16-Civ-B7 Transportation Planning and Engineering · December 2013
Question 7 of 7
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. 98-Civ-B7 Highway Engineering, National Examinations
December 2013 — a three-hour open-book examination; any
non-communicating calculator is permitted. The cover page states that a total of five
solutions is required, that only the first five as they appear in the answer book will
be marked, and that all questions are of equal value. The grading scheme printed on
page 1 confirms 20 marks per question, split as: Q1 20; Q2 20; Q3 (a) 15 and (b) 5;
Q4 (a) 8 and (b) 12; Q5 (a) 8 and (b) 12; Q6 20; Q7 (a) 8 and (b) 12. All
seven printed questions are worked below, because this set is a study
resource rather than a timed attempt; on exam day a candidate submits only the first
five, in order. The paper also states that any data required but not given may be
assumed and that assumptions should be recorded with the answer — several
questions need that licence, and every assumption is flagged where it is made.
Reference texts. N.J. Garber and L.A. Hoel, Traffic and Highway
Engineering, 5th ed. (sight distance, vertical and horizontal alignment, traffic
stream models, earthwork); Transportation Association of Canada, Geometric Design
Guide for Canadian Roads (Canadian design-domain values for stopping sight
distance, perception-reaction time and deceleration); AASHTO, A Policy on Geometric
Design of Highways and Streets (the tabulated metric stopping sight distances);
AASHTO, Guide for Design of Pavement Structures (1993) (rigid pavement
thickness, reliability, drainage and load-transfer coefficients); Asphalt Institute,
Mix Design Methods MS-2 (gradation charts, the 0.45 power chart, aggregate
blending); M.S. Mamlouk and J.P. Zaniewski, Materials for Civil and Construction
Engineers, 4th ed. (aggregate moisture states, sieve analysis); Transportation
Association of Canada, Pavement Asset Design and Management Guide (Canadian
pavement design practice).
Check — assumptions carried through this paper. Four inputs
the exam does not supply are assumed under its own Note 2 (“any data required,
but not given, can be assumed”), and each is restated at the point of use:
(i) Question 2 needs a stopping-sight-distance basis — a 2.5 s
perception-reaction time and a 3.4 m/s2 deceleration, the TAC and AASHTO
design values, giving the tabulated 185 m at 100 km/h; (ii) Question 2 also needs to
know whether the 600 m radius is to the road centreline — it is taken as the
centreline, and Step 5 shows the alternative reading changes the answer by 0.02 m;
(iii) Question 6 does not say whether the transverse joints are dowelled —
dowels are assumed, giving a load-transfer coefficient J = 3.2, with the
undowelled case quantified in a callout; (iv) Question 6 gives a drainage description
rather than a coefficient, so Cd = 1.00 is read from the AASHTO
table, again with the alternative quantified.
Given. Percent passing for two aggregate stockpiles and the
specification band they must be blended to satisfy:
Given data — percent passing
Sieve size
19 mm
12.5 mm
9.5 mm
4.75 mm
2.36 mm
0.60 mm
0.30 mm
0.15 mm
0.075 mm
Specification limits
100
80–100
75–95
55–65
35–45
25–35
15–25
10–15
5–10
Aggregate A
100
100
95
70
50
40
30
20
10
Aggregate B
100
90
60
30
10
0
0
0
0
Find. The minimum and maximum proportions of aggregates A and B for
which every sieve of the blend falls inside the specification band, a selected working
blend, and a semi-log plot of A, B, the blend and the specification limits.
Approach. Write the blend as a linear combination of the two
stockpiles, invert that relation on each sieve to obtain the interval of proportions
that keeps that sieve inside its band, and intersect the nine intervals; the governing
constraints are then whichever sieves produce the highest lower bound and the lowest
upper bound.
Part (a) — workable range of proportions
Write the blend equation. If a fraction $p$ of aggregate A is
combined with $(1-p)$ of aggregate B, then on any sieve the percent passing of the
blend is the weighted mean of the two stockpiles:
$$P = p\,A + (1-p)\,B = B + p\,(A - B)$$
The relation is linear in $p$ on every sieve, which is what makes both the algebraic
and the graphical (Rothfuchs) solutions possible.
