24-Bld-A3 Construction Engineering · Undated paper
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Examinations — 07-Bld-A3, May 2019 — Construction Engineering. Closed book; candidates may use one of the two approved calculators (Casio or Sharp). The paper prints seven questions of equal value (20 marks each) and states that any five questions constitute a complete paper, only the first five appearing in the answer book being marked. Candidates are urged to record any interpretive assumptions with their answers. All seven questions are worked below, because the set is intended as a study resource rather than as a single exam sitting.
Reference texts: Hendrickson, C. & Au, T., Project Management for Construction (2nd ed., Carnegie Mellon) — precedence networks with SS/FS lags, cash-flow financing, contract types; Halpin, D.W. & Senior, B.A., Construction Management (4th ed., Wiley) — CPM/LOB scheduling, formwork & equipment production, bonding and cash flow; Canadian Construction Documents Committee, CCDC 2 — Stipulated Price Contract (2020) — contract clauses, addenda, change orders, holdback; Canadian Foundation Engineering Manual (CFEM) & WorkSafeBC Occupational Health and Safety Regulation, Part 20 — excavation support and shoring.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. Field-measured average load volume vs. load time, a fixed haul/return/dump/turn time of 3.0 min (i.e. cycle time = load time + 3.0 min), and a 50 min/hr efficiency factor.
| Load time (min) | 0.2 | 0.4 | 0.6 | 0.8 | 1.0 | 1.2 | 1.4 |
|---|---|---|---|---|---|---|---|
| Average load (CY) | 11.4 | 18.7 | 22.7 | 24.8 | 26.1 | 26.8 | 27.2 |
Find. The scraper's production (CY per 50-min hour) at each load time, and the load time that maximizes it.
Approach. A longer load time keeps filling the bowl (more CY per pass) but also lengthens every cycle, so production — volume per unit time, not volume per pass — first rises, peaks, and then falls; compute it at every tabulated load time and locate the peak.
| Load time (min) | Cycle time (min) | Load (CY) | Production (CY/hr) |
|---|---|---|---|
| 0.2 | 3.2 | 11.4 | 178.1 |
| 0.4 | 3.4 | 18.7 | 275.0 |
| 0.6 | 3.6 | 22.7 | 315.3 |
| 0.8 | 3.8 | 24.8 | 326.3 |
| 1.0 | 4.0 | 26.1 | 326.2 |
| 1.2 | 4.2 | 26.8 | 319.0 |
| 1.4 | 4.4 | 27.2 | 309.1 |
| Optimum load time ≈ 0.8–0.9 min; peak production ≈ 326–328 CY/hr | |||