NivaarExam PrepOfficial exam papers ↗

18-Env-A4 Water and Wastewater Engineering · December 2015

Question 5 of 5: Primary Clarifier Design

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams — December 2015 — 04-Env-A4 / Water and Wastewater Engineering. 3 hours duration; closed book with one double-sided aid sheet; approved calculator permitted. Question 1 is compulsory; the paper instructs candidates to attempt any three of the remaining four (100 marks total); all five are solved below for completeness. (The source page prints an internal header inconsistency — "NATIONAL EXAMINATION, MAY 2015" beside a page footer reading "December 2015" — the period is taken as December 2015 per the footer; this does not affect any question content.)

Reference texts. Metcalf & Eddy, Wastewater Engineering: Treatment and Resource Recovery; Davis & Cornwell, Introduction to Environmental Engineering; MWH's Water Treatment: Principles and Design; Guidelines for Canadian Drinking Water Quality (Health Canada).

Question 5: Primary Clarifier Design (25 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Influent, Q TSS 200, VSS 170, BOD₅ 160 mg/L Settling zone — surface area A, side water depth 3.0 m Effluent (weir) TSS 80, VSS 68, BOD₅ 104 mg/L Sludge hopper Primary sludge, 4% solids TSS removal 60% (BOD₅ removal 35%)
Primary clarifier mass balance: influent solids/BOD₅ split between the clarified effluent and the settled sludge withdrawn from the hopper.

Given.

Given data
QuantitySymbolValue
Average day flow$Q$20,000 m³/d
Influent TSS$C_{TSS}$200 mg/L
Influent VSS$C_{VSS}$170 mg/L
Influent BOD₅$C_{BOD}$160 mg/L
TSS removal efficiency$R_{TSS}$60%
Primary sludge solids concentration$P_s$4%
Primary sludge specific gravity$SG$1.03
Surface overflow rate (design, at peak flow)$SOR$80 m³/m²·d
Peaking factor$PF$2.25
Side water depth$d$3.0 m
Check: the source states a TSS removal efficiency but not a separate VSS or BOD₅ removal efficiency. VSS is treated as removed at the same 60% efficiency as TSS, since VSS is itself the volatile fraction of TSS and the two settle together as one particulate population. BOD₅ removal is read from the standard primary-clarifier TSS-vs-BOD₅ removal correlation (Metcalf & Eddy typical design ranges of 50–70% TSS removal against 25–40% BOD₅ removal, roughly $\%\text{BOD}\approx\%\text{TSS}-25$) — at 60% TSS removal this gives 35% BOD₅ removal, the "appropriate" figure the question asks the candidate to select.

I. TSS, VSS and BOD₅ Loads in Primary Effluent

Find. The mass loading (kg/d) of TSS, VSS and BOD₅ leaving the clarifier in the primary effluent.

Approach. Apply each substance's removal efficiency to its influent concentration to get the effluent concentration, then convert every concentration to a mass load using $\text{Load (kg/d)}=C(\text{mg/L})\times Q(\text{m}^3/\text{d})/1000$.

  1. Effluent concentrations. $$C_{TSS,eff}=200(1-0.60)=80\ \text{mg/L},\quad C_{VSS,eff}=170(1-0.60)=68\ \text{mg/L},\quad C_{BOD,eff}=160(1-0.35)=104\ \text{mg/L}.$$
  2. Convert to mass loads. $$\text{TSS load}=\frac{80\times20{,}000}{1000}=\boxed{1600\ \text{kg/d}},\qquad \text{VSS load}=\frac{68\times20{,}000}{1000}=\boxed{1360\ \text{kg/d}},\qquad \text{BOD}_5\ \text{load}=\frac{104\times20{,}000}{1000}=\boxed{2080\ \text{kg/d}}.$$
  3. Cross-check via the influent side. Influent loads are 4000, 3400 and 3200 kg/d for TSS, VSS and BOD₅; removing 60%, 60% and 35% respectively leaves $4000-2400=1600$, $3400-2040=1360$ and $3200-1120=2080$ kg/d — matching step 2 exactly.

II. Volume of Primary Sludge Produced per Day

Find. The daily volume of primary sludge withdrawn from the clarifier.

Approach. The dry mass of solids captured equals the TSS removed (influent load minus effluent load); dividing that mass by the sludge's wet density and solids fraction gives the wet sludge volume.

  1. Mass of TSS captured (removed) per day. $$m_{TSS,removed}=\frac{200\times20{,}000}{1000}\times0.60=4000\times0.60=2400\ \text{kg/d}.$$
  2. Sludge (wet) density from its specific gravity. $$\rho_{sludge}=SG\times1000\ \text{kg/m}^3=1.03\times1000=1030\ \text{kg/m}^3.$$
  3. Sludge volume from mass, density and solids fraction. $$V_{sludge}=\frac{m_{TSS,removed}}{\rho_{sludge}\times P_s}=\frac{2400}{1030\times0.04}=\frac{2400}{41.2}=\boxed{58.3\ \text{m}^3/\text{d}}.$$

III. Surface Area of the Primary Clarifier

Find. The clarifier surface area sized for the design SOR at peak day flow.

Approach. Scale the average day flow up to the peak day flow using the peaking factor, then size the area directly from $A=Q_{peak}/SOR$.

  1. Peak day flow. $$Q_{peak}=Q\times PF=20{,}000\times2.25=\boxed{45{,}000\ \text{m}^3/\text{d}}.$$
  2. Required surface area. $$A=\frac{Q_{peak}}{SOR}=\frac{45{,}000}{80}=\boxed{562.5\ \text{m}^2}.$$

IV. Hydraulic Retention Time at Average Day Flow

Find. The HRT of the clarifier basin sized in Part III, evaluated at the average day flow.

Approach. Multiply the Part III surface area by the given side water depth to get the basin volume, then divide by the average day flow.

  1. Basin volume. $$V=A\times d=562.5\times3.0=1687.5\ \text{m}^3.$$
  2. HRT at average day flow. $$\text{HRT}=\frac{V}{Q}=\frac{1687.5}{20{,}000}=0.0844\ \text{d}=0.0844\times24=\boxed{2.03\ \text{h}}.$$
Check: sizing the clarifier area on the PEAK flow (Part III) but then evaluating HRT at the AVERAGE flow (Part IV) is the standard design convention — the SOR criterion must hold even during the peak, while HRT is normally reported at average conditions since that is what the tank experiences most of the time; the two calculations therefore deliberately use different flows, not an inconsistency. A 2.03 h average-flow HRT sits at the low end of the typical 1.5–3 h range for primary clarifiers (Metcalf & Eddy) — a direct consequence of sizing area on this paper's relatively high SOR (80 m³/m²·d).
QuantityValue
TSS load, primary effluent1600 kg/d
VSS load, primary effluent1360 kg/d
BOD₅ load, primary effluent2080 kg/d
Primary sludge volume58.3 m³/d
Peak day flow45,000 m³/d
Clarifier surface area562.5 m²
Basin volume1687.5 m³
HRT at average day flow2.03 h (0.0844 d)
Back to the paper →