NivaarExam PrepOfficial exam papers ↗

22-Agric-A2 Soil Physics and Mechanics · December 2013

Question 7 of 7: Effective Stress Beneath a Sand-and-Clay Site, Before and After Construction

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. 04-Agric-A2 Soil Physics & Mechanics, National Exams December 2013 — a three-hour open-book examination; any non-communicating calculator is permitted. The cover page states that five (5) questions constitute a complete exam paper and that only the first five as they appear in the answer book are marked, that each question is of equal value, and that some questions require a written answer whose clarity and organization matter for marks. All seven printed questions are worked here, because the set is a study resource rather than a timed attempt; on exam day a candidate submits only the first five, in order.

Reference texts. B.M. Das, Principles of Geotechnical Engineering, 9th ed. (weight-volume relationships, permeability, effective stress, compaction); R.F. Craig, Craig's Soil Mechanics, 9th ed. (seepage, effective stress, shear strength, consolidation); G.O. Schwab et al., Soil and Water Conservation Engineering, 5th ed. (drainage, infiltration, dewatering design); USDA NRCS National Engineering Handbook (field methods for hydraulic conductivity and infiltration).

Question 7: Effective Stress Beneath a Sand-and-Clay Site, Before and After Construction (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given.

QuantityValue
Original profile0–2 m sand, 2–7 m clay
Original water table depth4.0 m
Excavationremove top 1.0 m of sand
Building dead load (surcharge)48 kN/m²
γdry,sand / γsat,sand15.7 / 19.6 kN/m³
γdry,clay / γsat,clay16.7 / 17.9 kN/m³

Find. Total stress σ, pore pressure u, and effective stress σ′ at the bottom of the clay layer, in each of the three stages.

Approach. With no "moist" unit weight given, use γdry for soil above the water table and γsat below it, sum γ×thickness down to the bottom of the clay for σ, get u = γw×(depth below the water table), and take σ′ = σ − u. Stage (c) additionally requires recognizing that, immediately after construction, a saturated clay carries a fresh surface load undrained.

Original G.S.SandClay7 m▽ W.T.New G.S.SandClay6 m▽ W.T.48 kN/m² (building)
Left: original profile (sand 0–2 m, clay 2–7 m, W.T. at 4 m). Right: after removing 1 m of sand the ground surface drops 1 m but the water table's absolute elevation is unchanged, so it now sits 3 m below the new surface; the building's 48 kN/m² dead load is then applied at the new surface.
  1. a) Prior to any work. Above the 4 m water table: 2 m dry sand + 2 m dry clay; below it: 3 m saturated clay down to the 7 m base: $$\sigma = \gamma_{d,\text{sand}}(2) + \gamma_{d,\text{clay}}(2) + \gamma_{sat,\text{clay}}(3) = 15.7(2)+16.7(2)+17.9(3) = \boxed{118.5\ \text{kPa}}$$ $$u = \gamma_w(7-4) = 9.81(3) = \boxed{29.43\ \text{kPa}}, \qquad \sigma' = \sigma - u = 118.5-29.43 = \boxed{89.07\ \text{kPa}}$$
  2. b) After excavating 1 m of sand. The water table's elevation is unchanged, so it is now only 3 m below the new (lower) surface; the clay base is still 3 m below the water table (that vertical distance is fixed by the clay-base and water-table elevations, neither of which moved), while the profile above the W.T. has lost 1 m of sand: $$\sigma = \gamma_{d,\text{sand}}(1) + \gamma_{d,\text{clay}}(2) + \gamma_{sat,\text{clay}}(3) = 15.7(1)+16.7(2)+17.9(3) = \boxed{102.8\ \text{kPa}}$$ $$u = \gamma_w(3) = 29.43\ \text{kPa}\ (\text{unchanged: still 3 m below the W.T.}), \qquad \sigma' = 102.8-29.43 = \boxed{73.37\ \text{kPa}}$$ Removing overburden lowers both σ and σ′ (u is unaffected because it depends only on depth below the water table) — the clay is unloaded and tends to rebound/swell, exactly the "stress relief" a preload fill (Question 3c) is meant to guard against re-occurring under later construction.
  3. c) Immediately after construction. The building's 48 kPa dead load is applied at the new surface. Check: assumes a saturated clay responds to a sudden surface load essentially undrained immediately after construction (Skempton B ≈ 1), so the entire stress increment initially appears as excess pore pressure rather than as a change in effective stress. Total stress rises by the full surcharge; pore pressure rises by the same amount (Δu = Δσ); effective stress is therefore, for this instant, unchanged from stage (b): $$\sigma = 102.8+48 = \boxed{150.8\ \text{kPa}}, \qquad u = 29.43+48 = \boxed{77.43\ \text{kPa}}$$ $$\sigma' = 150.8-77.43 = \boxed{73.37\ \text{kPa}}\ (\text{unchanged from stage b})$$ Over time, as this excess pore pressure dissipates through consolidation, u will fall back toward its hydrostatic value (29.43 kPa) and σ′ will rise to 150.8−29.43 = 121.4 kPa, producing the settlement a preload strategy is designed to pre-empt.
Stageσ (kPa)u (kPa)σ′ (kPa)
(a) Prior to any work118.529.4389.07
(b) After excavating 1 m sand102.829.4373.37
(c) Immediately after construction150.877.4373.37