NivaarExam PrepOfficial exam papers ↗

24-MMP-B5 Mineral Processing Design and Operations · May 2016

Question 5 of 8: Preliminary fixed capital cost and capacity-expansion cost

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Exam 09-MMP-B5, Mill Design & Operations — May 2016, 3 hours. Candidates were instructed to answer any 6 of the 8 questions (each of equal value); all 8 are solved below as a complete study resource.

Reference texts: Wills' Mineral Processing Technology (B.A. Wills & J. Finch, 8th ed., Butterworth-Heinemann) — Ch. 4 Comminution, Ch. 8 Screening, Ch. 9 Classification, Ch. 12 Froth Flotation, Ch. 14 Solid-Liquid Separation; Mular, Halbe & Barratt (eds.), Mineral Processing Plant Design, Practice and Control (SME, 2002); Mular & Poulin, CIM Special Volume 47 (1998) preliminary capital cost estimation; SME Mining Engineering Handbook (3rd ed.).

Question 5: Preliminary fixed capital cost and capacity-expansion cost (5/6)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. Equipment cost ratio table above (factor $F_1$ and current purchased cost per category). Future capacity ratio $1.30$; M&S escalation ratio $1.25$ over the same 5-year horizon.

Find. (a) Preliminary total fixed capital cost. (b) Preliminary cost of the facility at the expanded capacity, in future (escalated) dollars.

Approach. The equipment-cost-ratio (factored/Lang-type) method installs each equipment category by multiplying its own purchased cost by its own factor, then sums across categories; the six-tenths rule then rescales the whole facility to the new capacity and re-escalates by the M&S index ratio.

  1. Installed cost per category. $\text{Installed}_i = F_{1,i}\times\text{Cost}_i$: $$\begin{aligned} \text{Crushers} &= 3.5\times2{,}500{,}000 = \$8{,}750{,}000 \\ \text{Electric motors} &= 8.5\times700{,}000 = \$5{,}950{,}000 \\ \text{Conveyors} &= 2.3\times500{,}000 = \$1{,}150{,}000 \\ \text{Dust collectors} &= 3.5\times1{,}000{,}000 = \$3{,}500{,}000 \\ \text{Screens} &= 2.3\times120{,}000 = \$276{,}000 \\ \text{Instrumentation} &= 4.1\times850{,}000 = \$3{,}485{,}000 \\ \text{Non-specified equip.} &= 3.0\times750{,}000 = \$2{,}250{,}000 \end{aligned}$$
  2. Sum for total fixed capital. $$\text{Fixed capital} = \boxed{\$25{,}361{,}000}$$
  3. Six-tenths-rule scale-up for the 30% capacity increase. $$\text{Cost}_2 = \text{Cost}_1\left(\frac{\text{Capacity}_2}{\text{Capacity}_1}\right)^{0.6}=25{,}361{,}000\times(1.30)^{0.6}=25{,}361{,}000\times1.1705=\$29{,}686{,}000$$
  4. Escalate to future dollars via the M&S index. $$\text{Cost}_2^{\text{escalated}} = 29{,}686{,}000\times1.25=\boxed{\$37{,}106{,}000}$$ For reference, escalating the ORIGINAL (unexpanded) facility by the same M&S ratio alone gives $25{,}361{,}000\times1.25=\$31{,}701{,}000$; the incremental cost attributable purely to the 30% capacity increase is therefore $37{,}106{,}000-31{,}701{,}000\approx\$5{,}405{,}000$.
Final Results — Question 5
QuantityValue
Preliminary fixed capital cost (present)USD 25,361,000
Facility cost at expanded (130%) capacity, future dollarsUSD 37,106,000
Incremental cost of the capacity increase alone≈ USD 5,405,000