24-MMP-A5 Surface Mining Methods and Design · December 2016
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Surface Mining Methods and Design (09-MMP-A5) — December 2016 National Exam. Compulsory Question 1 (six sub-questions) plus all five optional Questions 2–6 are answered in full below (candidates select only three of Questions 2–6 in the real exam; all are solved here as a complete study resource).
Reference texts: Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (3rd ed.) — pit optimization, Lerchs–Grossmann, floating cone, dragline stripping geometry; SME Mining Engineering Handbook (3rd ed.); BC Health, Safety and Reclamation Code for Mines; Newnan, Eschenbach & Lavelle, Engineering Economic Analysis — sinking funds and future-worth factors.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. Total static lift = 1740−1650 = 90 m; two pumps in series (bottom, submersible, at 1650 m; top, tandem-coupled, at 1695 m, i.e. 45 m of pipe rise to the top pump, then a further 45 m of pipe/elevation to the crest); friction assumed negligible; pump curves per Fig. 5.1 (below) for the high-head "433, HT" and high-volume "431, MT" configurations.
[Figure not reproduced: Fig. 5.1 (redrawn) — HT curve starts near 58 m head at shut-off and terminates near 20 m at ≈107 L/s; MT curve starts near 35 m and declines gently to ≈12 m at 250 L/s. The two-HT operating point (both pumps at 45 m, Q≈36 L/s) is marked. See the official exam paper.]
Approach. Because the two pumps run IN SERIES, the SAME flow Q passes through both, and their heads simply ADD: $H_1(Q)+H_2(Q)=90\text{ m}$ (friction negligible). In addition, the BOTTOM pump alone must supply at least the 45 m of elevation up to the top pump's inlet, or that inlet would be starved (sub-atmospheric/cavitating) — i.e. $H_1(Q)\ge45$ m is a hard floor on the bottom pump, independent of what the top pump does.
| Quantity | Value |
|---|---|
| 5.1.1 Both-MT feasible? | No (2×35 m < 90 m even at shut-off) |
| 5.1.2 Best config. / max flow | Both pumps HT; Q ≈ 36 L/s |
| 5.1.3 Bottom pump in / out | ≈0 m / 45 m |
| 5.1.3 Top pump in / out | ≈0 m / 45 m |
| 5.1.4 Discharge pressure / pipe class | ≈438 kPa → PN10 HDPE |
5.2.1 Transmissibility and storage. Transmissibility $T$ (m²/day) is the rate at which the pit-wall aquifer can transmit water through its full saturated thickness under a unit hydraulic gradient ($T=Kb$, hydraulic conductivity × aquifer thickness); the storage coefficient $S$ (dimensionless) is the volume of water released from (or taken into) storage per unit surface area per unit change in head. Both are found from a PUMPING TEST: a test well is pumped at a constant known rate while drawdown is logged with time in nearby observation wells, and the drawdown-vs-time (or drawdown-vs-distance) data is plotted against the THEIS (or, at late time, the Jacob straight-line simplification of Theis) TYPE CURVE; matching the field curve to the type curve (or reading the slope/intercept of the Jacob semi-log straight line) yields $T$ and $S$ directly from the match-point coordinates.
5.2.2 Well layout and depth. Wells are laid out in plan around the pit perimeter (and along the internal access ramp where the wall geometry allows) at a spacing set by the aquifer's own radius of influence (from the pumping test above) so that adjacent wells' cones of depression overlap and jointly draw the water table down below the advancing pit floor; each well is drilled/screened to a depth that keeps the pumping water level safely below the deepest bench the pit will reach at that location, with enough submergence over the pump intake to avoid air-entrainment.
5.2.3 Feasibility and cost. Feasibility is assessed from the SAME pumping-test $T$ and $S$ values, used to predict the well spacing/count and total pumping rate needed to achieve the target drawdown ahead of mining; cost is then estimated from the number of wells (drilling + casing + screen + submersible pump per well) plus the power cost of continuous pumping at the predicted combined rate, and compared against the in-pit pump alternative's own capital (pumps, pipe, tandem stations) and power cost.
5.2.4 Operational advantages. Deep wells dewater the rock mass AHEAD of the excavation, so the working faces and floor stay dry and stable (better wall/floor trafficability, reduced slope-failure risk from pore pressure) with no pumps or pipework occupying working benches inside the pit, unlike the in-pit tandem system of 5.1 which must be relocated as the pit deepens and occupies bench space needed for haulage.