(513{,}000\) at the ends of months 2 to 6. The retention accumulated on the first five invoices is$$\textstyle\sum 0.05\,I_m = 2{,}000 + 5{,}500 + 8{,}000 + 23{,}000 + 27{,}000 = \$65{,}500$$and it is released with the final payment, so month 7 brings \(710{,}000 + 65{,}500 = \$775{,}500\). The receipts total \(\$2{,}020{,}000\), exactly the invoice total — retention delays money, it does not remove it, and that identity is the first check on the table.
  2. Part (b), step 2 — set up the overdraft recursion. The contractor pays for the work as it is done and is reimbursed a month later, so the shortfall is carried on an overdraft. Charging interest on the balance brought into each month,$$N_m = N_{m-1}(1 + i) + E_m - R_m, \qquad i = 0.01 \text{ per month}$$where \(E_m\) is the cost incurred in month \(m\) and \(R_m\) the cash received. With no separate cost data on the paper, the invoiced value is taken as the cost of the work performed in that month, which is the standard reading of this question.
  3. Part (b), step 3 — roll the overdraft forward. Month 1 carries no opening balance, so no interest, and closes at \(\$40{,}000\). Month 2 is charged \(0.01 \times 40{,}000 = \$400\) and closes at \(40{,}000 + 400 + 110{,}000 - 38{,}000 = \$112{,}400\); month 3 at \(0.01 \times 112{,}400 = \$1{,}124.00\) closing at \(\$169{,}024.00\); and so on through the table below. The overdraft peaks at the end of month 6:$$N_{\max} = \boxed{\$789{,}366.40 \text{ at the end of month 6}}$$which is 39 percent of the contract value — the number that sizes the contractor's line of credit.
  4. Part (b), step 4 — total the interest. Adding the monthly charges,$$\textstyle\sum I_m = 400 + 1{,}124.00 + 1{,}690.24 + 4{,}787.14 + 5{,}865.01 + 7{,}893.66 = \boxed{\$21{,}760.06}$$The six charges above are each rounded to the cent and so add to \(\$21{,}760.05\) as printed; the boxed figure is the total of the unrounded charges, and it is that figure the closing-balance identity must reproduce. Because the receipts exactly repay the costs, the balance left standing after the month-7 payment must be the accumulated financing charge and nothing else — and it is, at \(\$21{,}760.06\). That identity is the self-check on the whole recursion. The charge is 1.08 percent of the contract value, which is what the contractor must carry in the markup purely to finance the payment lag and the retention.
050010001500200001234567End of monthCumulative amount (thousands of dollars)Cumulative costCumulative incomeshaded gap = overdraft carried
Figure 5.2 — cumulative cost and cumulative income. The vertical gap between the curves is the overdraft the contractor must finance; it is widest at the end of month 6 and closes only when the retention is released in month 7.
Overdraft roll-forward at 1 percent per month (CAD)
MonthCost incurredCash receivedInterest chargedClosing overdraft
140,000—0.0040,000.00
2110,00038,000400.00112,400.00
3160,000104,5001,124.00169,024.00
4460,000152,0001,690.24478,714.24
5540,000437,0004,787.14586,501.38
6710,000513,0005,865.01789,366.40
7—775,5007,893.6621,760.06
Total2,020,0002,020,00021,760.0621,760.06 (= the interest)

Check: the interest convention and the cost basis. Interest is charged here on the balance brought forward into each month, which is the convention that makes the closing balance equal the total interest exactly. Charging instead on the closing balance of each month raises the total only to \(\$21{,}977.66\); the convention should be stated on an exam script either way. The second assumption is that the invoiced value equals the cost of the work in that month, since the paper gives no separate cost column. If the invoices instead carried a ten percent markup, the costs would be about nine percent lower, the overdraft would peak at \(\$603{,}366\) and the interest would fall to \(\$17{,}536\) — the method is unchanged.