Reference texts: Tchobanoglous, Theisen & Vigil, Integrated Solid Waste Management: Engineering Principles and Management Issues; Vesilind, Worrell & Reinhart, Solid Waste Engineering; Davis & Cornwell, Introduction to Environmental Engineering (6th ed.); Freeze & Cherry, Groundwater; CCME, Guidance Document on Landfill Gas Management; Canadian Environmental Protection Act, 1999.

Question 18: Post-Closure Care Factors (3 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Three factors that must be considered in post-closure care: (1) Groundwater and leachate monitoring — continued sampling of the monitoring-well network and any residual leachate collection system, trended against regulatory limits, for the full post-closure care period. (2) Landfill gas monitoring and management — continued operation of the LFG collection/flare or energy-recovery system and perimeter/structure methane monitoring, since gas generation continues for years after the site stops accepting waste. (3) Final cover maintenance — periodic inspection and repair of the cap for erosion, differential settlement cracking and vegetation cover, since a degraded cover increases both infiltration (more leachate) and gas migration risk.