NivaarExam PrepOfficial exam papers ↗

16-Civ-B8 Management of Construction · December 2016

Question 3 of 6: Project Control

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. 98-Civ-B8 Management of Construction, National Exams December 2016. Three hours, closed book, one approved calculator (Casio or Sharp). Six questions of equal value (20 marks each); any five constitute a complete paper and only the first five presented in the answer book are marked. All six are solved here, because the set is a study resource rather than an examination script.

Reference texts.

  • Halpin & Senior, Construction Management, 4th ed. — precedence networks with lags, bonding, project control.
  • Hendrickson, Project Management for Construction, 2nd ed. — scheduling, cost control, earned value, financing of constructed facilities.
  • Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 6th ed. — schedule and cost management, earned value.
  • Fraser et al., Global Engineering Economics, 5th Canadian ed. — present worth, deferred annuities, maximum justifiable investment.
  • Canadian Construction Documents Committee: CCDC 2 (stipulated price), CCDC 4 (unit price), CCDC 14 (design-build), CCDC 3 (cost-plus), CCDC 23 Guide to Calling Bids and Awarding Contracts; CCDC 220 / 221 / 222 bond forms.
  • Builders Lien Act (British Columbia, RSBC 1997 c. 45) and the provincial construction-lien / prompt-payment statutes; RSMeans Residential Square Foot Costs.

Question 3: Project Control (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

(a) The S-curve, the expense-versus-payment profiles, and project financing

Cumulative expenditure on a construction project plots as a shallow S. Early on, only mobilisation, survey, site preparation and submittals are running, so the curve is flat; through the middle of the job the major trades are all working at once and the curve is steep; near the end only deficiency work, commissioning and demobilisation remain, so it flattens again. The same shape appears whether the ordinate is the owner’s budget, the contractor’s cost, or physical percent complete, which is what makes the S-curve the standard baseline against which progress is judged.

financing gap holdback released cumulative expense (cost incurred) cumulative payment received project time cumulative dollars
Figure 3.1 — typical project S-curve: the contractor’s smooth cumulative expense curve against the stepped, lagging cumulative payment curve. The vertical distance between them is the contractor’s working-capital requirement.

The payment profile is not the same curve. Cost is incurred continuously, day by day as labour is paid and material is delivered, but payment arrives in discrete monthly steps, after a progress claim has been submitted, certified by the consultant, and paid within the contractual period — typically 30 days under CCDC 2, and now within the statutory deadlines of the prompt-payment legislation being adopted across Canada. On top of that lag sits the statutory holdback (10 per cent in most provinces, retained until the lien period expires after substantial performance). The result is the picture in Figure 3.1: a smooth expense curve and a stepped payment curve that lies below it for essentially the whole job, closing only when the holdback is released. The vertical gap between them is money the contractor has spent and not yet been paid — the working capital it must finance, and the interest on that borrowing is a real project cost that must be recovered in the bid.

Several measures reduce that interest charge, and a competent contractor uses all of them:

(b) Performance indices for schedule and cost control

Schedule and cost cannot be controlled independently, because a job can be on budget only by being behind, or on time only by spending more. Earned-value analysis solves this by measuring all three quantities in the same units — dollars of budgeted work — so that progress and expenditure can be compared directly. The three primitives are the planned value \(PV\) (budgeted cost of work scheduled), the earned value \(EV\) (budgeted cost of work actually performed) and the actual cost \(AC\) of that performed work.

Given. To make the indices concrete, take a job at its data date with \(PV = \$500{,}000\), \(EV = \$450{,}000\), \(AC = \$480{,}000\) and a budget at completion \(BAC = \$1{,}200{,}000\).

Find. The schedule and cost variances and indices, and the forecast cost at completion.

  1. Variances measure the gap in dollars. The schedule variance compares work done with work planned, and the cost variance compares work done with money spent: $$SV = EV - PV = 450{,}000 - 500{,}000 = -\$50{,}000, \qquad CV = EV - AC = 450{,}000 - 480{,}000 = -\$30{,}000 .$$ Both are negative, so the job is behind schedule and over cost. Variances are useful for reporting an absolute exposure but they cannot be compared between projects of different size.
  2. Indices normalise the same information into a ratio. Dividing rather than subtracting gives dimensionless numbers that can be trended and benchmarked: $$SPI = \frac{EV}{PV} = \frac{450{,}000}{500{,}000} = 0.90, \qquad CPI = \frac{EV}{AC} = \frac{450{,}000}{480{,}000} = 0.9375 .$$ $$\boxed{SPI = 0.90 \;(\text{10 percent behind}), \qquad CPI = 0.94 \;(\text{about 6 percent over cost})}$$ A value of 1.0 is on plan; below 1.0 is unfavourable in both cases.
  3. Extrapolate to completion. If the cost performance achieved so far persists, the estimate at completion is the budget inflated by the reciprocal of the cost index: $$EAC = \frac{BAC}{CPI} = \frac{1{,}200{,}000}{0.9375} = \$1{,}280{,}000,$$ a forecast overrun of \(\$80{,}000\). The same logic applied to \(SPI\) gives a first estimate of the completion date, though schedule forecasting is better done by re-running the critical path than by extrapolating an index.

Beyond these four, three further indices are in routine use. The to-complete performance index, \(TCPI = (BAC-EV)/(BAC-AC)\), states the cost efficiency the remaining work must achieve to land on budget, and is the honest test of whether a recovery plan is credible — a \(TCPI\) far above the \(CPI\) actually being achieved means the plan is wishful. The critical ratio, \(CR = SPI \times CPI\), combines both dimensions into a single health indicator for portfolio reporting. And on the schedule side, earned schedule converts \(EV\) back into time units to correct the well-known defect that \(SPI\) drifts to 1.0 at completion no matter how late the project finishes, because at the end \(EV = PV = BAC\) by definition.

Question 3 — earned-value indices for the illustrative job
MeasureFormulaValueInterpretation
Schedule variance\(EV-PV\)−$50,000Behind schedule
Cost variance\(EV-AC\)−$30,000Over cost
Schedule performance index\(EV/PV\)0.9010 % behind plan
Cost performance index\(EV/AC\)0.9494 cents of value per dollar spent
Estimate at completion\(BAC/CPI\)$1,280,000Forecast overrun of $80,000