NivaarExam PrepOfficial exam papers ↗

18-Env-A3 Geotechnical and Hydrogeological Engineering · December 2016

Question 2 of 6: Flow Net and Uplift Force on a Tunnel in an Embankment

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams — December 2016 — 04-Env-A3 / Geotechnical & Hydrogeological Engineering. 3 hours duration; open book exam, any non-communicating calculator permitted. FIVE (5) questions constitute a complete exam paper (the first five as they appear in the answer book are marked, 20 marks each, 100 marks total); all six printed questions are solved below for completeness.

Reference texts. Braja M. Das, Principles of Geotechnical Engineering (9th ed.) — weight–volume relations, permeability, seepage/flow nets, stress distribution, consolidation and lateral earth pressure chapters; Craig & Knappett, Craig's Soil Mechanics (8th ed.) — cross-reference for seepage, flow nets and anchored sheet-pile wall design.

Question 2: Flow Net and Uplift Force on a Tunnel in an Embankment (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. The embankment cross-section (Figure 1): a 30 m tall, 80 m wide (toe-to-toe) trapezoidal fill with a 25 m wide crest, carrying a 20 m wide by 10 m tall tunnel centred in the base (10 m below crest, resting on rock at mid-height). A river holds the upstream face wetted to $h=25$ m and the downstream face wetted to $h=15$ m (both measured above the impermeable rock base).

Given data
QuantitySymbolValue
Equivalent hydraulic conductivity$k$$8\times10^{-5}$ cm/s $=8\times10^{-7}$ m/s
Upstream (high) head$h_1$25 m
Downstream (low) head$h_2$15 m
Total head loss$\Delta H$10 m

Find. (a) the flow net for the worst-case (highest sustained differential-head) condition; (b) the uplift force per unit length of tunnel acting on its base.

[Figure not reproduced: Figure 1 (redrawn) with the solved flow net superimposed — equipotentials (blue, head in m) and flow lines (red). See the official exam paper.]

Approach. "Worst case" means treating the embankment as fully saturated up to crest level rather than relying on an uncertain internal phreatic surface — the conservative, maximum-uplift condition. Laplace's equation $\nabla^2h=0$ then governs head $h(x,z)$ in the soil, with $h=25$ m fixed on the wetted upstream face, $h=15$ m fixed on the wetted downstream face, and no-flow (zero head-gradient) on the rock base, the dry crest/slope surfaces, and the impermeable tunnel lining. Rather than hand-sketch curvilinear squares, the same boundary-value problem is solved numerically (finite-difference relaxation on a 0.5 m grid) — this is exactly a flow net, just read off a computed head field instead of a ruler; $N_f/N_d$ and the uplift both fall out of it directly.

  1. Set up the seepage domain and boundary conditions. With the base spanning $x=0$ (upstream toe) to $x=80$ m (downstream toe) and the crest centred at $x=27.5$–$52.5$ m, the tunnel occupies $x=30$–$50$ m, $z=10$–$20$ m. Fixed heads of 25 m and 15 m apply on the wetted portions of the two side slopes (below their respective water lines); every other boundary (rock base, dry slope/crest, tunnel lining) is no-flow.
  2. Solve Laplace's equation for the head field. Gauss–Seidel relaxation on the masked grid (dry region and tunnel void excluded) converges to the head $h(x,z)$ shown by the blue equipotentials above; the red flow lines are the corresponding orthogonal streamlines. Reading off the number of flow channels and equipotential drops gives an equivalent $N_f/N_d\approx1.12$, so $Q\approx k\,\Delta H\,(N_f/N_d)\approx8\times10^{-7}\times10\times1.12=8.9\times10^{-6}\ \text{m}^3/\text{s per m}$ — a useful cross-check that the mesh has converged to a physically sensible flow net.
  3. Read the head along the tunnel base. Sampling $h$ along $z=10$ m, $x=30$–$50$ m gives a head that falls from about 23.0 m (upstream side) to 18.7 m (downstream side), averaging $\bar h=\boxed{20.8\ \text{m}}$.
  4. Convert head to pore pressure and integrate for the uplift force. At each point on the base, $u=\gamma_w(h-z)$ with $z=10$ m and $\gamma_w=9.81$ kN/m³. Integrating $u$ across the 20 m base width, $$U=\int_{30}^{50}\gamma_w\big(h(x,10)-10\big)\,dx=\boxed{2113\ \text{kN per metre of tunnel}}.$$
Check: the exam gives only the embankment's outer dimensions (25 m crest, 30 m height as 10+10+10, 80 m base) and the tunnel's own 20 m×10 m footprint (implied by the 30+20+30 m base split); the crest is taken centred over the tunnel and the two side slopes are taken as straight lines from toe to crest edge, which is the only geometry consistent with every printed dimension simultaneously.
QuantityValue
Equivalent $N_f/N_d$ (from the solved net)≈1.12
Seepage quantity, $Q$≈8.9×10-6 m³/s per m
Average head at tunnel base, $\bar h$20.8 m
(b) Uplift force per unit length of tunnel2113 kN/m