NivaarExam PrepOfficial exam papers ↗

16-Civ-B8 Management of Construction · May 2016

Question 3 of 6: Estimating and Bidding

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

Paper format. National Exams, May 2016 — 98-Civ-B8 Management of Construction. Three hours, closed book, one approved calculator (Casio or Sharp). Six questions, all of equal value (20 marks each); any five constitute a complete paper and only the first five presented in the answer book are marked. All six are solved here, because the set is a study resource rather than an examination script.

Reference texts.

Question 3: Estimating and Bidding (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. Seven indirect-cost items totalling $60,800, incurred over a project duration of six months.

Given data — indirect costs incurred on a six-month project
ItemDescriptionCost
1Total cost of permits$4,500
2Crane rental$17,000
3Office secretary$14,000
4Cost of project utilities$1,200
5Mobilization cost$8,300
6Batch plant on site$12,000
7Site preparation for work$3,800
Total indirect cost$60,800

Find. A two-way classification of each item — project versus general overhead, and fixed versus variable — and a linear model $Y = aX + b$ of total indirect cost as a function of project duration, with the meaning of a and b explained.

Approach. Classify by attribution first (can the cost be charged to this one project, or does it belong to the company as a whole?), then by behaviour (does the cost accrue with elapsed time, or is it a one-time charge independent of duration?), and finally fit the linear model by making b the sum of the time-independent items and a the time-dependent items divided by the six-month duration.

  1. Separate project overhead from general overhead. Project (job-site or field) overhead is indirect cost that is caused by and traceable to one project but not to any single item of permanent work; general (head-office or company) overhead is the cost of being in business at all, incurred whether or not this particular project exists, and recovered by distributing it across all projects as a percentage of direct cost or revenue. Applying that test: the permits are taken out for this project (item 1); the crane is rented for this site (2); the utilities serve this site (4); mobilization brings plant and personnel to this site (5); the batch plant is erected on this site (6); and the site preparation is done on this site (7). All six are project overhead. The office secretary (item 3) staffs the company office, serving every project and the pursuit of future work, and is therefore general overhead.
  2. Separate fixed from variable indirect cost. In construction estimating the relevant independent variable for indirect cost is time, so “variable” means time-related — the charge continues to accrue for as long as the project runs — while “fixed” means a lump, one-time charge that does not change if the project is extended. Permits (item 1) are paid once at a scheduled fee; mobilization (5) and site preparation (7) are single events at the start; and the batch plant (6) is erected, used and dismantled, its cost set by the installation rather than by the calendar. These four are fixed, and they sum to $$b = 4{,}500 + 8{,}300 + 12{,}000 + 3{,}800 = \$28{,}600$$ The crane is rented by the month (2), the secretary is salaried by the month (3) and the utilities are metered monthly (4); these three are variable and sum to $$\text{variable total} = 17{,}000 + 14{,}000 + 1{,}200 = \$32{,}200$$ and the two groups reconcile to the given total, $b + \text{variable} = 28{,}600 + 32{,}200 = \$60{,}800$.
  3. Convert the variable total into a monthly rate. The variable group accrued over the full six-month duration, so the rate per month is the group total divided by the duration: $$a = \frac{32{,}200}{6}$$ $$\boxed{a = \$5{,}366.67 \text{ per month}}$$
  4. Write the indirect-cost equation. With X the project duration in months and Y the total indirect cost in dollars, $$Y = aX + b$$ $$\boxed{Y = 5{,}366.67\,X + 28{,}600}$$ Checking the model at the observed duration reproduces the data, which is the arithmetic proof that the split is complete and nothing has been double counted: $$Y(6) = 5{,}366.67 \times 6 + 28{,}600 = 32{,}200 + 28{,}600 = \$60{,}800 \;\checkmark$$
  5. Explain the parameters. Y is the total indirect cost of the project in dollars, the amount that must be recovered by the mark-up applied to the direct estimate. X is the independent variable, here the project duration in months; the model is meaningful only over the range in which the same site establishment is maintained. a is the slope, the time-related indirect cost per month — the daily-cost or “standing cost” figure of $5,366.67 per month (about $176 per calendar day) that determines what an extension of time is worth. It is the number quoted when a delay claim is priced, and it is the number that makes acceleration worth paying for. b is the intercept, the time-independent indirect cost of $28,600 that is incurred even for a project of vanishing duration: it is the cost of establishing and removing the site, and it does not shrink if the work is compressed. The practical reading is that extending this project by one month adds $5,367 of indirect cost and no more, while a decision to mobilise at all costs $28,600 before a single month of standing time is counted.

Check: the batch plant (item 6) is treated here as a fixed charge, on the reading that the $12,000 is the cost of erecting and dismantling a plant installed for this job — the natural contrast with item 2, which the paper explicitly calls a rental. If instead the $12,000 is read as a monthly hire of the plant, it moves into the variable group and the model becomes $Y = 7{,}366.67\,X + 16{,}600$, which still reproduces $60,800 at X = 6 but roughly doubles the value of a month of delay. State the reading before pricing any extension of time.

Check: if the equation is wanted for project indirect cost only — that is, with the head-office secretary excluded and recovered instead as a company-wide percentage mark-up — then $a = (17{,}000 + 1{,}200)/6 = \$3{,}033.33$ per month, $b = \$28{,}600$, and $Y(6) = \$46{,}800$.

Final results — classification of the seven indirect-cost items
ItemDescriptionCostProject or general overheadFixed or variable
1Total cost of permits$4,500ProjectFixed
2Crane rental$17,000ProjectVariable (per month)
3Office secretary$14,000GeneralVariable (per month)
4Cost of project utilities$1,200ProjectVariable (per month)
5Mobilization cost$8,300ProjectFixed
6Batch plant on site$12,000ProjectFixed (see callout)
7Site preparation for work$3,800ProjectFixed
Fixed total, b$28,600
Variable total (6 months)$32,200
Slope, a$5,366.67 per month
Indirect-cost equationY = 5,366.67 X + 28,600 (X in months)
Check at X = 6$60,800 = given total