24-MMP-A4 Mine Valuation and Mineral Resource Estimation · December 2018
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
EGBC National Exam — Mining and Mineral Processing Engineering, 09-MMP-A4 Mine Valuation and Mineral Resource Estimation, 2018-Dec. 3 hours duration; one handwritten 8.5×11 in reference sheet permitted (not an open-book exam); only approved Sharp or Casio calculators allowed. Question 1 is compulsory (40 marks, parts 1.1–1.8); candidates then select THREE of the five optional Questions 2–6 (20 marks each) to complete the paper.
Reference texts: Isaaks & Srivastava, An Introduction to Applied Geostatistics (variogram modelling, kriging, anisotropy); Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (mine valuation, NPV/IRR and cut-off grade methodology); Gentry & O'Neil, Mine Investment Analysis (smelter/refining contract terms, net smelter return, taxation and risk); Guilbert & Park, The Geology of Ore Deposits, and Evans, Ore Geology and Industrial Minerals (VMS/SEDEX and porphyry deposit models); SME Mining Engineering Handbook, 3rd ed. (mineral exploration/evaluation stages, ore reserve classification); CIM Best Practice Guidelines and NI 43-101 (Canadian Securities Administrators).
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. Alternative 6A cash flows: Investment −80M (now); Y1–Y4 = 50, 30, 20, 10M; Y5 = 7M + 5M terminal = 12M. Alternative 6B: Investment −80M; Y1–Y5 = 28M/yr level; Y5 also carries a 10M terminal value (38M total in Y5). Table 6's individual and cumulative PV factors at each 5% step.
Approach. Compute NPV at successive 5% steps for each alternative using Table 6's factors (6A year-by-year; 6B via the 4-year cumulative factor plus the year-5 factor on 38M), locate the adjacent pair of rates where NPV changes sign, then interpolate within that narrow 5-point window.
| Alternative | Bracket used | Refined IRR |
|---|---|---|
| 6A | 20%–25% | 22.97% |
| 6B | 20%–25% | 24.23% (higher) |
Both alternatives comfortably clear the company's 15% minimum acceptable rate. Comparing the two, Alternative 6B has the higher (better) IRR — its level USD 28M/yr cash flow stream, though less front-loaded than 6A's, compounds to a larger total present value at these discount rates because of its larger terminal value and more even distribution; 6B is therefore preferred on the IRR criterion.