24-MMP-B5 Mineral Processing Design and Operations · May 2016
Question 5 of 8: Preliminary fixed capital cost and capacity-expansion cost
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
National Exam 09-MMP-B5, Mill Design & Operations — May 2016, 3 hours. Candidates were instructed to answer any 6 of the 8 questions (each of equal value); all 8 are solved below as a complete study resource.
Reference texts: Wills' Mineral Processing Technology (B.A. Wills & J. Finch, 8th ed., Butterworth-Heinemann) — Ch. 4 Comminution, Ch. 8 Screening, Ch. 9 Classification, Ch. 12 Froth Flotation, Ch. 14 Solid-Liquid Separation; Mular, Halbe & Barratt (eds.), Mineral Processing Plant Design, Practice and Control (SME, 2002); Mular & Poulin, CIM Special Volume 47 (1998) preliminary capital cost estimation; SME Mining Engineering Handbook (3rd ed.).
Question 5: Preliminary fixed capital cost and capacity-expansion cost (5/6)
Given. Equipment cost ratio table above (factor $F_1$ and current purchased cost per category). Future capacity ratio $1.30$; M&S escalation ratio $1.25$ over the same 5-year horizon.
Find. (a) Preliminary total fixed capital cost. (b) Preliminary cost of the facility at the expanded capacity, in future (escalated) dollars.
Approach. The equipment-cost-ratio (factored/Lang-type) method installs each equipment category by multiplying its own purchased cost by its own factor, then sums across categories; the six-tenths rule then rescales the whole facility to the new capacity and re-escalates by the M&S index ratio.
Sum for total fixed capital.
$$\text{Fixed capital} = \boxed{\$25{,}361{,}000}$$
Six-tenths-rule scale-up for the 30% capacity increase.
$$\text{Cost}_2 = \text{Cost}_1\left(\frac{\text{Capacity}_2}{\text{Capacity}_1}\right)^{0.6}=25{,}361{,}000\times(1.30)^{0.6}=25{,}361{,}000\times1.1705=\$29{,}686{,}000$$
Escalate to future dollars via the M&S index.
$$\text{Cost}_2^{\text{escalated}} = 29{,}686{,}000\times1.25=\boxed{\$37{,}106{,}000}$$
For reference, escalating the ORIGINAL (unexpanded) facility by the same M&S ratio alone gives $25{,}361{,}000\times1.25=\$31{,}701{,}000$; the incremental cost attributable purely to the 30% capacity increase is therefore $37{,}106{,}000-31{,}701{,}000\approx\$5{,}405{,}000$.
Final Results — Question 5
Quantity
Value
Preliminary fixed capital cost (present)
USD 25,361,000
Facility cost at expanded (130%) capacity, future dollars