24-MMP-A5 Surface Mining Methods and Design · December 2017
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Reference texts: Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (3rd ed.) — pit optimization, Lerchs–Grossmann, floating cone, pit slope design; Hoek & Bray, Rock Slope Engineering — planar and circular slope-stability analysis; SME Mining Engineering Handbook (3rd ed.) — surface mining equipment, mine dewatering, cut-off grade economics.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. Figure 1.3 is a hand-annotated cash-flow (i,j) block matrix for a 2-D pit cross-section; wall slope 45°, blocks 15×15×15 m. The matrix is printed rotated 90° on the original paper; the bench rows are reproduced below, centre-aligned per the 45° slope, each cell a per-block net cash flow (thousands of dollars, arbitrary units).
| Bench | Cash flow by column (blank = outside this bench’s width) | |||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 (widest) | -5,-5,-5,-5,-5,-5,-5,-5,-4,-1,2,2,-1,-4,-5,-5 | |||||||||||||||
| 2 | -4,-4,-4,-4,-4,-4,-4,-4,-4,4,2,2,1,-4,-4,-4 | |||||||||||||||
| 3 | -3,-3,-3,-3,-3,-3,-3,-3,-3,3,2,-3,-4,-4,-4,-1 | |||||||||||||||
| 4 | -3,-3,-3,-3,-3,-3,-3,-3,-3,-3,2,-3,-3,-3,-1 | |||||||||||||||
| 5 | -2,-2,-2,-2,-2,-2,-2,-2,-2,-2,-3,-3,-1,3,4 | |||||||||||||||
| 6 | -1,-1,-1,-1,-1,-1,-1,-1,-1,-1,-2,0,-1,4,2 | |||||||||||||||
| 7 | -1,-1,-1,-1,-1,-1,-1,-1,-1,-1,-1,-1,-1,2 | |||||||||||||||
| 8 | -2,-2,-2,-2,-2,-2,-2,-2,-2,-2,-2 | |||||||||||||||
| 9 (pit floor) | -1,-1,-1,-1,-1,-1,-1,-1,-1,-1 | |||||||||||||||
Find. (1.3.1) the MC decision rule; (1.3.2/1.3.3) the resulting pit outline and its total cash-flow sum.
1.3.1 — the moving/floating cone rule base. For every block with a positive cash flow, construct the inverted cone of blocks that MUST be removed above it to expose it at a 45° wall slope (in 2-D, the cone is a triangle widening by one block per bench going up). Sum the cash flows of the candidate block plus its overlying cone. If that sum is positive, the cone is “mineable” — mark every block in it as removed and merge it into the current pit outline (overlapping cones already mined are not re-charged). If the sum is negative, the candidate block is left in place (not mined on its own). Re-scan the section, because merging one cone can expose new candidate positive blocks or change the marginal cone cost of a neighbouring one, and repeat until no further positive-sum cone remains. The method is a LOCAL, greedy heuristic — the question explicitly warns not to use a simple adjacent-block cash-flow sum because there is no reliable general algorithm for the true 3-D cone test; a rigorous 2-D equivalent (used to check the greedy result) is to find, independently, the maximum-value stepped outline subject to the same ±1-column-per-bench slope constraint — mathematically the same graph-closure idea Lerchs & Grossmann formalise in Question 3.
Approach. Apply the rigorous stepped-outline equivalent of the cone test (a 1-D envelope optimisation across the columns of Figure 1.3, enforcing the 45° slope as a ±1 column shift per bench) to the reconstructed matrix, and read off the outline and its cash-flow total.
Summing the cash flow of every block inside that outline: $$\boxed{\text{MC optimal pit cash flow} = +2}$$ — a small but positive net value, i.e. this cross-section is only marginally profitable to mine at all under the moving-cone test; most of the section (the -1 to -6 waste blocks with no adjacent ore lens) is correctly left un-mined.
| Item | Result |
|---|---|
| MC rule base | mine a positive block only if (block + overlying 45° cone) ≥ 0; merge cones; repeat to convergence |
| MC pit outline | shallow lens, columns ≈10–15, benches 1–6 (see Given table, bolded cells) plus its minimum cone |
| Sum of cash flows, MC-optimal section | +2 (arbitrary cash-flow units) |