22-Elec-B7 Power Systems Engineering · December 2016
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Paper format. National Exams, December 2016 — 07-Elec-B7 Power Systems Engineering. Open-book, 3 hours duration. Seven problems are printed; any five constitute a complete paper, only the first five appearing in the answer book are marked, and all questions are of equal value (20 points each). All seven are solved in full below, because this set is a study resource rather than a timed sitting.
Reference texts. This exam code follows M. E. El-Hawary, Electrical Power Systems: Design and Analysis (IEEE Press) — the notation is his throughout: the “cantilever” transformer equivalent of Problem 3, the two-reaction salient-pole construction of Problem 2, the ABCD two-port of Problem 1 and the sequence-network fault reduction of Problem 6. Corroborating references: J. D. Glover, M. S. Sarma and T. J. Overbye, Power System Analysis and Design, 6th ed. (ch. 3 transformers, ch. 4–5 transmission lines, ch. 6 power flow, ch. 7–9 faults and symmetrical components, ch. 11 transient stability); J. J. Grainger and W. D. Stevenson, Power System Analysis; and S. J. Chapman, Electric Machinery Fundamentals, 5th ed., for the machine and transformer chapters. Canadian practice references where grounding and protection are discussed: CSA C22.1 Canadian Electrical Code, Part I, CSA C22.2 and the IEEE C62 / IEEE 142 (Green Book) series on system grounding.
Check: four judgement calls carried through the solutions, all recorded here rather than hedged in the answers.
(i) Problem 1 does not state a frequency. Parts (c) and (d) need one, and the paper is a Canadian national exam, so 60 Hz is used throughout — consistent with the 60 Hz stated in Problems 3 and 7. At 50 Hz the capacitance and surge impedance are unchanged (they do not involve frequency) and only the propagation constant of part (d) rescales by 5/6.
(ii) Problem 2 prints “neglecting armature reaction”. Armature reaction is precisely what the direct- and quadrature-axis reactances represent, so the phrase is read as its standard counterpart, neglecting armature resistance — the only reading under which the two given reactances can be used at all.
(iii) Problem 6 prints a part label “c-” with no question text. The five parts that do carry text (a, b, d, e, f) are marked 4 points each and total the 20 points the paper allots to every problem, so nothing is missing from the assessment; the sequence networks that the empty label most plausibly asked for are drawn anyway.
(iv) Problem 5 gives no reactance between buses 2 and 3. Figure (3) confirms the topology: bus 3 hangs radially off bus 1 through the j0.12 pu line, and the only other tie is line 1–2.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given.
| Quantity | Symbol | Value |
|---|---|---|
| Base rating and voltage | $S_b,\ V_b$ | 5000 kVA, 4160 V (three-phase) |
| Utility source, positive and negative | $X_+=X_-$ | 0.06 pu |
| Utility source, zero sequence | $X_0$ | 0.04 pu |
| Added generator, positive and negative | $X_+=X_-$ | 0.15 pu |
| Added generator, zero sequence | $X_0$ | 0.10 pu (generator is ungrounded) |
| Grounding resistor in the utility transformer neutral | $R_n$ | $6\ \Omega$ |
| Pre-fault bus voltage | $E$ | 1.0 pu |
Find. Why systems are grounded at all; then the phase-A line-to-ground fault current on the plant bus for three successive configurations — utility alone, utility plus an ungrounded generator, and utility plus generator with a resistor in the utility transformer neutral — together with that resistor expressed in per unit.
Part (a) — why systems are grounded. Connecting the system neutral to earth, directly or through an impedance, serves four distinct purposes and no single one of them is the whole answer. The first is control of overvoltage. An ungrounded system has no reference to earth except its own distributed capacitance, so a single line-to-ground fault does not draw useful current but does displace the neutral by a full phase voltage, raising the two healthy phases to line-to-line voltage; worse, an intermittent (arcing) ground fault can resonate with that capacitance and produce transient overvoltages of five to six times normal, puncturing insulation anywhere on the system. Grounding pins the neutral and caps the healthy-phase rise at about 1.25 times normal for an effectively grounded system.
The second purpose is reliable fault detection and clearing. Ground faults are by far the commonest fault type, and unless the system is grounded there is no return path to give the overcurrent or ground-fault relays anything to measure. A grounded system turns an insulation failure into a current large enough to be selectively detected and cleared before it escalates into a phase-to-phase or three-phase fault. The third is personnel and equipment safety: bonding and grounding hold exposed metalwork near earth potential, limiting touch and step voltages, which is the basis of the equipment-grounding and bonding requirements of CSA C22.1, the Canadian Electrical Code, Part I (Section 10), and of CSA C22.3 No. 1 for outdoor distribution. The fourth is a defined path for lightning and switching surges, letting surge arresters discharge to a solid reference and allowing arresters of lower rating — and therefore lower protective level — to be used.
The choice of grounding method then trades these against each other, and part (f) of this question is a direct illustration. Solid grounding gives the best overvoltage control and the simplest relaying but the largest ground-fault current, with the attendant arc-flash energy and equipment damage. Low-resistance grounding, as introduced here, limits the current to a few hundred amperes — enough for selective relaying, small enough to avoid burning laminations and to cut incident energy sharply. High-resistance grounding limits it to a few amperes so the plant can keep running on the first fault, which is why it is common in continuous-process industry; and reactance or resonant (Petersen coil) grounding occupies the ground between.
Approach. For a single line-to-ground fault the three sequence networks are connected in series, so $I_{a1}=I_{a2}=I_{a0}=E/(Z_1+Z_2+Z_0)$ and $I_f=I_a=3I_{a1}$. The work in each configuration is therefore only to build the three sequence impedances correctly — and the decisive reading is which sources are admitted to the zero-sequence network.
| Quantity | Symbol | Result |
|---|---|---|
| Base impedance and current | $Z_b,\ I_b$ | $3.4611\ \Omega$, 693.93 A |
| (b) Utility alone | $X_1,X_2,X_0$ | 0.06, 0.06, 0.04 pu |
| (b) SLG fault current | $I_f$ | 18.75 pu = 13 011 A |
| (d) Utility + ungrounded generator | $X_1,X_2,X_0$ | 0.042857, 0.042857, 0.04 pu |
| (d) SLG fault current | $I_f$ | 23.86 pu = 16 560 A |
| (e) Neutral resistor in per unit | $R_n$ | 1.7335 pu (3R = 5.2006 pu) |
| (f) SLG fault current, resistance grounded | $I_f$ | 0.577 pu = 400.2 A |
| Three-phase fault for comparison, case (b) | $I_{3\phi}$ | 16.67 pu = 11 566 A |