NivaarExam PrepOfficial exam papers ↗

16-Civ-B7 Transportation Planning and Engineering · December 2014

Question 1 of 7: Earthwork volumes by average end area, and the shrinkage balance

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Examinations, December 2014 — 98-Civ-B7 Highway Engineering. Three-hour, OPEN BOOK paper; any non-communicating calculator permitted. Seven questions of equal value; a total of five solutions constitutes a complete paper, and only the first five in the answer book are marked. The grading scheme printed on page 1 splits the marks as Q1 (15+5), Q2 (12+8), Q3 (20), Q4 (10+10), Q5 (10+10), Q6 (6+14), Q7 (5+15). Note 1 invites the candidate to state any assumption made about an ambiguous question; Note 2 permits any required datum that is not given to be assumed. All seven questions are solved here, because the set is a study resource rather than a timed attempt.

Reference texts.

Check — source check. The only defects on page 5 (Questions 6 and 7) are two typographical errors in the printed paper itself (“horizintal” for horizontal and “Detrmine” for determine). No question data is in doubt. Where the paper omits a datum the assumption made is stated in a callout beside the calculation, as Note 2 of the paper permits.

Question 1: Earthwork volumes by average end area, and the shrinkage balance (15 + 5 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. Six surveyed cross-sections between station 351+00 and station 352+50, with the cut and fill end areas tabulated above. The statement that “the distance between the stations is 100 m” fixes the stationing as metric (full stations 100 m apart), so the plus-values read directly as metres: 351+50 lies 50 m beyond 351+00, 351+75 lies 75 m beyond it, and so on. The material shrinks 12 percent between the borrow condition and the compacted condition.

Find. (a) The volume of cut and the volume of fill over the 150 m reach by the average-end-area method; (b) after allowing for 12 percent shrinkage, whether the reach is in surplus or deficit and by how much.

10102020303040405050351+0057.93351+5052.28351+7523.58352+008.403.73352+1413.80352+5033.34CUTFILLend area (m2)station (chainage along centreline)End-area profile, station 351+00 to 352+50The section passes from fill to cut between 351+75 and 352+14; each branch is integrated separately.
Figure 1.1 — End areas plotted against station. Fill is shown below the datum and cut above it. The tabulated zeros at 351+75 (cut) and 352+14 (fill) are the grade points, so each branch begins and ends at a genuine zero area and no interval straddles a transition.

Approach. Apply the average-end-area rule interval by interval, keeping the cut and the fill branches in separate running totals, then convert the bank volume of cut to its compacted equivalent through the shrinkage factor and compare it with the compacted fill required.

  1. Part (a) — set out the interval lengths from the metric stationing. The six sections are not equally spaced, so the spacing of each of the five intervals must be taken from the stationing rather than assumed: $$L_1 = 50\ \text{m},\ L_2 = 25\ \text{m},\ L_3 = 25\ \text{m},\ L_4 = 14\ \text{m},\ L_5 = 36\ \text{m}$$ These sum to 150 m, which is the distance from 351+00 to 352+50 and confirms that the stationing has been read correctly.
  2. State the average-end-area rule. For two consecutive sections of end area $A_i$ and $A_{i+1}$ separated by a distance $L$, the enclosed volume is $$V = \frac{A_i + A_{i+1}}{2}\,L$$ The rule is exact when the section varies linearly with chainage and is the standard basis for progress payment on Canadian highway contracts. Cut and fill are never netted section by section: a station carrying both areas is contributing to two different earthwork operations, and combining them would conceal the true haul.
  3. Integrate the fill branch. Fill is present from 351+00 through to 352+14, where the fill area falls to zero: $$V_F = \tfrac{57.93+52.28}{2}(50) + \tfrac{52.28+23.58}{2}(25) + \tfrac{23.58+3.73}{2}(25) + \tfrac{3.73+0}{2}(14)$$ $$V_F = 2755.25 + 948.25 + 341.375 + 26.11 = \boxed{4071.0\ \text{m}^3}$$
  4. Integrate the cut branch. Cut begins at the grade point at 351+75, where the cut area is zero, and runs to the end of the reach: $$V_C = \tfrac{0+8.40}{2}(25) + \tfrac{8.40+13.80}{2}(14) + \tfrac{13.80+33.34}{2}(36)$$ $$V_C = 105.00 + 155.40 + 848.52 = \boxed{1108.9\ \text{m}^3}$$ The two branches overlap only over the 39 m between the grade points, where the section is part cut and part fill — a side-hill section, which is exactly why the paper tabulates the two areas separately.
  5. Part (b) — convert the cut from bank measure to compacted measure. A shrinkage of 12 percent means that a bank cubic metre of excavated material occupies only 0.88 compacted cubic metres once it has been placed and rolled in the embankment: $$V_{C,\text{comp}} = V_C\,(1 - s) = 1108.9 \times 0.88 = \boxed{975.9\ \text{m}^3}$$
  6. Strike the balance over the reach. Comparing what the cut can deliver with what the embankment demands, both now in compacted measure, $$\Delta V = V_F - V_{C,\text{comp}} = 4071.0 - 975.9 = \boxed{3095.1\ \text{m}^3\ \text{deficit}}$$ The reach is therefore not in surplus. It is short of fill by roughly 3100 compacted cubic metres, and that shortfall must be imported.
  7. Express the shortfall as a borrow quantity. Borrow is paid for and hauled in bank measure, and it shrinks by the same 12 percent on placement, so the volume to be excavated from the borrow pit is $$V_{\text{borrow}} = \frac{\Delta V}{1-s} = \frac{3095.1}{0.88} = \boxed{3517.2\ \text{m}^3\ \text{bank measure}}$$ Rounding for a schedule of quantities, roughly 3520 m3 of borrow is required over these 150 m.
Check — two conventions worth stating on the answer paper. First, the balance above is struck for this reach in isolation; on a real project the deficit would be tested against the mass-haul diagram for the whole grading contract before any borrow pit is opened, since an adjacent reach may be in surplus within economic haul. Second, if the examiner intended shrinkage to be applied as a swell on the fill side instead (“fill needed in bank measure” $= 4071.0/0.88 = 4626.1\ \text{m}^3$), the deficit in bank measure is $4626.1 - 1108.9 = 3517.2\ \text{m}^3$ — identically the borrow quantity found in Step 7. The two readings agree, so the answer is robust to the ambiguity.
QuantityValueBasis
Volume of fill, station 351+00 to 352+144071.0 m3compacted
Volume of cut, station 351+75 to 352+501108.9 m3bank
Cut available after 12 percent shrinkage975.9 m3compacted
Net balance over the reach3095.1 m3 deficitcompacted
Borrow required3517.2 m3 (say 3520)bank
← Paper overview