NivaarExam PrepOfficial exam papers ↗

18-Geol-A6 Soil Mechanics · December 2014

Question 4 of 6: Consolidation

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exams — December 2014 — 04-Geol-06, Soil Mechanics. Three-hour, closed-book exam; one of two approved calculators permitted. Six questions of equal value (20 marks each, Q6 split 5 marks per sub-part); the paper instructs candidates to answer only the first five questions appearing in the answer book — all six are answered here as a complete study resource.

Reference texts: Das, Principles of Geotechnical Engineering — USCS classification (Q1), phase relations (Q2, Q6d), consolidation theory (Q4), flow nets and seepage (Q5), permeability testing (Q6a/c); Craig, Craig's Soil Mechanics — lateral earth pressure coefficients and limit-equilibrium slope stability (Q3), effective stress and consistency limits (Q6b); EGBC Geoscience Professional Practice Guidelines for assumption-disclosure conventions.

Question 4: Consolidation (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

(a) Settlement of the overconsolidated clay

Given. $H_0=7\text{ m}$; $C_c=0.32$; $C_r=0.065$; $e_0=0.864$; $\sigma'_p=310\text{ kPa}$; $\sigma'_{vo}=126\text{ kPa}$; applied pressure $\Delta\sigma=285\text{ kPa}$.

Find. (i) Settlement given the clay's actual (overconsolidated) stress history. (ii) Settlement if the clay were instead normally consolidated (never preconsolidated beyond the existing overburden).

Approach. Compare the final vertical effective stress $\sigma'_{vf}=\sigma'_{vo}+\Delta\sigma$ against $\sigma'_p$ to decide whether the stress path stays on the recompression line or crosses onto the virgin compression line.

  1. Final effective stress. $$\sigma'_{vf}=\sigma'_{vo}+\Delta\sigma=126+285=\boxed{411\text{ kPa}}$$ Since $\sigma'_{vf}=411>\sigma'_p=310\text{ kPa}$, the stress path recompresses from 126 to 310 kPa, then follows the virgin compression line from 310 to 411 kPa — both terms of the combined settlement formula are needed.
  2. Part (i) — settlement using the actual stress history. With $H_0/(1+e_0)=7/1.864=3.755\text{ m}$: $$\Delta H=C_r\frac{H_0}{1+e_0}\log\frac{\sigma'_p}{\sigma'_{vo}}+C_c\frac{H_0}{1+e_0}\log\frac{\sigma'_{vf}}{\sigma'_p}$$ $$\Delta H=0.065(3.755)\log\frac{310}{126}+0.32(3.755)\log\frac{411}{310}=0.0954+0.1473=\boxed{0.243\text{ m}\ (24.3\text{ cm})}$$
  3. Part (ii) — settlement if never preconsolidated above the overburden. With no preconsolidation "memory" ($\sigma'_p=\sigma'_{vo}$), the entire stress increase from 126 to 411 kPa follows the steeper virgin compression line only: $$\Delta H=C_c\frac{H_0}{1+e_0}\log\frac{\sigma'_{vf}}{\sigma'_{vo}}=0.32(3.755)\log\frac{411}{126}=\boxed{0.617\text{ m}\ (61.7\text{ cm})}$$ This is about 2.5× the overconsolidated-clay settlement of part (i), illustrating why preconsolidation (from prior loading, erosion, or desiccation) makes a clay stratum substantially stiffer against a new load than a normally consolidated clay at the same void ratio.

(b) Time rate of settlement: single vs. double drainage

Given. Design estimate: 10 cm settlement at some elapsed time under double drainage, with 50 cm ultimate settlement; $c_v=2.41\times10^{-4}\text{ cm}^2/\text{s}$; clay thickness $H=7\text{ m}$.

Find. (i) How the double-to-single drainage change affects the ultimate settlement magnitude. (ii)–(iii) Time to reach 10 cm of settlement under single and double drainage, computed directly from $c_v$.

Approach. The degree of consolidation at 10 cm of settlement is $U=\Delta H(t)/\Delta H_{\text{ult}}=10/50=20\%$, independent of drainage condition (ultimate settlement is set by the stress change and compressibility alone, not by how the water escapes). The time to reach that $U$ is then found from the time factor $T=c_vt/H_{dr}^2$, using $H_{dr}=H/2$ for double drainage and $H_{dr}=H$ for single drainage.

  1. Part (i) — effect on total settlement. The ultimate settlement $\Delta H_{\text{ult}}$ depends only on $C_c$, $C_r$, $e_0$ and the stress change (the same equations as part (a)) — it does not appear anywhere in $T=c_vt/H_{dr}^2$. Removing the bottom drainage boundary therefore does not change the total (ultimate) settlement, which remains $\boxed{50\text{ cm}}$ either way; it only slows the rate at which that settlement is reached, because the drainage path length $H_{dr}$ doubles (from $H/2$ to $H$) when the bottom boundary is sealed.
  2. Degree of consolidation at the 10 cm point. $$U=\frac{\Delta H(t)}{\Delta H_{\text{ult}}}=\frac{10}{50}=\boxed{20\%}$$ Since $U<60\%$, the low-$U$ time-factor relation applies: $$T=\frac{\pi}{4}\left(\frac{U}{100}\right)^2=\frac{\pi}{4}(0.20)^2=\boxed{0.0314}$$
  3. Part (iii) — time under double drainage. $H_{dr}=H/2=3.5\text{ m}=350\text{ cm}$. $$t=\frac{TH_{dr}^2}{c_v}=\frac{0.0314(350)^2}{2.41\times10^{-4}}=1.60\times10^{7}\text{ s}=\boxed{0.51\text{ yr}\ (\approx185\text{ days})}$$
  4. Part (ii) — time under single drainage. $H_{dr}=H=7\text{ m}=700\text{ cm}$ — the same $T$ (same $U$) but a drainage path twice as long: $$t=\frac{TH_{dr}^2}{c_v}=\frac{0.0314(700)^2}{2.41\times10^{-4}}=6.39\times10^{7}\text{ s}=\boxed{2.03\text{ yr}\ (\approx739\text{ days})}$$ Since $t\propto H_{dr}^2$ at fixed $U$, doubling the drainage path exactly quadruples the time: $t_{\text{single}}/t_{\text{double}}=(H/(H/2))^2=4$, consistent with $2.03/0.51\approx4$.
Check: the source narrative states the double-drainage 10 cm settlement was originally estimated to occur "in 2 years," but computing directly from the given $c_v$ and the $U$–$T$ relation gives $\approx$0.51 years for double drainage (and $\approx$2.03 years for single drainage, which is close to the narrative's "2 years" figure). This appears to be an inconsistency in the source data between the narrative design estimate and the $c_v$ value supplied for parts (ii)–(iii); for data inconsistencies, both times below are computed directly and independently from the given $c_v$, $H$ and $U=20\%$ rather than forced to reproduce the narrative's "2 years."
QuantityResult
(a)(i) Settlement, actual (OC) stress history0.243 m (24.3 cm)
(a)(ii) Settlement, if normally consolidated0.617 m (61.7 cm)
(b)(i) Ultimate settlement, single vs. double drainageunchanged at 50 cm; only the rate slows
(b) Time factor at $U=20\%$$T=0.0314$
(b)(iii) Time to 10 cm, double drainage0.51 yr ($\approx$185 days)
(b)(ii) Time to 10 cm, single drainage2.03 yr ($\approx$739 days)