Question 2 of 4: Project Scheduling — New Ore Zone Development
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
09-MMP-B8, Mine Management & Systems Analysis — May 2013 sitting. 3-hour closed-book exam, answer all questions, Appendix A (discounted cash-flow factor tables) attached.
Reference texts. Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (pit optimization, truck/shovel matching, mine scheduling); Hartman & Mutmansky (eds.), SME Mining Engineering Handbook (mine life-cycle, project economics); Blank & Tarquin, Engineering Economy (DCF/NPV/PVR/payback); Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide) (Critical Path Method).
Check: the exam booklet is headed “09-MMP-B8 Mine Management & Systems Analysis”, not Rock Slope Engineering — the content below solves the paper as printed. Also: only Questions 1, 3, 4 and 5 exist anywhere in the 6-page exam booklet — the cover sheet instructs “ANSWER ALL 5 QUESTIONS FOR A TOTAL OF 100 MARKS” and each question is marked out of 20, but no Question 2 appears on any page between Question 1 (ending “2 of 6”) and Question 3 (starting on page 3). This is a genuine gap in the original exam booklet — all four questions that DO exist are answered in full below (80 of the stated 100 marks).
Question 3: Project Scheduling — New Ore Zone Development (20 marks)
New Ore Zone Development — task list and dependencies
#
Task description
Duration (months)
Depends on task #
1
Drive new ramp Phase A
8
none
2
Develop new shaft for hoisting and ventilation
36
1
3
Drive new ramp Phase B
12
1
4
Develop new u/g exploration drilling gallery
2
1
5
Complete u/g exploration drilling program, ore body model and mining schedule
18
4
6
Reconfigure mine ventilation system for new zone
4
3
7
Expand u/g diesel powered equipment fleet
4
6
8
Develop upper mining level for new zone
12
7
9
Develop lower mining level for new zone
14
3
10
Develop slot raises for initial stope blocks
2
8, 9
11
Drill open stoping blastholes for initial 2 stopes
1
10, 5
12
First production from stopes in new zone
0 (milestone)
11, 2
Find. (a) the sequence of tasks forming the critical path; (b) the shortest project duration; (c) every non-critical task and why it isn't critical (its total float).
Approach. Build the activity-on-node network from the given dependencies, run a forward pass to get each task's earliest start/finish (ES/EF), then a backward pass from the project finish to get each task's latest start/finish (LS/LF); the critical path is the chain of tasks with zero total float (LS−ES = 0), and every other task's float is how many months it can slip without delaying the milestone (Task 12).
Forward pass (ES/EF). $ES$ of a task is the largest $EF$ among its predecessors ($ES=0$ for Task 1). Task 1: ES 0, EF 8. Task 2 (dep. 1): ES 8, EF 44. Task 3 (dep. 1): ES 8, EF 20. Task 4 (dep. 1): ES 8, EF 10. Task 5 (dep. 4): ES 10, EF 28. Task 6 (dep. 3): ES 20, EF 24. Task 7 (dep. 6): ES 24, EF 28. Task 8 (dep. 7): ES 28, EF 40. Task 9 (dep. 3): ES 20, EF 34. Task 10 (dep. 8, 9): $ES=\max(40,34)=40$, EF 42. Task 11 (dep. 10, 5): $ES=\max(42,28)=42$, EF 43. Task 12 (dep. 11, 2): $$\boxed{ES_{12}=\max(43,44)=44\ \text{months} = \text{project duration}}$$
Backward pass (LS/LF). Starting from $LF_{12}=44$ and working back, $LS$ of a task is the smallest $LS$ among its successors minus its own duration. Task 12: LF 44, LS 44. Task 11 (feeds 12): LF 44, LS 43. Task 2 (feeds 12): LF 44, LS 8. Task 10 (feeds 11): LF 43, LS 41. Task 8 (feeds 10): LF 41, LS 29. Task 9 (feeds 10): LF 41, LS 27. Task 7 (feeds 8): LF 29, LS 25. Task 6 (feeds 7): LF 25, LS 21. Task 5 (feeds 11): LF 43, LS 25. Task 3 (feeds 6 and 9): $LF=\min(21,27)=21$, LS 9. Task 4 (feeds 5): LF 25, LS 23. Task 1 (feeds 2, 3, 4): $$LF_1=\min(8,9,23)=8,\qquad LS_1=8-8=0$$
The result is a little counter-intuitive: the longest-looking chain of individual activities is the exploration/drilling → slot-raise → blasthole path (Tasks 1→3→9→10→11→12, or 1→4→5→11→12), but neither is critical — the single, standalone 36-month shaft-sinking activity (Task 2), which depends on nothing but the initial ramp, is the true bottleneck because nothing else can start production until both the shaft AND the full underground development chain are ready, and the shaft alone already takes as long as the whole development chain. The tightest non-critical branch (Tasks 3→6→7→8→10→11, ventilation/equipment/upper-level) has only 1 month of float and needs close monitoring even though it is not, strictly, critical.
Question 3 — final results
Item
Result
(a) Critical path
Task 1 → Task 2 → Task 12 (Ramp A → Shaft development → First production)