Question 3 of 7: Post-Tensioned Girder — Section and Tendons
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. 16-Civ-B2 Advanced Structural Design, May 2018 — a three-hour examination. The cover page allows design handbooks and textbooks but no notes, states that any five questions constitute a complete paper, that all seven questions carry equal value, and that all loads shown on the figures are unfactored. The mark split printed on page 1 is Q1 (12+6+2), Q2 (12+8), Q3 (12+4+4), Q4 (14+6), Q5 (10+5+5), Q6 (10+4+6) and Q7 (12+8). All seven questions are worked below, because the set is a study resource rather than an answer book.
Design data (page 1, reproduced verbatim). These values are used throughout and are not repeated in every question.
Design data supplied with the paper
Material
Property
Value
Concrete
Cylinder strength $f'_{c}$
30 MPa
Structural steel
$F_{y}$
350 MPa
Reinforcing steel
$f_{y}$
400 MPa
Prestressed concrete
$f_{ci}$ at transfer
35 MPa
$f'_{c}$
50 MPa
Modular ratio $n$
6
$f_{ult}$
1750 MPa
$f_{y}$ (strand)
1450 MPa
$f_{initial}$
1200 MPa
Loss of prestress
240 MPa
Reference texts. The answers are written to the Canadian limit-states codes that Engineers Canada lists for this examination:
CSA S16:19, Design of Steel Structures (with the CISC Handbook of Steel Construction, 11th ed.).
CSA A23.3:19, Design of Concrete Structures (with the Cement Association of Canada Concrete Design Handbook, 4th ed.).
National Building Code of Canada 2020, Part 4, for load combinations.
CSA S6:19, Canadian Highway Bridge Design Code, for the bridge floor of Question 4.
Kulak and Grondin, Limit States Design in Structural Steel, 9th ed.; MacGregor and Bartlett, Reinforced Concrete: Mechanics and Design (Canadian edition); Collins and Mitchell, Prestressed Concrete Structures.
Check — load factors. Page 1 says only that the loads shown are unfactored; it gives no dead-to-live split. Every question below therefore applies a single $\alpha = 1.5$ to the loads printed on the figures (the NBCC live-load factor, which is the conservative reading of an unidentified load) and $\alpha_{D} = 1.25$ to any self weight the solution itself introduces. Mechanisms, section classifications and all interaction equations are independent of that choice; only the magnitudes move with it. State this assumption on the answer paper, as the cover page invites.
Given. Figure 2 shows a 12 m concrete girder on a roller at the left end and built in at the right (marked FIXED END), carrying unfactored point loads of 600 kN at 3 m and 400 kN at 6 m from the roller. The prestressing data from page 1 apply.
Prestressing data and derived allowable stresses
Quantity
Symbol
Value
Strength at transfer
$f'_{ci}$
35 MPa
Strength in service
$f'_{c}$
50 MPa
Jacking stress after anchorage
$f_{pi}$
1200 MPa
Total loss
—
240 MPa
Effective stress
$f_{se}$
960 MPa
Prestress ratio
$\eta = f_{se}/f_{pi}$
0.80
Tension at transfer (Cl 18.3.1)
$f_{ti} = 0.25\sqrt{f'_{ci}}$
1.479 MPa
Compression at transfer
$0.60 f'_{ci}$
21.0 MPa
Tension in service (Cl 18.3.2)
$f_{ts} = 0.50\sqrt{f'_{c}}$
3.536 MPa
Compression in service
$0.45 f'_{c}$
22.5 MPa
Find. A rectangular section whose extreme fibres reach — but do not exceed — the permitted tension at both the transfer and the service stage, together with the strand area and a tendon profile that stays inside the permissible zone all along the member.
Approach. Analyse the propped cantilever for service moments, size the depth from the standard section-modulus inequality, then write the two governing tension limits as equalities in the two unknowns $P_{e}/A$ and $P_{e}e/Z$ and solve them simultaneously — "maximum permitted tension" is a two-equation closed-form problem, not an iteration. Convert $P_{e}$ to strands, re-trim the eccentricity for the rounded strand count, and finish by mapping the permissible zone and drawing a parabolic profile inside it.
Check — axial restraint. A post-tensioned member must be free to shorten, or the supports absorb the precompression the tendon is paying for. Here that is satisfied: only the right-hand end is built in, and the left-hand support is drawn as a roller, so the girder can contract freely. The fixity therefore supplies rotational restraint only, and the member is a genuine propped cantilever, once redundant.
