Question 4 of 6: Copper-Ore Final-Wall Control Program
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
National Exams, 09-Mmp-B2 Rock Fragmentation, December 2016, 3 hours, closed book
(one double-sided aid sheet permitted). Question 1 plus four (4) of Questions 2-6
constitute a complete paper; every question (1-6) is answered in
full as a complete study resource.
Reference texts: Persson, Holmberg & Lee, Rock Blasting and
Explosives Engineering; C.J. Konya & E.J. Walter, Rock Blasting and Overbreak
Control (FHWA); ISEE, Blasters' Handbook, 18th ed.; W. Hustrulid,
Blasting Principles for Open Pit Mining; SME Mining Engineering Handbook,
3rd ed., Ch. Drilling and Blasting; W.I. Duvall & C.F. Fogelson, USBM RI 5514
(cratering theory); D.E. Siskind et al., USBM RI 8507 (vibration/airblast).
Question 4: Copper-Ore Final-Wall Control Program (21 marks)
Find. Burden, spacing and charging for a buffer row plus a final (wall
control) row that limit overbreak/backbreak as the pit approaches its final wall.
Approach. Adopt the minimum permitted diameter (165 mm) for BOTH rows
– a smaller final-wall diameter gives tighter spacing/burden and hence finer control, and
sharing one diameter with the buffer row lets both be drilled with the same rig. Scale the
buffer row's burden/spacing down from the production pattern by the diameter ratio (same
similarity argument as Q2/Q3). Design the final row as a presplit line
(the standard wall-control method for hard, massive rock, UCS 140 MPa) using the
established smooth-blasting spacing rule and a lightly decoupled charge.
Buffer row (transition from production to wall control). Scale the 9 m
production pattern down by the diameter ratio:
$$\frac{De_{wall}}{De_{prod}}=\frac{165}{311}=0.531$$
$$B_{buf}=S_{buf}=9.0(0.531)=\boxed{4.77\ \text{m}\ (\approx4.8\ \text{m})}$$
This preserves the production powder factor at the smaller diameter, giving the buffer row a
normal (not heavily reduced) charge that still breaks its own rock cleanly while beginning to
step the pattern down toward the tighter final-row geometry.
Final (presplit) row spacing. Standard smooth-blasting/presplit guidance
sets perimeter-hole spacing at 10–12×De:
$$S_{final}=10\text{–}12\times0.165=1.65\text{–}1.98\ \text{m}\ \Rightarrow\
\boxed{S_{final}\approx1.8\ \text{m}}$$
Final-row burden from the buffer row. A presplit line is fired with
little or no relief (often ahead of the whole round), so its own "burden" toward the buffer
row is kept smaller than the buffer row's own burden to avoid over-stressing the presplit
plane before it has done its job:
$$B_{final}\approx0.8\times B_{buf}=0.8(4.77)=\boxed{3.82\ \text{m}\ (\approx3.8\ \text{m})}$$
Final-row (presplit) charge. Use a lightly decoupled column (small-diameter
cartridge or detonating cord load well inside the 165 mm hole, decoupling ratio
dc/dh≈0.2–0.3) rather than a fully-coupled production charge
– enough energy to create a continuous shear/tension crack along the row without the
overbreak-driving borehole pressure of a full charge:
$$P_{borehole}=P_{detonation}\left(\frac{d_c}{d_h}\right)^{2.4}$$
Air-deck or leave the top ≈1–1.5 m uncharged to control collar fracturing (same
mechanism discussed in Q1(e)).
Row
Diameter
Burden
Spacing
Charge
Production (existing)
311 mm
9.0 m
9.0 m
full column
Buffer
165 mm
4.8 m
4.8 m
full column, De-scaled powder factor
Final (presplit)
165 mm
3.8 m
1.8 m
decoupled, dc/dh≈0.2–0.3 + top air-deck
Timing: fire the presplit (final) line FIRST – simultaneously or on a
very short interval (0–3 ms via detonating cord) along its own length, before or with
minimal lead-time ahead of the rest of the round – so the crack plane forms while the rock
is still fully confined and undisturbed by adjacent blasting. The buffer row then fires as part
of the main sequence (25–42 ms after the presplit line), with its charge and timing
chosen so shock transmitted toward the already-formed presplit plane is kept low, protecting the
final wall from further damage. The rest of the production pattern fires in its normal diagonal
echelon sequence, retreating away from the wall toward the pit's open face.
Fig. Q4(b) – wall-control cross-section: production, buffer and
final (presplit) rows approaching the 80° final pit wall.
Check: no explosive VOD/density is given for a dedicated perimeter
product, so the decoupling ratio (0.2–0.3) and air-deck length are stated as standard
industry design guidance rather than back-calculated from a specific product; the buffer/final
row BURDEN AND SPACING values above follow directly from the given diameter constraint and
established scaling/spacing rules.
(b) Sketch of loading and design
See Fig. Q4(b) above: three drilled rows are shown in cross-section approaching the final
80° pit wall – the existing 311 mm production pattern (full column charge, B=S=9 m),
a 165 mm buffer row (full column, De-scaled burden ≈4.8 m) that steps the pattern
down, and a 165 mm final row fired as a presplit line (tight 1.8 m spacing, decoupled
charge with a top air-deck) directly against the intended final wall. The presplit row is drawn
with a dashed fire line to indicate it is initiated first/independently of the main round.