24-MMP-A5 Surface Mining Methods and Design · May 2015
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
EGBC National Exam — Mining and Mineral Processing Engineering, 09-MMP-A5 Surface Mining Methods and Design, 2015-May. 3 hours duration, closed book; one hand-written 8.5×11 inch reference sheet and an approved Casio or Sharp calculator permitted. Question 1 is compulsory (40 marks, all six parts 1.1–1.6); a candidate then selects FOUR of Questions 2–7 (each worth 20 marks).
Reference texts: Hartman & Mutmansky (eds.), SME Mining Engineering Handbook, 3rd ed. (equipment availability/utilization, dragline stripping systems, truck-shovel productivity, mine dewatering, mine cost estimation); Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design, 3rd ed. (block-model economics, floating/moving-cone algorithm, the Lerchs–Grossmann graph-theoretic pit-optimization method, discounted cash-flow scheduling); Kennedy, B.A. (ed.), Surface Mining, 2nd ed., SME (dragline range-diagram geometry, stripping methods); Lerchs, H. & Grossmann, I.F. (1965), “Optimum Design of Open-Pit Mines,” CIM Bulletin, 58, 47–54; O’Hara, T.A. (1980), CIM Bulletin (Feb. 1980), and Mular, A.L. & Poulin, R. (1998), CapCosts: A Handbook for Estimating Mining and Mineral Processing Equipment Costs, CIM Special Volume 47 (parametric capital-cost formulae used in Question 6); Theis, C.V. (1935) and Cooper & Jacob (1946) aquifer-test methods (standard hydrogeology references, Question 3.2).
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. Discount (interest) rate $i=10\%$/yr; future cash-flow years $n=5$ and $n=15$; cash flow $F=\$100$ million in each case.
Find. The single-payment present-worth factor $(P/F,10\%,n)$ for $n=5,15$, and the present (year-zero) value of the $100M cash flow in each case.
Approach. A discount rate converts a future cash flow to its present-day equivalent by compounding the time value of money backwards: apply the standard single-payment present-worth factor $(1+i)^{-n}$.
1.2.3 – Effect on pit design and scheduling. Because far-future cash flows are worth so little today, discounting drives the pit optimizer and mine scheduler toward front-loading value: high-grade, low strip-ratio ore (typically the near-surface supergene-enriched cap on a copper porphyry, or the higher-grade epithermal vein sets) is scheduled as early as practically possible, waste stripping is deferred wherever slope/access allows, and phased (pushback) pit designs are preferred over a single monolithic pit precisely because they delay the waste-heavy outer pushbacks into later, more heavily discounted years. A high discount rate can even make the NPV-optimal pit SMALLER than the tonnage-maximizing ultimate pit, because low-grade, high-strip outer benches mined only in year 15+ contribute almost nothing in present-value terms while still consuming capital and stripping cost today – directly relevant to the Q2 Phase-1/Phase-2 sequencing, where Phase 1 is mined first partly because its cash flow is worth more, discounted, than deferring it to expose Phase 2 sooner.
1.2.4 – Discount rate as a risk proxy. Yes, in a limited way: raising the discount rate used in an NPV/DCF evaluation is the standard way analysts embed country or sovereign policy risk (expropriation, royalty/tax changes, permitting reversals) into an otherwise deterministic cash-flow model – a project in a jurisdiction perceived as unstable is evaluated at a higher hurdle rate (e.g. 12–15% instead of 8–10%), which penalizes long-dated cash flows (the years most exposed to a future policy change) far more than near-term ones. This is a coarse, single-number proxy, however: it cannot distinguish a small probability of total asset loss from a general rise in operating cost, and it says nothing about the TIMING or magnitude of a specific policy event – scenario/decision-tree analysis or an explicit sovereign-risk premium layered on top of the base discount rate are the more rigorous alternatives used alongside it in practice.
| Item | Value |
|---|---|
| (P/F, 10%, 5) | 0.6209 |
| (P/F, 10%, 15) | 0.2394 |
| PV of $100M at year 5 | $62.09 million |
| PV of $100M at year 15 | $23.94 million |