Part (a) — analyse the propped cantilever. Taking the cantilever fixed at the right end as the released structure and the prop reaction $R_{A}$ as the redundant, compatibility at the roller gives $$R_{A} = \sum \frac{P b^{2}(3L-b)}{2L^{3}} = \frac{600(9)^{2}(36-9) + 400(6)^{2}(36-6)}{2(12)^{3}} = \frac{1\,744\,200}{3456} = 504.7\ \text{kN}$$ where $b$ is measured from the built-in end. The applied-load moments follow directly: $M = 1514.1$ kN·m under the 600 kN load, $1228.1$ kN·m under the 400 kN load, and $-1743.8$ kN·m at the fixed end, with the point of contraflexure at $x = 8.48$ m.
Add self weight and identify the critical section. The section reached in Step 3 is $400 \times 1500$ mm, weighing $0.4(1.5)(24) = 14.4$ kN/m. For a propped cantilever under a uniform load, $M_{0} = -wL^{2}/8 = -259.2$ kN·m at the fixed end and $+129.6$ kN·m at 3 m. Superposing, $$M_{T} = 2003.0\ \text{kN}\cdot\text{m}\ \text{(hogging, fixed end)}, \qquad M_{T} = 1643.7\ \text{kN}\cdot\text{m}\ \text{(sagging, 3 m)}$$ The built-in end governs, and there the tension face is the top, so the tendon must sit above the centroid at that section.
Size the section. Requiring the transfer compression and the service tension limits to be simultaneously satisfiable gives the standard inequality $$Z \ge \frac{M_{T} - \eta M_{0}}{\eta\,(0.60f'_{ci}) + f_{ts}} = \frac{(2003.0 - 0.80 \times 259.2)\times 10^{6}}{0.80(21.0) + 3.536} = \frac{1795.6 \times 10^{6}}{20.34} = 88.3 \times 10^{6}\ \text{mm}^{3}$$ A $400 \times 1500$ mm rectangle supplies $Z = bh^{2}/6 = 150 \times 10^{6}\ \text{mm}^{3}$ and $A = 600\,000\ \text{mm}^{2}$, comfortably above the requirement. The surplus is deliberate: a depth of $L/8$ keeps the strand count sensible and, as Step 8 shows, keeps the ultimate-strength check under-reinforced.
Write the two tension limits as equalities. Let $X = P_{e}/A$ and $Y = P_{e}e/Z$, and measure both moments as magnitudes about the tension face. Service tension at the top fibre and transfer tension at the bottom fibre give $$X + Y = \frac{M_{T}}{Z} - f_{ts}, \qquad X - Y = \eta\left(-f_{ti} - \frac{M_{0}}{Z}\right)$$ Substituting $M_{T}/Z = 13.353$ MPa and $M_{0}/Z = 1.728$ MPa, $$X + Y = 9.817, \qquad X - Y = -2.565 \;\Rightarrow\; X = 3.626\ \text{MPa}, \quad Y = 6.191\ \text{MPa}$$ Both permitted tensions are reached exactly, which is what the wording of the question asks for.
Recover the prestressing force and eccentricity. $$\begin{gathered}P_{e} = X A = 3.626 \times 600\,000 = 2176\ \text{kN}, \\ e = \frac{Y Z}{P_{e}} = \frac{6.191 \times 150 \times 10^{6}}{2.176 \times 10^{6}} = 427\ \text{mm}\end{gathered}$$ measured above the centroid at the built-in end. With 120 mm to the strand centroid the physical limit is 630 mm, so the cable fits with room to spare.
Part (b) — strand area, then re-trim the eccentricity. The area follows from the effective stress: $$A_{ps} = \frac{P_{e}}{f_{se}} = \frac{2176 \times 10^{3}}{960} = 2266\ \text{mm}^{2} \;\Rightarrow\; 2266/140 = 16.2 \ \text{strands}$$ so provide 17 strands of 15.2 mm diameter ($A_{ps} = 2380\ \text{mm}^{2}$), in two ducts. Rounding up raises the force to $P_{e} = 2380(960) = 2285$ kN, which pushes the transfer stage past its limit unless the eccentricity is pulled back. Re-solving the transfer equation alone with the supplied area, $$Y = X + \eta f_{ti} + \eta\frac{M_{0}}{Z} = 3.808 + 1.183 + 1.382 = 6.373 \;\Rightarrow\; e = 418\ \text{mm}$$ The band that satisfies both stages is then 394.5 to 418.4 mm; adopt $\boxed{e = 410\ \text{mm}}$ above the centroid at the built-in end, a round buildable value inside it. Quoting the trial 427 mm with 17 strands would overshoot the transfer tension — a small slip that a marker will find.
