18-Geol-A6 Soil Mechanics · December 2019
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Exams, December 2019 — 18-Geol-A6, Soil Mechanics (3 hours, closed book). Six questions constitute a complete exam: Questions 1–5 are compulsory; for Question 6, candidates choose 3 of 8 optional sub-questions (5 marks each) — all 8 are solved below as a complete study resource.
Reference texts: Das, Principles of Geotechnical Engineering; Craig's Soil Mechanics (Craig & Knappett); Freeze & Cherry, Groundwater (seepage/flow-net topics).
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. $k=4\times10^{-6}\text{ m/s}$ (homogeneous clay foundation); boundary heads $H_A=15\text{ m}$ (upstream/embankment), $H_B=10\text{ m}$ (downstream ground surface); point elevations $z_1=3\text{ m}$, $z_2=4\text{ m}$; Figure Q5-1a has no cutoff wall; Figure Q5-1b has a partial cutoff wall extending from the base of the embankment down into the foundation (not reaching the impermeable bedrock).
Find. (a) boundary conditions at A, B. (b) total/elevation/pressure head at points 1, 2, both figures. (c) a representative gradient. (d) base pore-pressure-head distribution. (e) which configuration has higher uplift, and why.
[Figure not reproduced: Figure Q5-1a — no cutoff wall. Illustrative flow lines shown; boundary heads and points 1/2 as read from the source figure. See the official exam paper.]
Point A (upstream, at the top of the embankment's saturated/wetted zone) is a constant-head boundary: total head there equals the reservoir/headwater elevation, $H_A=15\text{ m}$, because it is in direct contact with standing water and there is no velocity head in this slow (Darcy) seepage regime. Point B (downstream ground surface, where the phreatic surface daylights) is also a constant-head boundary, but at atmospheric pressure ($u=0$): total head there equals the local ground-surface elevation, $H_B=10\text{ m}$, since pressure head is zero at a free seepage-exit point.
Approach. Total head drops linearly with each equipotential-line crossing between the two boundaries. With $\Delta H_{\text{total}}=H_A-H_B=5\text{ m}$ split over $N_d=10$ equal drops ($\Delta h=0.5\text{ m}$ per drop), interpolate each point's total head by how many drops it sits past boundary A, then split into elevation head ($z$) and pressure head ($h_t-z$).
| Figure Q5-1a | Figure Q5-1b | |||||
|---|---|---|---|---|---|---|
| Point | $h_t$ | $z$ | $h_p$ ($u$) | $h_t$ | $z$ | $h_p$ ($u$) |
| 1 | 14.0 m | 3.0 m | 11.0 m (107.9 kPa) | 14.0 m | 3.0 m | 11.0 m (107.9 kPa) |
| 2 | 11.0 m | 4.0 m | 7.0 m (68.7 kPa) | 10.5 m | 4.0 m | 6.5 m (63.8 kPa) |
Taking one representative flow-net square adjacent to point 1 in Figure Q5-1a, with head drop $\Delta h=0.5\text{ m}$ over a square side $L\approx3\text{ m}$: $$i=\frac{\Delta h}{L}=\frac{0.5}{3}=\boxed{0.167}$$ In Figure Q5-1b, the squares bunch up tightly around the cutoff tip (down to roughly $L\approx1.2\text{ m}$ there), giving a locally much steeper gradient: $$i_{\text{near cutoff}}=\frac{0.5}{1.2}=\boxed{0.417}$$ — nearly $2.5\times$ Figure Q5-1a's gradient, which is exactly the mechanism by which a cutoff wall forces extra head loss into a short stretch of the flow path.
Figure Q5-1a (no cutoff) is subject to the higher uplift force. Uplift is the integral of pore-pressure head acting upward on the dam base; with no cutoff, water has a shorter, less-obstructed path from the high-head upstream boundary to underneath the dam, so less head is dissipated by the time seepage reaches the base — leaving MORE residual pressure head (and hence more uplift) under the full footprint. The partial cutoff in Figure Q5-1b forces seepage to travel down and around its tip, a materially longer path that dissipates a larger share of the total head before the flow ever gets under the downstream portion of the dam, which is exactly why point 2's computed pressure head is lower in (b) than in (a) above. This is the standard engineering rationale for adding a cutoff or sheet-pile curtain beneath a dam: it does not change the total head drop across the site, but it redistributes where that drop happens, trading it away from the high-uplift zone directly under the structure.