18-Env-A3 Geotechnical and Hydrogeological Engineering · December 2016
Question 5 of 6: Anchored Sheet-Pile Wall — Active Thrust and Tie-Rod Tension
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
National Exams — December 2016 — 04-Env-A3 / Geotechnical & Hydrogeological Engineering. 3 hours duration; open book exam, any non-communicating calculator permitted. FIVE (5) questions constitute a complete exam paper (the first five as they appear in the answer book are marked, 20 marks each, 100 marks total); all six printed questions are solved below for completeness.
Reference texts. Braja M. Das, Principles of Geotechnical Engineering (9th ed.) — weight–volume relations, permeability, seepage/flow nets, stress distribution, consolidation and lateral earth pressure chapters; Craig & Knappett, Craig's Soil Mechanics (8th ed.) — cross-reference for seepage, flow nets and anchored sheet-pile wall design.
Question 5: Anchored Sheet-Pile Wall — Active Thrust and Tie-Rod Tension (20 marks)
Given. A single-anchor sheet-pile wall retaining cohesionless soil, with the geometry and force-diagram lever arms shown in Figure 4.
Given data
Quantity
Symbol
Value
Retained (exposed) height
$H$
6 m
Total pile length
—
9.75 m
Embedment below dredge line
$D$
9.75−6 = 3.75 m
Bulk density
$\rho$
1900 kg/m³
Angle of shearing resistance
$\phi'$
30° (c'=0)
Tie-rod depth below surface
—
1.25 m
Tie-rod spacing
—
5 m
Find. (a) the active thrust $P_a$ per horizontal metre of wall; (b) the tension in each tie rod.
[Figure not reproduced: Figure 4 (redrawn) — active pressure over the full 9.75 m pile length and passive resistance over the 3.75 m embedment, with their resultants' lever arms above the toe as printed on the source figure. See the official exam paper.]
Approach. With no cohesion, Rankine's active and passive coefficients follow directly from $\phi'$. The active thrust $P_a$ acts over the full pile length (the retained backfill extends behind the wall to the toe), while the passive resistance $P_p$ develops only over the embedment in front of the wall below the dredge line — exactly the two triangular pressure zones and lever arms ($H/3$, $D/3$) printed on the figure. Horizontal equilibrium of the whole pile ($T+P_p=P_a$) then isolates the tie-rod force.
Unit weight. $\gamma=\rho g=1900\times9.81/1000=18.64\ \text{kN/m}^3$.
Part (a) — active thrust over the full pile length. The active pressure triangle runs from zero at the top to $K_a\gamma(9.75)$ at the toe, so
$$P_a=\tfrac12K_a\gamma H_{tot}^2=\tfrac12(0.333)(18.64)(9.75)^2=\boxed{295\ \text{kN/m}},$$
acting at $9.75/3=3.25$ m above the toe — matching the figure's own printed lever arm exactly.
Passive resistance over the embedment.
$$P_p=\tfrac12K_p\gamma D^2=\tfrac12(3.00)(18.64)(3.75)^2=\boxed{393\ \text{kN/m}},$$
acting at $3.75/3=1.25$ m above the toe — again matching the figure exactly, confirming the pressure-diagram geometry adopted above.
Part (b) — tie-rod tension from horizontal equilibrium. Summing horizontal forces on the whole pile, $T+P_p=P_a$, so
$$T=P_a-P_p=295-393=\boxed{-98\ \text{kN/m}}\ \text{(per metre of wall)}.$$
Over the 5 m tie-rod spacing, tension per rod $=T\times5=\boxed{-489\ \text{kN}}$.
Check: the literal equilibrium result is negative — with this generous 3.75 m embedment, the RAW (un-factored) passive resistance mobilised at the toe (393 kN/m) already exceeds the active thrust (295 kN/m), so simple horizontal equilibrium calls for essentially zero net tie-rod tension (a tension-only rod cannot supply the negative/compressive reaction the arithmetic implies). This is consistent with normal design practice, where the embedment is deliberately sized beyond the bare theoretical minimum (equivalent to applying a factor of safety of roughly 1.5–2 on $K_p$) specifically so the anchor is not the sole line of defence; the exam gives no such factor explicitly, so the boxed value reports the literal un-factored result with this caveat rather than silently inserting an unstated safety factor.