24-MMP-A5 Surface Mining Methods and Design · May 2013
Question 13 of 13: Capital-Cost Estimation – O’Hara Method
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
EGBC National Exam — Mining and Mineral Processing Engineering, 09-Mmp-A5 Surface Mining Methods and Design, 2013-May. 3 hours duration; one handwritten 8.5×11 in reference sheet permitted (not an open-book exam); only approved Sharp or Casio calculators allowed. Question 1 is compulsory (40 marks, parts 1.1–1.7); candidates then select FOUR of the six optional Questions 2–7 (15 marks each) to complete the paper.
Reference texts: Hartman & Mutmansky, SME Mining Engineering Handbook, 3rd ed. (dewatering, slope stability classification, dragline stripping geometry, truck dispatch, mine closure); Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (moving-cone and Lerchs–Grossmann pit optimization, capital-cost estimating, truck-shovel match factor); Lerchs, H. & Grossmann, I.F. (1965) “Optimum Design of Open-Pit Mines,” CIM Bulletin (the graph-theoretic 2-D worked example this question is drawn from); O’Hara, T.A. (1980) “Quick Guides to the Evaluation of Orebodies,” CIM Bulletin, Feb. 1980, and Mular, A.L. & Poulin, R. (1998) CANCOST, CIM Special Volume 47 (capital-cost formulae); Bieniawski, Z.T. (1989) Engineering Rock Mass Classifications (RMR system).
Find. Stripping ratio; each cost centre C12…C4; shovel/truck size and fleet counts; indirect costs; total fixed capital cost of the open-pit section (mine only, excluding milling infrastructure per the question’s own instruction).
Approach. This is a sequential, published parametric cost-estimating chain (O’Hara 1980 / Mular & Poulin CANCOST 1998): compute each cost centre’s own power-law formula from the given tonnages in the stated order, round equipment sizes and counts up to the next standard/integer unit exactly as instructed, then sum direct costs and apply the percentage indirect-cost factors to reach the total.
7.1 – quick order-of-magnitude estimate (0.5 marks). A ±40%, one-day turnaround estimate is a Class 5 / order-of-magnitude (conceptual) estimate in AACE terms – the right contact is an in-house senior mining/cost engineer (or a mine-equipment vendor’s applications engineer for a quick equipment-based check) working from parametric formulae exactly like the O’Hara method below, not a detailed engineering firm, since a ±10–15% definitive estimate needs weeks of detailed take-off, not a day.
7.2 – the O’Hara method (1 mark). O’Hara’s method (CIM Bulletin, Feb. 1980, later extended as Mular & Poulin’s CANCOST, CIM Special Volume 47, 1998) is a parametric (power-law regression) capital and operating cost estimator: each major cost centre of a mine/mill (site prep, stripping, mobile equipment, maintenance facilities, etc.) is fit to a simple formula of the form $C = a\,X^{b}$ against a single scale variable (throughput tonnage, equipment size), calibrated from a database of actual completed mine capital costs; summing the cost-centre formulae with the standard indirect-cost percentages (7.4.9) gives a rapid, order-of-magnitude total project capital cost from only a handful of basic design parameters, exactly as exercised in 7.4 below.
7.3 – escalating to present-day dollars (0.5 marks). Convert using a published mining capital-cost index (e.g. the Marshall & Swift Mine/Mill index of Q1.7, or an equivalent CE/Nelson-Farrar-type index) ratioed between the base year and the target year:
$$C_{2012} = C_{1980}\times\frac{Index_{2012}}{Index_{1980}}, \qquad C_{2015}=C_{1998}\times\frac{Index_{2015}}{Index_{1998}}$$
using the 1980-base index series for the O’Hara-year costs and the 1998-base series for the CANCOST-year costs, since each formula set was calibrated in its own base-year dollars.
7.4.1 – stripping ratio. Ore feed equals mill capacity (9,000 mt/day); waste is the remainder of the 23,000 mt/day total:
$$\text{ore}=9{,}000\ \text{mt/d}, \quad \text{waste}=23{,}000-9{,}000=14{,}000\ \text{mt/d}$$
$$SR = \frac{\text{waste}}{\text{ore}} = \frac{14{,}000}{9{,}000} = \boxed{1.56:1}$$
Stripping ratio is the tonnes of waste that must be removed for every tonne of ore mined – the single most common measure of a pit’s overall economic burden.
7.4.6.2 – unit costs, index check, and drill count.
$$\text{cost/shovel} = C_{31}/N_S = \boxed{\$2{,}276{,}261} \qquad \text{cost/truck} = C_{32}/N_T = \boxed{\$852{,}700}$$
These are plausible present-day large-shovel/haul-truck unit costs, so the formula set (once escalated per 7.3) still tracks real equipment pricing reasonably well – the main risk in relying on 1978–80-vintage cost data is that it under-represents the disproportionate cost growth of emissions controls, electronics/automation content and ultra-class truck sizes that have entered the market since, so the escalated total should be treated as a lower-bound sanity check, not a definitive estimate. If drills cost approximately the same as trucks, the “rule of thumb” number of drills follows from the drilling-cost total divided by the unit truck cost:
$$N_{drills} \approx \frac{C_{33}}{\text{cost/truck}} = \frac{3{,}534{,}436}{852{,}700} = 4.14 \;\Rightarrow\; \boxed{5\ \text{drills}}$$
This rule of thumb becomes unreliable for very large trucks, since drill cost scales far more slowly with pit throughput than ultra-class truck cost does – at very large truck sizes the rule can imply an implausibly low drill count; the estimator should cross-check against a drills-per-shovel operating ratio (typically 1–2 drills per shovel) rather than accept the cost-ratio result blindly when it is inconsistent with normal operating fleet ratios.
7.4.10 – total fixed capital cost (mine only).
$$Total = \Sigma_{prep}+\Sigma_{equip}+C_{7.4.9.1}+C_{7.4.9.2}+C_{7.4.9.3} = \boxed{\$92{,}839{,}190}$$
At roughly $92.8M for a 23,000 mt/day open-pit mine (excluding the mill, per the question’s own instruction to exclude 7.4.8), this is a reasonable order-of-magnitude fixed capital figure once escalated by the appropriate index (7.3) from the formula set’s 1978–80 base to the target estimate year – the answer is reasonable at Class-5 (±40%) precision, consistent with the intent of a same-day parametric estimate.
Item
Result
7.4.1 Stripping ratio
1.56 : 1
7.4.2 C12 (site prep)
$1,730,412
7.4.3 C21 / C22 (stripping)
$2,145,064 / $35,232,767
7.4.4 Shovel / truck size
6.1 m³ (8 yd) / 77 mt (85 st)
7.4.5 Shovels / trucks
5 / 19
7.4.6.1 C31 / C32 / C33
$11.38M / $16.20M / $3.53M
7.4.6.2 Cost/shovel / cost/truck / drills
$2.28M / $0.85M / 5
7.4.7 C4 (maintenance)
$6,829,326
7.4.9 Indirect costs (sum)
$15,784,577
7.4.10 Total fixed capital cost
$92,839,190
The exponent pairing adopted here – $N_S=0.0058\,T^{0.8}/S^{0.8}$, $N_T=0.198\,T^{0.8}/t^{0.8}$, mirroring the standard O’Hara sub-linear tonnage scaling used throughout the rest of this formula family – produces plausible fleet sizes (5 shovels, 19 trucks) for a 23,000 mt/day pit; an alternative reading of the exponent would change the specific counts but not the calculation method demonstrated.