24-MMP-A5 Surface Mining Methods and Design · December 2016
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Surface Mining Methods and Design (09-MMP-A5) — December 2016 National Exam. Compulsory Question 1 (six sub-questions) plus all five optional Questions 2–6 are answered in full below (candidates select only three of Questions 2–6 in the real exam; all are solved here as a complete study resource).
Reference texts: Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (3rd ed.) — pit optimization, Lerchs–Grossmann, floating cone, dragline stripping geometry; SME Mining Engineering Handbook (3rd ed.); BC Health, Safety and Reclamation Code for Mines; Newnan, Eschenbach & Lavelle, Engineering Economic Analysis — sinking funds and future-worth factors.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
A range diagram is a scaled cross-section (or family of cross-sections at increasing overburden depth) that plots the dragline's own working envelope — its maximum digging radius/depth and its maximum dump radius/height, both measured from the machine's own tub centre — superimposed on the overburden/coal geometry being mined. It is the standard tool used to check, for a GIVEN cut geometry, whether a specific dragline model can reach the digging face and still reach far enough (and high enough) to place the spoil where the mine plan requires, exactly the check carried out numerically in 2.5–2.6 below.
Given. Tub diameter D = 20 m; positioning factor P = 75% of tub diameter, measured from the dragline centreline to the highwall edge; operating radius R = 90 m.
Find. (2.2.1) sketch; (2.2.2) distance from highwall edge to nearest tub edge, and from highwall edge to dragline centreline; (2.2.3) dragline reach in terms of R and P.
Approach. The positioning percentage is defined directly on the tub diameter, so distances follow from simple subtraction of the tub radius and the operating radius.
| Quantity | Value |
|---|---|
| Centreline → highwall edge | 15 m |
| Highwall edge → nearest tub edge | 5 m |
| Dragline reach beyond highwall (R − P) | 75 m |
Given. Swell factor SF = 0.25 (decimal). Find. Volume of 1 m³ unbroken overburden after digging and placing on the spoil pile.
Given. Cut depth = overburden depth Dc = 25 m; pit width w = 20 m; highwall slope θhw = 63° from horizontal; spoil angle of repose θr = 35°; swell factor SF = 0.25; coal seam thickness = 3 m; operating radius R = 90 m; max stacking height (rated) = 12 m.
| Parameter | Value |
|---|---|
| Cut/overburden depth | 25 m |
| Pit width | 20 m |
| Highwall slope | 63° |
| Spoil angle of repose | 35° |
| Swell factor | 0.25 |
| Coal seam thickness | 3 m |
| Rated max stacking height | 12 m |
Find. (2.5.1) cut area; (2.5.2) spoil pile area; (2.5.3) spoil height above coal floor; (2.5.4) spoil height above dragline tub base; (2.5.5) operational stacking height; (2.5.6) horizontal reach factor.
Approach. Model the cut as a rectangle (pit width × depth) plus the triangular highwall-batter allowance, then bulk that area by the swell factor and re-shape it as a symmetric angle-of-repose triangle to find the spoil pile's own height and footprint; check: the dragline's own tub sits at the ORIGINAL ground surface (simple side-casting per 1.2.a), i.e. 25+3 = 28 m above the coal-seam floor, and the spoil pile is assumed dumped on that same floor with the SAME angle of repose on both faces (only one repose angle is given in the source).
| Quantity | Value |
|---|---|
| 2.5.1 Cut area | 659.2 m² per m |
| 2.5.2 Spoil pile area (swelled) | 824.0 m² per m |
| 2.5.3 Spoil height above coal floor | 24.0 m |
| 2.5.4 Spoil height above tub base | −4.0 m (below tub) |
| 2.5.5 Operational stacking excursion | 24.0 m |
| 2.5.6 Horizontal reach factor | 67.0 m |
Yes. Both governing checks clear with margin: the horizontal reach factor (67.0 m, highwall crest to spoil crest) is comfortably inside the 90 m operating radius, and the spoil pile crest (2.5.4) sits 4.0 m BELOW the dragline's own tub level, i.e. nowhere near the 12 m rated maximum stacking height above grade. The single side-casting method of 1.2.a is therefore geometrically adequate for this cut — no walk-up to an advanced/extended bench is required.
Had either check failed — e.g. a deeper cut pushing the reach factor beyond the operating radius, or a swell/repose combination pushing the pile crest above the rated stacking height — the standard remedies are: (i) switch to advanced/extended bench mining (1.2.b/c) to gain both reach and stacking height by working from a self-built elevated platform; (ii) pre-strip part of the overburden with a truck-and-shovel fleet ahead of the dragline so the dragline only handles the portion within its own envelope; (iii) use a bulldozer to push/rehandle spoil further from the crest, flattening the pile and trading dozer cost for dragline reach; or (iv) re-cast with drill-and-blast pattern changes that reduce the swell factor (tighter fragmentation control), directly lowering the required spoil pile height.