Invert the blend equation on each sieve. Requiring
$L \le P \le U$ for the lower and upper specification limits, and noting that
$A > B$ on every sieve where the two differ,
$$\frac{L - B}{A - B} \;\le\; p \;\le\; \frac{U - B}{A - B}$$
Applied to the 4.75 mm sieve, where $A = 70$, $B = 30$ and the band is 55 to 65,
$$p \ge \frac{55 - 30}{70 - 30} = 0.625, \qquad p \le \frac{65 - 30}{70 - 30} = 0.875$$
Repeat on every sieve and collect the intervals. The 19 mm sieve
imposes no constraint, since both stockpiles pass 100% and the specification requires
100%. The remaining eight give:
Permissible fraction of aggregate A, sieve by sieve
Sieve (mm)
$A$</th><th>$B$</th><th>Band</th><th>Lower bound on $p$</th><th>Upper bound on $p$
19
100
100
100
no constraint ($A = B$)
12.5
100
90
80–100
0.000 (any)
1.000
9.5
95
60
75–95
0.429
1.000
4.75
70
30
55–65
0.625
0.875
2.36
50
10
35–45
0.625
0.875
0.60
40
0
25–35
0.625
0.875
0.30
30
0
15–25
0.500
0.833
0.15
20
0
10–15
0.500
0.750
0.075
10
0
5–10
0.500
1.000
Intersect the intervals to obtain the workable range. The binding
lower bound is the largest of the lower bounds and the binding upper bound is the
smallest of the upper bounds:
$$p_{min} = \max(0.429, 0.625, 0.625, 0.625, 0.500, 0.500, 0.500) = 0.625$$
$$p_{max} = \min(1.000, 1.000, 0.875, 0.875, 0.875, 0.833, 0.750, 1.000) = 0.750$$
so that
$$\boxed{62.5\% \le A \le 75.0\%}\qquad\text{and correspondingly}\qquad
\boxed{25.0\% \le B \le 37.5\%}$$
Identify which sieves govern, and why. Three sieves —
4.75 mm, 2.36 mm and 0.60 mm — produce the same lower bound of 0.625, because on
each of them the difference $A - B$ is exactly 40 percentage points and the lower limit
sits 25 points above B. The upper bound comes from the 0.150 mm sieve alone: aggregate
B contains nothing finer than 0.600 mm, so every particle passing 0.150 mm in the blend
comes from A, and the 15% ceiling on that sieve caps A at $15/20 = 75\%$. The workable
window is therefore only 12.5 percentage points wide, which is narrow; the two
stockpiles are only marginally compatible with this specification.
Select a working blend and prove it. A designer takes a round
proportion near the middle of the window — the midpoint is 68.75% — so
select
$$\boxed{70\%\ \text{aggregate A} + 30\%\ \text{aggregate B}}$$
Evaluating $P = 0.70A + 0.30B$ on each sieve, for instance at 2.36 mm,
$$P_{2.36} = 0.70(50) + 0.30(10) = 35 + 3 = 38\%$$
against a band of 35 to 45. The complete check is tabulated in the results below;
every sieve falls inside its limits, with the tightest margins at 2.36 mm (3 points
above the floor) and 0.15 mm (1 point below the ceiling).
Part (b) — semi-log gradation plot
Plot all four curves on the semi-log chart. Percent passing is the
linear ordinate and sieve size the logarithmic abscissa. The specification limits are
plotted as an upper and a lower curve enclosing a band; aggregate A, aggregate B and
the 70/30 blend are plotted as separate curves through the tabulated points.
Read the plot. Aggregate A lies above the band throughout the
middle of the range — it is too fine on its own, exceeding the upper limit at
4.75 mm (70 against 65) and at 2.36 mm (50 against 45). Aggregate B lies below the band
from 9.5 mm down — too coarse on its own, with no material at all finer than
0.600 mm. Neither stockpile is usable alone, but the blend curve threads the band on
every sieve, which is the visual statement of the algebra in part (a).
Note what the plot adds beyond the numbers. The blend curve runs
close to the upper limit at the coarse end and close to the lower limit at the fine
end, so it is a slightly coarse-of-centre mixture. If the plant experienced normal
stockpile variation of a few percent on the 0.150 mm sieve, the blend could drift above
the 15% ceiling; the graph shows at a glance where the quality-control attention should
go, and it argues for keeping the A fraction nearer 68% than 72% in production.
Semi-log gradation chart: aggregates A and B, the selected 70/30 blend and the specification band.
Final results — Question 7
Sieve (mm)
Aggregate A (%)
Aggregate B (%)
Blend 70A/30B (%)
Specification band (%)
Within band?
19
100
100
100.0
100
yes
12.5
100
90
97.0
80–100
yes
9.5
95
60
84.5
75–95
yes
4.75
70
30
58.0
55–65
yes
2.36
50
10
38.0
35–45
yes
0.60
40
0
28.0
25–35
yes
0.30
30
0
21.0
15–25
yes
0.15
20
0
14.0
10–15
yes
0.075
10
0
7.0
5–10
yes
Permissible range: aggregate A from 62.5% to 75.0%; aggregate B from 25.0% to 37.5%. Governing sieves: 4.75, 2.36 and 0.60 mm set the minimum A; 0.15 mm sets the maximum A.