NivaarExam PrepOfficial exam papers ↗

11-CS-2 Engineering Communications · May 2015

Question 5 of 7: Risk Management and Chemical Risk Assessment

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams — May 2015 — 11-CS-2 Engineering in Society: Health and Safety. Closed book; approved calculator permitted. Any five of the seven questions constitute a complete paper; all questions are of equal value. Answers are written in point form but fully, as instructed. Complete answers to all seven questions follow.

Question 5: Risk Management and Chemical Risk Assessment (20 marks: 6/7/7)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

(i) Components of the Risk-Management Process

(ii) Steps in Chemical Risk Assessment

  1. Identify the chemicals and their hazards — inventory, SDS, hazard classification.
  2. Identify exposure scenarios — who is exposed, tasks, routes (inhalation/skin/ingestion), frequency and duration.
  3. Assess exposure — measure or estimate airborne concentrations/skin contact and compare against occupational exposure limits (TWA/STEL/ceiling).
  4. Characterize the risk — combine hazard severity with exposure likelihood; determine whether risk is acceptable.
  5. Determine controls (hierarchy) and re-assess residual risk.
  6. Document, communicate and review (after change or periodically).

(iii) Risk Reduction in Chemical Processing Plants