18-Env-A6 Solid Waste Engineering and Management · December 2017

Question 6 of 18: Long-Term Landfill Closure Plan

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Examination, December 2017 — 04-Env-A6 / 18-Env-A6, Solid Waste Engineering and Management. 3 hours duration, closed book, one of two calculators permitted (Casio or Sharp approved model). All eighteen (18) questions constitute a complete paper (100 marks total).

Reference texts: Tchobanoglous, Theisen & Vigil, Integrated Solid Waste Management: Engineering Principles and Management Issues; Vesilind, Worrell & Reinhart, Solid Waste Engineering; Davis & Cornwell, Introduction to Environmental Engineering (6th ed.); Freeze & Cherry, Groundwater; CCME, Guidance Document on Landfill Gas Management; Canadian Environmental Protection Act, 1999.

Question 6: Long-Term Landfill Closure Plan (3 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

A long-term closure plan has to address the physical works, the ongoing monitoring/maintenance obligation, and the financial mechanism that pays for both, since a closed landfill remains an environmental liability for decades after it stops accepting waste. Final cover system: design and construction of a low-permeability cap (compacted clay or geomembrane), a drainage layer to shed infiltration, and a vegetated topsoil layer to control erosion and support final land use, built to the regulatory design standard in force. Post-closure monitoring: a multi-decade program (commonly 25–30 years under CCME/provincial guidance) of groundwater, leachate and landfill-gas monitoring at a defined well/probe network, with defined trigger levels and a contingency response if a trend is detected. Continued leachate and gas management: ongoing operation of the leachate collection/treatment system and the LFG collection/flare or energy system until generation rates decline to background levels. Financial assurance: a trust fund, bond or other instrument sized to cover the full post-closure monitoring, maintenance and any remediation contingency, since the responsible party must be able to fund the obligation even decades after final waste receipt. Land-use controls: deed notations/restrictions on future site use reflecting expected settlement and residual gas migration risk.