Question 1 of 5: RQD, RMR and Unsupported Stand-up Time for a Tunnel in Jointed Rock
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
National Exams — December 2013 — 04-Geol-A5 Rock Mechanics. Three-hour, closed-book exam; one of two approved calculators permitted, plus two sheets of the candidate's own rock-mechanics formulae/notes. Five questions of equal value (20 marks each); the paper instructs candidates to answer only the first 4 of 5 questions appearing in the answer book — all five are answered here as a complete study resource. Selected equations, RMR tables (Bieniawski 1989) and the Modified Lauffer stand-up-time chart are supplied at the back of the exam and are reproduced where used.
Reference texts: Bieniawski, Engineering Rock Mass Classifications (Wiley, 1989) — the RMR system, discontinuity-condition guidelines, and excavation/support tables used in Q1; Hoek, Practical Rock Engineering — Mohr-Coulomb strength parameters from triaxial data, Kirsch stress solutions around circular openings, and thick-wall liner design used in Q2/Q3/Q5; Brady & Brown, Rock Mechanics for Underground Mining (3rd ed.) — tributary-area pillar stress analysis and elastic pillar deformation used in Q4; EGBC Geoscience Professional Practice Guidelines for assumption-disclosure conventions.
Question 1: RQD, RMR and Unsupported Stand-up Time for a Tunnel in Jointed Rock (20 marks)
Given. Core recovery log (Figure Q1) — six 0.5 m runs, total 3.0 m; point-load/UCS calibration pairs and 10 further point-load-only readings (table below); two joint sets with the strike/dip/spacing/roughness/separation data quoted above; groundwater inflow < 5 L/min (< 10 L/min per 10 m tunnel length bracket); Bieniawski (1989) RMR Tables 1–2 and the Modified Lauffer stand-up-time relationship (Table D / Figure 5) supplied with the exam.
Core Strength Data (Page 3 of the exam)
$S_c$ (MPa)
$I_{s54}$ (MPa)
206.2
9.2*
221.4
10.2*
211.3
9.5*
203.3
8.8*
205.5
9.4*
—
9.7, 8.9, 9.1, 10.1, 9.3, 9.7, 9.0, 8.9, 9.9, 9.7
*calibration pairs (used to establish the site-specific $S_c/I_{s54}$ ratio, then applied to the remaining ten $I_{s54}$-only readings).
Find. (a) RQD from the core log. (b) RMR (Bieniawski 1989) for the rock mass. (c) The maximum and minimum practicable unsupported excavation span. (d) The unsupported stand-up time over that span range, and the corresponding rock-bolt/shotcrete/steel-set support range.
Approach. Count intact core-piece lengths ≥ 100 mm directly off the recovery log for RQD (the direct-measurement definition, since the actual core is available — the empirical $RQD=115-3.3J_v$ formula is reserved for cases with no core to inspect). Sum the five RMR parameters (strength, RQD, spacing, condition, groundwater) from Tables 1 and the discontinuity-condition guidelines, plus the tunnel-orientation adjustment, to get RMR and the rock-mass class (Table 1C). Use the class's own Table 1D benchmark span/stand-up-time pair as the primary (non-graphical) quantitative anchor for parts (c)/(d), supplemented by Table 2's excavation/support guidance for that class.
Part (a) — RQD from the core log. Each of the six 0.5 m (500 mm) runs is broken into intact pieces by its mapped fractures; pieces ≥ 100 mm count toward RQD. Run 1: pieces of 120, 80, 180, 60 mm → 120+180=300 mm qualifies. Run 2: 220, 240 mm (both qualify) → 460 mm. Run 3: 80, 140, 120, 100 mm → 140+120+100=360 mm qualifies (the 80 mm piece is excluded). Run 4: 40, 280, 80, 40 mm → only 280 mm qualifies. Run 5: 40, 180, 200 mm → 180+200=380 mm qualifies. Run 6: 340, 80, 40 mm → only 340 mm qualifies.
$$\sum(\text{pieces}\ge100\text{mm}) = 300+460+360+280+380+340 = 2120\ \text{mm}$$
$$RQD=\frac{2120}{3000}\times100=\boxed{70.7\%}$$
By Table 1 (parameter 2), 70.7% falls in the 50–75% bracket → RQD rating = 13.
