16-Civ-B8 Management of Construction · December 2019
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Paper format. National Exams, December 2019 — 16-Civ-B8, Management of Construction. Three hours, closed book, one of two approved calculators (Casio or Sharp). Six questions of equal value; any five constitute a complete paper and only the first five appearing in the answer book are marked. All six are worked here, because the set is a study resource rather than a sitting.
Reference texts. Hendrickson, Project Management for Construction, 2nd ed. (network scheduling, PERT, project control); Halpin & Senior, Construction Management, 4th ed. (precedence networks with lags, estimating, tendering, safety); RSMeans, Building Construction Cost Data (crew composition, daily output, masonry lines); Fraser et al., Global Engineering Economics, 5th Canadian ed. (present worth, annual worth, benefit–cost analysis of public projects); CCDC 2 (2020) Stipulated Price Contract with the CCDC 220/221 bond forms, and CCDC 23 A Guide to Calling Bids and Awarding Contracts (tendering practice); the Society of Construction Law Delay and Disruption Protocol, 2nd ed., and AACE International RP 29R-03 (forensic schedule analysis); Hinze, Construction Safety, 2nd ed., with the WorkSafeBC Occupational Health and Safety Regulation Part 20 (Construction) and Ontario O. Reg. 213/91.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. Two brick faces of one house, dimensioned on the page-3 drawing, and a table of brick coverage rates and mason production rates for three brick sizes. The crew is four brick masons and two labourers; openings are to be ignored, and the coverage rates already include a waste factor.
| Item | Value |
|---|---|
| Front face width | 22′-4″ = 22.333 ft |
| Front face height to eave | 10′-6″ = 10.5 ft |
| Gable height, eave to ridge | 6′-6″ = 6.5 ft (17 ft overall) |
| Wall carried below the eave-line datum | 2 ft deep over the last 9 ft of the front face |
| Side wall | 59 ft long × 10.5 ft high |
| Brick coverage (waste included) | Standard 7.4/SF; King 5.7/SF; Jumbo 3.3/SF |
| Production per brick mason | Standard 400/day; King 385/day; Jumbo 360/day |
| Crew | 4 brick masons + 2 labourers, 8-hour shift |
Find. The wall surface area to be bricked, the number of bricks required for each of the three brick sizes, and the crew duration for each.
[Figure not reproduced: Figure 5.1 — the two faces to be bricked, redrawn flat from the page-3 elevation. The front face resolves into a rectangle, a gable triangle and the triangular strip carried below the eave-line datum; the side wall is a plain rectangle because the eave line is level. The two elevations are dra. See the official exam paper.]
Approach. Decompose each face into rectangles and triangles, take the gross area with the openings ignored as instructed, convert area to brick count with the coverage rate, and convert brick count to duration with the crew's daily output — noting that the production rate is stated per mason, so it must be multiplied by the four masons and not by the six-person crew.
$$A_{\text{rect}}=22.333\times10.5=234.50\ \text{SF}$$
The gable above it is a triangle on the same base, 6′-6″ high, which the 17′ overall dimension confirms since $10.5+6.5=17$:
$$A_{\text{gable}}=\tfrac12\times22.333\times6.5=72.58\ \text{SF}$$
Below the eave-line datum the wall is carried down to 2′ over the last 9′ of its length, a right triangle:
$$A_{\text{strip}}=\tfrac12\times9\times2=9.00\ \text{SF}$$
so the front face totals $234.50+72.58+9.00=316.08$ SF.
$$A_{\text{side}}=59\times10.5=619.50\ \text{SF}$$
$$A=316.08+619.50=\boxed{935.58\ \text{SF}}$$
The instruction to ignore openings means this gross figure is the take-off quantity; the two windows and the door drawn on the elevation are deliberately not deducted. That is also why the coverage rates carry a waste allowance — the estimate is made deliberately slightly generous rather than exactly right.
$$N_{\text{Standard}}=935.58\times7.4=6{,}923.3\ \Rightarrow\ \boxed{6{,}924\ \text{bricks}}$$
$$N_{\text{King}}=935.58\times5.7=5{,}332.8\ \Rightarrow\ \boxed{5{,}333\ \text{bricks}}$$
$$N_{\text{Jumbo}}=935.58\times3.3=3{,}087.4\ \Rightarrow\ \boxed{3{,}088\ \text{bricks}}$$
In practice these would be ordered by the cube or by the thousand and rounded up again to the supplier's packing unit.
$$Q_{\text{crew}}=4\times400=1{,}600;\quad 4\times385=1{,}540;\quad 4\times360=1{,}440\ \text{bricks/day}$$
and the duration follows as $t=N/Q_{\text{crew}}$:
$$t_{\text{Standard}}=\frac{6{,}923.3}{1{,}600}=\boxed{4.33\ \text{days}}\quad\left(5\ \text{working days}\right)$$
$$t_{\text{King}}=\frac{5{,}332.8}{1{,}540}=\boxed{3.46\ \text{days}}\quad\left(4\ \text{working days}\right)$$
$$t_{\text{Jumbo}}=\frac{3{,}087.4}{1{,}440}=\boxed{2.14\ \text{days}}\quad\left(3\ \text{working days}\right)$$
$$H=t\times48=207.7,\quad166.2,\quad102.9\ \text{crew-hours}$$
for Standard, King and Jumbo respectively. Multiplying these by the assembled crew rate — four mason hours and two labourer hours per six crew-hours, at the applicable collective-agreement or prevailing wage — gives the labour cost, to which the delivered brick and mortar cost is added.
Check: assumptions stated explicitly. (i) The 2′ strip below the eave-line datum is read as a triangular wedge running from zero at 9′ in to the full 2′ at the right-hand corner, as drawn; if it were instead a full 9′ × 2′ rectangle the front face would gain a further 9.00 SF, raising the total to 944.58 SF and the Standard-brick duration from 4.33 to 4.37 days — under 1 %, so the recommendation is unaffected either way. (ii) The side wall is taken as rectangular to the eave line, which follows from the roof being gabled on the front face; if the far end were also gabled and were included, another 72.58 SF would have to be added, but the question asks only for the front face and one side. (iii) An eight-hour shift is assumed for the crew-hour conversion; a ten-hour shift would compress the calendar duration proportionally but leave the brick quantity, and hence the material cost, unchanged. (iv) Openings are ignored as instructed, so the take-off is gross; a real estimate would deduct openings over about 10 SF and add for the return jambs and the sills.
| Quantity | Standard | King | Jumbo |
|---|---|---|---|
| Wall surface area (both faces) | 935.58 SF (front 316.08 SF + side 619.50 SF) | ||
| Bricks required (waste included) | 6,924 | 5,333 | 3,088 |
| Crew output (4 masons) | 1,600/day | 1,540/day | 1,440/day |
| Equivalent wall area per crew-day | 216.2 SF | 270.2 SF | 436.4 SF |
| Duration | 4.33 days (5 shifts) | 3.46 days (4 shifts) | 2.14 days (3 shifts) |
| Crew-hours (6 workers × 8 h) | 207.7 | 166.2 | 102.9 |