24-MMP-A5 Surface Mining Methods and Design · May 2015
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
EGBC National Exam — Mining and Mineral Processing Engineering, 09-MMP-A5 Surface Mining Methods and Design, 2015-May. 3 hours duration, closed book; one hand-written 8.5×11 inch reference sheet and an approved Casio or Sharp calculator permitted. Question 1 is compulsory (40 marks, all six parts 1.1–1.6); a candidate then selects FOUR of Questions 2–7 (each worth 20 marks).
Reference texts: Hartman & Mutmansky (eds.), SME Mining Engineering Handbook, 3rd ed. (equipment availability/utilization, dragline stripping systems, truck-shovel productivity, mine dewatering, mine cost estimation); Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design, 3rd ed. (block-model economics, floating/moving-cone algorithm, the Lerchs–Grossmann graph-theoretic pit-optimization method, discounted cash-flow scheduling); Kennedy, B.A. (ed.), Surface Mining, 2nd ed., SME (dragline range-diagram geometry, stripping methods); Lerchs, H. & Grossmann, I.F. (1965), “Optimum Design of Open-Pit Mines,” CIM Bulletin, 58, 47–54; O’Hara, T.A. (1980), CIM Bulletin (Feb. 1980), and Mular, A.L. & Poulin, R. (1998), CapCosts: A Handbook for Estimating Mining and Mineral Processing Equipment Costs, CIM Special Volume 47 (parametric capital-cost formulae used in Question 6); Theis, C.V. (1935) and Cooper & Jacob (1946) aquifer-test methods (standard hydrogeology references, Question 3.2).
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
4.1 – Range diagram. A range diagram is a to-scale plot of a dragline's working envelope – digging depth, dumping radius and dumping height, all measured from the machine's own centreline/tub – used to check, for a given pit geometry (overburden depth, pit width, required spoil-pile height), whether that specific machine's reach and stacking capability can physically complete the planned cut, exactly the check performed numerically in 4.6 below.
Given. Tub diameter $=20$ m; positioning $=75\%$ of tub diameter from centreline to high-wall edge; operating radius $=70$ m; pit width $W=40$ m; overburden (cut) depth $D=25$ m; swell factor $SF=0.25$; angle of repose $\phi=35^\circ$; rated (max) stacking height $=12$ m; high-wall slope $=63^\circ$; coal seam thickness $=3$ m.
Find. The tub-positioning offsets (4.2.2–4.2.3), the swelled volume of a unit sample (4.3.1), the cut/spoil cross-section geometry for a 1 m wide slice (4.5.1–4.5.6), and whether this dragline can complete the cut as specified (4.6–4.7).
4.6 – Capability check. Unlike a larger dragline with a 90 m operating radius considered elsewhere in this course (for which the same 82.3 m reach factor is comfortably inside the machine's reach), THIS machine's 70 m operating radius is 12.3 m SHORT of the 82.3 m horizontal reach factor – it cannot physically reach the required dump point. The operational stacking height is also 29.6 m against a rated maximum of only 12 m – exceeded by 17.6 m. Both checks fail: the dragline can neither reach the required dump point nor stack the swelled spoil to the height this single-pass cross-section demands, so it CANNOT complete the mining plan as specified without modification.
4.7 – Auxiliary methods/equipment. Because BOTH reach and stacking height fall short (unlike a reach-only or stack-only shortfall), the fix must address both: (i) an advanced bench (Question 1.4.3) – pre-strip part of the overburden column with a dozer/scraper so the dragline only casts the lower portion, which reduces both the spoil volume (lowering the required pile height) AND the horizontal distance the remaining material must be cast; (ii) a chop-down two-pass technique (Question 1.4.4) by the same dragline, splitting the single 25 m cut into two shallower lifts, each individually within the machine's reach and stacking envelope; or (iii) a dedicated secondary machine (dozer, or a stacking conveyor/spreader) to re-handle and push the spoil pile further back and lower its effective crest height, extending the machine's effective reach at the cost of extra handling. Given the size of BOTH shortfalls here (12.3 m reach, 17.6 m stacking height), a combination of (i) advanced bench and (ii) chop-down is the more realistic fix than re-handling alone.
| Item | Value |
|---|---|
| 4.2.2 Edge→centreline / edge→tub | 15 m / 5 m |
| 4.2.3 Dragline reach (from high-wall edge) | 55 m |
| 4.3.1 Swelled volume of 1 m³ | 1.25 m³ |
| 4.5.1 Cut area | 1000 m²/m |
| 4.5.2 Spoil pile area | 1250 m²/m |
| 4.5.3 Spoil height above coal seam floor | 32.6 m |
| 4.5.4 Spoil height above tub base | 4.6 m |
| 4.5.5 Operational stacking height | 29.6 m (vs. 12 m rated) |
| 4.5.6 Horizontal reach factor | 82.3 m (vs. 70 m operating radius) |
| 4.6 Capable without modification? | No – reach short by 12.3 m AND stacking height short by 17.6 m |