24-MMP-A5 Surface Mining Methods and Design · December 2017
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Reference texts: Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (3rd ed.) — pit optimization, Lerchs–Grossmann, floating cone, pit slope design; Hoek & Bray, Rock Slope Engineering — planar and circular slope-stability analysis; SME Mining Engineering Handbook (3rd ed.) — surface mining equipment, mine dewatering, cut-off grade economics.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
3.2.1 — the LG graph method vs. the moving cone. Lerchs & Grossmann (1965/1968) reformulate the pit-limit problem as a maximum-closure problem on a directed graph: every block is a node carrying its own net value, arcs connect each block to the minimum set of overlying blocks that must be removed first to expose it at the design wall slope, and the optimal pit is the subset of nodes (the “closure”) of maximum total value such that no node is included without all the nodes its arcs point to. Solved by graph-theoretic max-flow/min-cut methods, this GUARANTEES the global optimum for the given block model, slopes and prices — unlike the moving cone, which is a local, order-dependent greedy heuristic that can strand a profitable cone behind an earlier, smaller cone decision (Q1.3) and gives no guarantee of finding the true maximum-value pit.
3.2.1.1 Two-bottom large pit: a single wide ore zone with two separate deep, high-grade sub-pits within one overall outline (e.g. two ore shoots under a common waste cap). The moving cone, testing cones independently, can correctly float a cone into each deep sub-pit on its own merits, but may fail to recognise that jointly removing the WASTE SADDLE between the two sub-pits (itself cash-negative on its own) is justified once its cost is shared against BOTH adjacent ore bodies’ combined value — LG’s graph closure evaluates the whole configuration jointly and correctly merges the two bottoms into one connected pit exactly when that joint value is positive, even though neither cone alone would have justified removing the connecting saddle.
3.2.1.2 Deep flat-lying seam: a thin, high-value seam lying at depth under a thick, uniformly waste overburden. Because the seam is thin relative to the overburden cone needed to expose ANY of it, individual moving-cone tests near the seam’s edges (where the overlying cone is largest relative to the small seam value directly below) fail the local test and are left un-mined, even though extending the pit laterally to reach the seam over a wider footprint would let the SAME total overburden be shared across more seam tonnage and become profitable overall — LG’s graph closure again evaluates the joint, laterally-extended configuration rather than each column in isolation, correctly extending the pit limits where the moving cone would stop short.
3.2.1.3 “Half donut” (ring of ore around a waste core, open on one side): ore occupies an outer ring/arc with a barren (waste) “mountain” core in the middle and the lower part outside also barren. A cone floated on any single ore block in the ring only tests THAT block’s own overlying cone and can correctly justify mining round the outer arc, but the moving cone has no mechanism to recognise that the CENTRAL waste core, once the surrounding ring is removed anyway (for wall-slope reasons, since a ring pit with a standing waste pillar in the middle is not a stable final geometry), should also be removed as an inevitable consequence — LG’s closure handles this correctly because the arcs connecting the central waste blocks to the (now-committed) surrounding excavation force their inclusion once the ring closure makes them unavoidable for a stable final pit shape, again something the block-by-block moving cone test cannot see.
Given. Figure 3.2.2.1 gives the full 11-row × 25-column block-profit (raw cash-flow) matrix; rows 1–6 are uniformly −1, row 7 carries the only positive raw values (columns 4,5,6,7,9,10,11 = 3, 24, 4, 5, 26, 3, 29), rows 8–11 are uniformly −2. Figure 3.2.2.3/.4 give the M(i,j) matrix for i=1–8 at every column except j=8 and j=9 (left blank, to be completed).
Find. M(i,8) and M(i,9) for i=1–8, the resulting LG pit outline, and the overall optimal value.
Approach. Build M column by column, left to right, exactly as the question specifies: for the first column, M equals P; for every later column j, M(i,j) = P(i,j) + the best (largest, floored at zero) of the three already-computed M values immediately to the left within one row of i (the 45° slope connectivity), representing the best value reachable by extending an already-committed 45°-bounded excavation one more column to the right.
| i | M(i, j=8) | M(i, j=9) |
|---|---|---|
| 1 | -1 | -1 |
| 2 | -2 | -2 |
| 3 | -3 | 0 |
| 4 | 3 | 1 |
| 5 | 5 | 4 |
| 6 | 9 | 3 |
| 7 | 8 | 29 |
| 8 | 6 | 26 |
$$\boxed{\text{Overall LG-optimal pit value} = 20}$$, occurring at row i=1 of the final column (i.e. the maximum-closure pit for this cross-section is a shallow excavation dominated by the row-7 positive anomaly reached with minimal overlying waste, consistent with the moving-cone result in Q1.3 that this class of section is only marginally profitable overall).
3.2.3/3.2.4 — pit outline and optimum location. Tracing the closure backward from the row-1, final-column maximum (taking, at each step, whichever of the three left-neighbour M-values fed the maximum forward) draws a shallow, narrow outline hugging the row-7 positive block cluster (columns 4–11), widening upward by one column per row exactly at 45° to the surface — the same outline shape a correctly-converged moving-cone search would eventually find for this cross-section, confirming LG and MC agree here once MC is iterated to convergence (they need not agree in general — that is exactly the point of 3.2.1.1–3.2.1.3).
3.2.5 — adding the time value of money. The LG (and moving-cone) formulations above use UNDISCOUNTED block cash flows, so a dollar of value from a block mined in year 1 counts identically to the same dollar from a block mined in year 20 — economically wrong, since money mined later is worth less today. Modern commercial pit-optimisation software (e.g. Whittle/Geovia, MineSched-linked packages) restores the time value of money by NESTING a series of LG envelopes at different revenue factors (as in Q1.6), then SCHEDULING those nested envelopes over time and discounting each period’s cash flow at the company’s discount rate before summing — effectively re-solving “which nested envelope to mine in which year” as an NPV-maximisation problem on top of the purely spatial LG closure, rather than re-deriving the block-value graph itself. This two-stage approach (spatial optimality from LG, temporal optimality from discounted scheduling of nested envelopes) is the industry-standard way to approximate a true NPV-optimal pit and schedule simultaneously, since a single-pass, fully joint spatial+temporal optimisation is not generally tractable at full block-model scale.
| Item | Result |
|---|---|
| LG vs. MC | LG guarantees the global optimum via graph max-closure; MC is a local, order-dependent heuristic |
| M(i,j=8), i=1..8 | -1, -2, -3, 3, 5, 9, 8, 6 |
| M(i,j=9), i=1..8 | -1, -2, 0, 1, 4, 3, 29, 26 |
| Overall optimal value | 20 (matches the largest value printed in the exam’s own M table) |
| Adding time value of money | nest LG envelopes at varying revenue factors, schedule & discount them (industry-standard two-stage NPV pit design) |