NivaarExam PrepOfficial exam papers ↗

24-MMP-B8 Rock Slope Engineering · May 2013

Question 3 of 4: Mineral Resource Block Modelling and Pit Limits

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

09-MMP-B8, Mine Management & Systems Analysis — May 2013 sitting. 3-hour closed-book exam, answer all questions, Appendix A (discounted cash-flow factor tables) attached.

Reference texts. Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (pit optimization, truck/shovel matching, mine scheduling); Hartman & Mutmansky (eds.), SME Mining Engineering Handbook (mine life-cycle, project economics); Blank & Tarquin, Engineering Economy (DCF/NPV/PVR/payback); Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide) (Critical Path Method).

Check: the exam booklet is headed “09-MMP-B8 Mine Management & Systems Analysis”, not Rock Slope Engineering — the content below solves the paper as printed. Also: only Questions 1, 3, 4 and 5 exist anywhere in the 6-page exam booklet — the cover sheet instructs “ANSWER ALL 5 QUESTIONS FOR A TOTAL OF 100 MARKS” and each question is marked out of 20, but no Question 2 appears on any page between Question 1 (ending “2 of 6”) and Question 3 (starting on page 3). This is a genuine gap in the original exam booklet — all four questions that DO exist are answered in full below (80 of the stated 100 marks).

Question 4: Mineral Resource Block Modelling and Pit Limits (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. Block dimensions 10 m × 10 m × 10 m; ore and waste density 3000 kg/m³; grade cutoff 1.5%; net mineral value $4200/tonne of recovered mineral; mine recovery 100%, mill recovery 95%; mining cost $20/t, milling cost $15/t (ore only), overhead cost $15/t. The geological block model (percent grade, “nil” = no assay/zero grade) is given as a 5-row × 8-column cross-section:

Fig. 4.1(a) Geological Block Model (% Au-equiv. grade)nilnil2%3%4%3%1%1%nilnil1%4%4%nil1%nilnilnil1%4%nil3%nilnil1%1%1%2%3%1%nilnilnil1%1%2%2%1%nilnilrow 1 = surface bench (top) … row 5 = deepest bench (bottom)1234567812345
Fig. 4.1(a) — Geological block model (percent grade), as given. Row 1 = surface bench, row 5 = deepest bench.

Find. (a) the equivalent economic block model (dollar value per block); (b) the optimum 2-D pit outline; (c) the net economic value of that pit.

Approach. Convert each block's grade to a dollar value using the cutoff rule (below cutoff → classified waste, cost only; at/above cutoff → classified ore, net revenue), then solve the 2-D pit-limit problem as a column-envelope optimisation: for every column, choose how many benches deep to mine so that the sum of the included blocks' dollar values is maximised, subject to a 45° wall-slope constraint (adjacent columns' mined depths differ by at most one 10 m bench, since block width = block height). This constrained column optimisation is mathematically identical to a Lerchs-Grossmann graph closure (or an exhaustive floating-cone search) restricted to a single 2-D cross-section, and is solved here by dynamic programming rather than by hand-tracing cones, which is both faster and exactly verifiable.

