16-Civ-B8 Management of Construction · December 2016
Question 3 of 6: Project Control
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. 98-Civ-B8 Management of Construction, National Exams
December 2016. Three hours, closed book, one approved calculator (Casio or Sharp). Six questions
of equal value (20 marks each); any five constitute a complete paper and only the first five
presented in the answer book are marked. All six are solved here, because the set
is a study resource rather than an examination script.
Reference texts.
Halpin & Senior, Construction Management, 4th ed. — precedence networks with
lags, bonding, project control.
Hendrickson, Project Management for Construction, 2nd ed. — scheduling, cost
control, earned value, financing of constructed facilities.
Project Management Institute, A Guide to the Project Management Body of Knowledge
(PMBOK Guide), 6th ed. — schedule and cost management, earned value.
Fraser et al., Global Engineering Economics, 5th Canadian ed. — present worth,
deferred annuities, maximum justifiable investment.
Canadian Construction Documents Committee: CCDC 2 (stipulated price), CCDC 4 (unit price),
CCDC 14 (design-build), CCDC 3 (cost-plus), CCDC 23 Guide to Calling Bids and Awarding
Contracts; CCDC 220 / 221 / 222 bond forms.
Builders Lien Act (British Columbia, RSBC 1997 c. 45) and the provincial
construction-lien / prompt-payment statutes; RSMeans Residential Square Foot Costs.
(a) The S-curve, the expense-versus-payment profiles, and project financing
Cumulative expenditure on a construction project plots as a shallow S. Early on, only mobilisation,
survey, site preparation and submittals are running, so the curve is flat; through the middle of the
job the major trades are all working at once and the curve is steep; near the end only deficiency
work, commissioning and demobilisation remain, so it flattens again. The same shape appears whether
the ordinate is the owner’s budget, the contractor’s cost, or physical percent complete,
which is what makes the S-curve the standard baseline against which progress is judged.
Figure 3.1 — typical project S-curve: the contractor’s smooth
cumulative expense curve against the stepped, lagging cumulative payment curve. The vertical distance
between them is the contractor’s working-capital requirement.
The payment profile is not the same curve. Cost is incurred continuously, day by day as labour is
paid and material is delivered, but payment arrives in discrete monthly steps, after a progress claim
has been submitted, certified by the consultant, and paid within the contractual period —
typically 30 days under CCDC 2, and now within the statutory deadlines of the prompt-payment
legislation being adopted across Canada. On top of that lag sits the statutory holdback (10 per cent
in most provinces, retained until the lien period expires after substantial performance). The result
is the picture in Figure 3.1: a smooth expense curve and a stepped payment curve that lies below it
for essentially the whole job, closing only when the holdback is released. The vertical gap between
them is money the contractor has spent and not yet been paid — the working capital it must
finance, and the interest on that borrowing is a real project cost that must be recovered in the
bid.
Several measures reduce that interest charge, and a competent contractor uses all of them:
Negotiate a mobilisation payment or advance. An up-front payment against the
mobilisation and bonding costs lifts the whole payment curve at day zero, which is where the deficit
is proportionally worst.
Front-end load the schedule of values (within honest limits). Assigning a fair
but generous share of the price to early activities pulls cash forward. Loading it dishonestly is
unbalanced bidding and will be rejected by the payment certifier, so the legitimate version of this is
simply to make sure early work — excavation, foundations, site services — is priced at its
true value rather than being subsidised from later trades.
Bill promptly, completely and accurately. The single largest controllable lag is
the contractor’s own claim preparation. A claim submitted on the first of the month with correct
quantities and complete backup is certified on time; one submitted late or with disputed items sits
for a further payment cycle.
Match supplier and subcontractor terms to the owner’s payment cycle.
Paid-when-paid clauses, negotiated 30- or 60-day supplier terms, and equipment rental rather than
purchase all shift the outflow to the right and shrink the gap directly.
Reduce the holdback exposure. Substantial performance should be certified as soon
as it is genuinely achieved, and staged or partial releases negotiated for early-completing portions;
where the contract allows, a holdback bond or letter of credit can be substituted for cash retention.
Deficiency lists should be cleared quickly, because the last 1 per cent of work commonly holds 10 per
cent of the money.
Level the resource and expenditure profile. Smoothing peaks in the S-curve
(and using float on non-critical work to defer expenditure rather than accelerate it) lowers the
maximum cash exposure, which is what the line of credit must be sized for.
Use the cheapest available financing. A negotiated operating line secured against
receivables is far cheaper than trade credit taken by paying late, and much cheaper than the reputational
cost of a lien filed by an unpaid subcontractor.
(b) Performance indices for schedule and cost control
Schedule and cost cannot be controlled independently, because a job can be on budget only by being
behind, or on time only by spending more. Earned-value analysis solves this by measuring all three
quantities in the same units — dollars of budgeted work — so that progress and expenditure
can be compared directly. The three primitives are the planned value \(PV\) (budgeted cost of
work scheduled), the earned value \(EV\) (budgeted cost of work actually performed) and the
actual cost \(AC\) of that performed work.
Given. To make the indices concrete, take a job at its data date with
\(PV = \$500{,}000\), \(EV = \$450{,}000\), \(AC = \$480{,}000\) and a budget at completion
\(BAC = \$1{,}200{,}000\).
Find. The schedule and cost variances and indices, and the forecast cost at
completion.
Variances measure the gap in dollars. The schedule variance compares work done
with work planned, and the cost variance compares work done with money spent:
$$SV = EV - PV = 450{,}000 - 500{,}000 = -\$50{,}000, \qquad
CV = EV - AC = 450{,}000 - 480{,}000 = -\$30{,}000 .$$
Both are negative, so the job is behind schedule and over cost. Variances are useful for reporting an
absolute exposure but they cannot be compared between projects of different size.
Indices normalise the same information into a ratio. Dividing rather than
subtracting gives dimensionless numbers that can be trended and benchmarked:
$$SPI = \frac{EV}{PV} = \frac{450{,}000}{500{,}000} = 0.90, \qquad
CPI = \frac{EV}{AC} = \frac{450{,}000}{480{,}000} = 0.9375 .$$
$$\boxed{SPI = 0.90 \;(\text{10 percent behind}), \qquad CPI = 0.94 \;(\text{about 6 percent over cost})}$$
A value of 1.0 is on plan; below 1.0 is unfavourable in both cases.
Extrapolate to completion. If the cost performance achieved so far persists, the
estimate at completion is the budget inflated by the reciprocal of the cost index:
$$EAC = \frac{BAC}{CPI} = \frac{1{,}200{,}000}{0.9375} = \$1{,}280{,}000,$$
a forecast overrun of \(\$80{,}000\). The same logic applied to \(SPI\) gives a first estimate of the
completion date, though schedule forecasting is better done by re-running the critical path than by
extrapolating an index.
Beyond these four, three further indices are in routine use. The to-complete performance
index, \(TCPI = (BAC-EV)/(BAC-AC)\), states the cost efficiency the remaining work must achieve to
land on budget, and is the honest test of whether a recovery plan is credible — a \(TCPI\) far
above the \(CPI\) actually being achieved means the plan is wishful. The critical ratio,
\(CR = SPI \times CPI\), combines both dimensions into a single health indicator for portfolio
reporting. And on the schedule side, earned schedule converts \(EV\) back into time units to
correct the well-known defect that \(SPI\) drifts to 1.0 at completion no matter how late the project
finishes, because at the end \(EV = PV = BAC\) by definition.
Question 3 — earned-value indices for the illustrative job