Part (b) — intact rock strength rating. The five calibration pairs give a site-specific ratio $S_c/I_{s54}$ of 22.4, 21.7, 22.2, 23.1 and 21.9 (mean $k=22.3$) — close to, but more reliable than, the exam's generic $S_c=24\,I_{s54}$ correlation because it is fitted to this rock. Applying $k=22.3$ to the ten further $I_{s54}$ readings and averaging all fifteen $S_c$ values (5 measured + 10 estimated) gives a mean intact-rock UCS of $\boxed{209.8\ \text{MPa}}$. By Table 1 (parameter 1), 100–250 MPa → strength rating = 12.
RMR — spacing, condition and groundwater ratings. Two joint sets are present with different governing spacings and conditions, so each RMR sub-parameter is scored from the set that controls it. Spacing: Joint #2 (0.3 m = 300 mm) is the closer, governing set — Table 1 bracket 200–600 mm → rating 10 (Joint #1's 1.5 m spacing would instead rate 15, but the closer-spaced set governs local block size). Condition: Joint #1's 1.0–1.5 mm continuous separation places it in the "Separation 1–5 mm, Continuous" bracket → rating 10; Joint #2 (very rough, discontinuous, separation << 0.1 mm) would rate 30, so Joint #1 is again the governing (weaker) set. Groundwater: < 5 L/min is inside the < 10 L/min per 10 m bracket ("damp") → rating 10.
Check: with two joint sets rating differently on spacing and condition, the WORSE (governing) rating from either set is taken for each sub-parameter independently — the conventional conservative treatment when a table gives no explicit rule for combining multiple joint families.
RMR — orientation adjustment and total. Joint #1 (the continuous, weaker-condition set) strikes parallel to the tunnel axis and dips only $15^{\circ}$ — Table 1B/F's "Dip 0–20°, irrespective of strike" row rates this "Fair" for tunnels & mines, an adjustment of $-5$.
$$RMR = 12\ (\text{strength}) + 13\ (\text{RQD}) + 10\ (\text{spacing}) + 10\ (\text{condition}) + 10\ (\text{water}) - 5\ (\text{orientation}) = \boxed{50}$$
By Table 1C, RMR 50 (41–60 bracket) places this rock mass in Class III — Fair rock.
Part (c) — limiting excavation dimensions. Table 1D's own Class III benchmark is a 5.0 m span at an average 1-week unsupported stand-up time — taken as the practical maximum unsupported span for this rock mass, since larger spans on the same RMR-contoured Lauffer curve (Figure 5) stand up for much less than a week. A practical minimum is set by Joint #2's 0.3 m spacing: for the rock mass to behave as the continuum the RMR classification assumes (rather than as a few discrete blocks), the opening should span at least about ten discontinuity spacings, i.e. $10\times0.3=\boxed{3.0\ \text{m}}$.
$$\boxed{3.0\ \text{m} \le \text{span} \le 5.0\ \text{m}}$$
Check: the 5.0 m maximum is read directly from the exam's own Table 1D (no digitization needed); the 3.0 m minimum applies the standard "span ≫ dominant block size" rule of thumb for RMR/Q continuum validity, since the source provides no explicit minimum-span table.
Part (d) — stand-up time and support range. At the 5.0 m maximum span, Table 1D gives an unsupported stand-up time of about 1 week for Class III. At the 3.0 m practical minimum, the same Class-III Lauffer curve (Figure 5) is markedly flatter at smaller spans, so the stand-up time is materially longer — qualitatively several weeks to a few months rather than a specific digitized value. Table 2's Class III (RMR 41–60) guidance applies across this whole span range: excavate top heading and bench (1.5–3 m advance in the heading), commence support after each blast and complete support within 10 m of the face; systematic rock bolts 4 m long spaced 1.5–2 m in crown and walls with wire mesh in the crown; 50–100 mm shotcrete in the crown and 30 mm in the sides; no steel sets required.
Figure Q1 — core recovery log, six 0.5 m runs (3.0 m total); green pieces ≥100 mm count toward RQD, tan pieces and red fracture zones are excluded.
Quantity
Result
(a) RQD
70.7% (rating 13)
(b) Mean intact UCS (from $I_{s54}$ correlation)
209.8 MPa (strength rating 12)
(b) RMR
50 — Class III, Fair rock
(c) Limiting span
3.0 m (min) to 5.0 m (max)
(d) Stand-up time at 5.0 m span
≈ 1 week
(d) Support (Class III, any span in range)
4 m bolts @ 1.5–2 m + 50–100 mm shotcrete crown, 30 mm sides, no steel sets