24-Bld-A3 Construction Engineering · Undated paper
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Examinations — 07-Bld-A3, May 2019 — Construction Engineering. Closed book; candidates may use one of the two approved calculators (Casio or Sharp). The paper prints seven questions of equal value (20 marks each) and states that any five questions constitute a complete paper, only the first five appearing in the answer book being marked. Candidates are urged to record any interpretive assumptions with their answers. All seven questions are worked below, because the set is intended as a study resource rather than as a single exam sitting.
Reference texts: Hendrickson, C. & Au, T., Project Management for Construction (2nd ed., Carnegie Mellon) — precedence networks with SS/FS lags, cash-flow financing, contract types; Halpin, D.W. & Senior, B.A., Construction Management (4th ed., Wiley) — CPM/LOB scheduling, formwork & equipment production, bonding and cash flow; Canadian Construction Documents Committee, CCDC 2 — Stipulated Price Contract (2020) — contract clauses, addenda, change orders, holdback; Canadian Foundation Engineering Manual (CFEM) & WorkSafeBC Occupational Health and Safety Regulation, Part 20 — excavation support and shoring.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Line-of-Balance vs. CPM. LOB plots each repetitive trade as a single sloped line (or band) across a floor/unit-vs-time chart, where the slope is that trade's production rate (units per day), instead of drawing every floor's activities as separate CPM nodes. Pros: it shows crew continuity directly (a flat, unbroken line means the crew never sits idle between floors), it makes the controlling (slowest) trade visually obvious as the one whose line is least steep, and it scales to buildings with many repeated floors without the network exploding into hundreds of near-identical CPM activities. Cons: it assumes each trade's output rate is steady and known in advance, which fits highly repetitive vertical construction (floor-by-floor fit-out) far better than one-off or highly interdependent scopes; and because it hides the detailed logic between individual tasks on a single floor, it is a poor substitute for CPM where complex, non-repetitive precedence (not just "trade X follows trade Y up the building") drives the schedule.
Given. 10 floors, each needing four sequential tasks A→B→C→D; every task takes 2 days to complete on one floor; the tasks' floor-delivery rates are $r_A=1$, $r_B=2$, $r_C=1$, $r_D=0.5$ floors/day.
Find. The crew count each task needs to sustain its stated rate, the resulting floor-by-floor schedule, and the overall project duration; then sketch the schematic LOB chart.
Approach. A task needs enough crews working in parallel, offset by $1/rate$ days, to keep delivering a new floor every $1/rate$ days despite each floor taking a full 2-day duration: crews $= duration \times rate$. Each floor's start on a task is the later of (i) when the previous task finished that same floor, and (ii) when this task's own crew(s) finished the previous floor.
| Task | Rate (floors/day) | Crews needed | Floor 1 (start→finish) | Floor 10 (start→finish) |
|---|---|---|---|---|
| A | 1 | 2 | day 0 → 2 | day 9 → 11 |
| B | 2 | 4 | day 2 → 4 | day 11 → 13 |
| C | 1 | 2 | day 4 → 6 | day 13 → 15 |
| D | 0.5 | 1 | day 6 → 8 | day 24 → 26 |
| Overall project duration = 26 days | ||||