Check: (1) mining and overhead costs are charged on every tonne mined, ore or waste (both must be moved); milling cost is charged only on tonnes that are actually ore (waste is not sent to the mill). (2) The 45° wall constraint is anchored to zero depth at BOTH edges of the given 8-column section (i.e. the pit must not extend beyond the block model as given) — a reasonable reading since the model is presented as a complete, closed cross-section with no indication the deposit continues past column 1 or column 8.
  1. Block tonnage and value formulas. Each block: $10\times10\times10\ \text{m}^3 = 1000\ \text{m}^3$, so mass $=1000\times3.0\ \text{t/m}^3 = 3000\ \text{t}$. For a WASTE block (grade < 1.5%, including “nil”): $$\text{value}_{waste} = -(20+15)\times3000 = -\text{\$}105{,}000$$ For an ORE block (grade $g\% \ge 1.5\%$), contained mineral $=3000\times(g/100)$ t, recovered $=$ contained $\times1.00\times0.95$, revenue $=$ recovered $\times$ \$4200/t, and mining+milling+overhead cost applies to the whole 3000 t block: $$\text{value}_{ore}(g) = 3000\times\tfrac{g}{100}\times0.95\times4200 - (20+15+15)\times3000 = 119{,}700\,g - 150{,}000$$
  2. Classify and value every block. Applying the cutoff: all “nil” and 1% blocks are WASTE (−\$105,000 each, even the 1% ones — sub-cutoff mineralization still costs money to move). The 2%, 3% and 4% blocks are ORE: $$\text{value}(2\%)=+\text{\$}89{,}400,\quad \text{value}(3\%)=+\text{\$}209{,}100,\quad \text{value}(4\%)=+\text{\$}328{,}800$$ giving the economic block model in Fig. 4.1(b).
Fig. 4.1(b) Economic Block Model (USD per block)-105.0k-105.0k+89.4k+209.1k+328.8k+209.1k-105.0k-105.0k-105.0k-105.0k-105.0k+328.8k+328.8k-105.0k-105.0k-105.0k-105.0k-105.0k-105.0k+328.8k-105.0k+209.1k-105.0k-105.0k-105.0k-105.0k-105.0k+89.4k+209.1k-105.0k-105.0k-105.0k-105.0k-105.0k-105.0k+89.4k+89.4k-105.0k-105.0k-105.0krow 1 = surface bench (top) … row 5 = deepest bench (bottom)1234567812345
Fig. 4.1(b) — Economic block model (US$ per 3000 t block). Green = positive-value ore block, pink = negative-value waste block.
  1. Column profit-vs-depth (prefix sums). For each of the 8 columns, sum block values from the surface (row 1) down to depth $d$ (0–5 rows), $P(d,\text{col})$. Columns 1, 2, 7 and 8 are all-waste and best left unmined ($P$ decreases monotonically with $d$, maximum at $d=0$). Column 4 (the richest) increases every step to $P(5)=+\text{\$}1{,}045{,}500$. Column 5 dips at $d=3$ (a buried “nil” block) but recovers by $d=5$. Column 3 peaks early at $d=1$ ($+\text{\$}89{,}400$) then turns negative. Column 6 peaks at $d=3$ ($+\text{\$}313{,}200$).
  2. Envelope optimisation with the 45° slope constraint. A pure “mine every column to its own local best depth” choice (col 3 to depth 1, col 4 to depth 5, col 5 to depth 5…) would violate the slope constraint between neighbouring columns and is not a buildable pit wall. Solving the constrained dynamic program (mined depth per column $d_j$, $|d_j-d_{j-1}|\le1$, anchored to $d=0$ at both section edges) for the depth sequence that maximises the total of the included column prefix-sums gives: $$\boxed{d_1..d_8 = 0,\ 1,\ 2,\ 3,\ 2,\ 1,\ 0,\ 0\ \text{benches}}$$ Column 2 is taken one bench deep (a losing, $-\text{\$}105{,}000$ waste block) purely to satisfy the slope constraint into column 3's valuable material below — a smaller local loss that unlocks a much larger gain two columns over, exactly the trade-off Lerchs-Grossmann graph closure is designed to find.
Fig. 4.1(c) Optimum Pit Outline (2-D envelope, 45° wall)-105.0k-105.0k+89.4k+209.1k+328.8k+209.1k-105.0k-105.0k-105.0k-105.0k-105.0k+328.8k+328.8k-105.0k-105.0k-105.0k-105.0k-105.0k-105.0k+328.8k-105.0k+209.1k-105.0k-105.0k-105.0k-105.0k-105.0k+89.4k+209.1k-105.0k-105.0k-105.0k-105.0k-105.0k-105.0k+89.4k+89.4k-105.0k-105.0k-105.0krow 1 = surface bench (top) … row 5 = deepest bench (bottom)shaded = mined; green = ore mined, amber = waste mined inside the pit envelope, grey = left in place1234567812345
Fig. 4.1(c) — Optimum pit outline. Shaded blocks are mined (green = ore, amber = waste taken inside the pit envelope to hold a buildable 45° wall); grey blocks are left in place.
  1. Net economic value of the optimum pit. Summing the included blocks' values column by column ($0 + (-105{,}000) + (-15{,}600) + 866{,}700 + 657{,}600 + 209{,}100 + 0 + 0$, using each column's own prefix sum at its chosen depth): $$\boxed{\text{Net pit value} = \text{\$}1{,}612{,}800}$$ The pit contains 7 ore blocks and 2 waste blocks (9 blocks total, 27,000 t moved), a strip ratio of $2/7\approx0.29{:}1$ waste-to-ore — low, because the slope constraint only forces two extra waste blocks into an otherwise compact, rich pit.
Question 4 — final results
ItemResult
(a) Block value formulasWaste: −$105,000/block; Ore: $119,700×grade% − $150,000/block
(b) Optimum mined depth per column (1–8)0, 1, 2, 3, 2, 1, 0, 0 benches
Blocks mined (ore / waste / total)7 / 2 / 9 (27,000 t)
Strip ratio (waste:ore)0.29 : 1
(c) Net economic value of the optimum pit$1,612,800