Stress check at the built-in end (compression positive)
Stage and fibre
Computed
Limit
Ratio
Transfer, bottom fibre
−1.318 MPa
−1.479 MPa
0.89
Transfer, top fibre
+10.84 MPa
+21.0 MPa
0.52
Service, top fibre
−3.300 MPa
−3.536 MPa
0.93
Service, bottom fibre
+10.92 MPa
+22.5 MPa
0.49
Map the permissible zone and draw the profile. At every section the four stress limits (two fibres, two stages) become upper and lower bounds on the eccentricity. Evaluated with $P_{e} = 2285$ kN and $P_{i} = P_{e}/\eta = 2856$ kN, and measuring $e$ positive below the centroid, the band runs as tabulated below. A pair of parabolas that meet tangentially at $x = 4.5$ m — $e = 330\,(2x/4.5 - x^{2}/4.5^{2})$ up to the vertex, then $e = 330 - 740\,[(x-4.5)/7.5]^{2}$ beyond it — starts on the centroid at the anchorage, reaches 330 mm below the centroid at 4.5 m, crosses the axis near the point of contraflexure and finishes 410 mm above it at the built-in end. Checked at 0.25 m intervals the profile lies inside the zone everywhere, with no violation.
Confirm the ultimate limit state. Serviceability sized the member, but Clause 18 still requires $M_{r} \ge M_{f}$. At the built-in end $d_{p} = 750 + 410 = 1160$ mm, $\rho_{p} = 2380/(400 \times 1160) = 0.00513$ and $f_{pr} = f_{pu}(1 - 0.5\rho_{p}f_{pu}/f'_{c}) = 1593$ MPa, giving $a = 339$ mm, $c/d_{p} = 0.35$ (safely under-reinforced) and $$M_{r} = \phi_{p}A_{ps}f_{pr}\left(d_{p} - \frac{a}{2}\right) = 3380\ \text{kN}\cdot\text{m} \ge M_{f} = 1.5(1743.8) + 1.25(259.2) = 2940\ \text{kN}\cdot\text{m}$$ The sagging section at 3 m returns $M_{r} = 2955$ against $M_{f} = 2433$ kN·m. Both pass.
Permissible eccentricity band ($e$ positive below the centroid)
$x$ (m)
Lower bound (mm)
Upper bound (mm)
Profile adopted (mm)
0.0
−327.7
+327.7
0
1.5
−115.3
+356.0
+183
3.0
+237.3
+373.1
+293
4.5
+181.8
+378.7
+330
6.0
+112.1
+373.1
+300
7.5
−234.3
+356.0
+212
9.0
−327.7
+327.7
+64
10.5
−367.4
−5.5
−144
12.0
−418.4
−394.5
−410
The band closes almost completely at the built-in end — barely 24 mm wide — which is the whole difficulty of this question. That is why the eccentricity there has to be fixed first and the rest of the profile drawn to suit, rather than the other way round.
Figure 2 girder (propped cantilever) with the adopted parabolic tendon profile.
Post-tensioned rectangular section at the fixed end, with the strand group above the centroid.
Question 3 — final results
Quantity
Value
Service moments
2003 kN·m hogging at the built-in end; 1644 kN·m sagging at 3 m
Section required
$Z \ge 88.3 \times 10^{6}$ mm$^{3}$
Section adopted
400 × 1500 mm rectangle
$P_{e}$ / $P_{i}$
2285 kN / 2856 kN
Prestressing steel
17 strands of 15.2 mm, $A_{ps} = 2380$ mm$^{2}$
$e$ at the built-in end
410 mm above the centroid
$e$ at 3 m / at 4.5 m
293 mm / 330 mm below the centroid
$e$ at the anchorage
0 (on the centroid)
Governing stress
service tension at the top fibre, 3.300 of 3.536 MPa (0.93)