Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Exams, May 2016 —
98-Civ-B8 Management of Construction. Three hours, closed book, one approved
calculator (Casio or Sharp). Six questions, all of equal value (20 marks each); any five
constitute a complete paper and only the first five presented in the answer book are marked.
All six are solved here, because the set is a study resource rather than an
examination script.
Project Management Institute, A Guide to the Project Management Body of Knowledge
(PMBOK Guide), 6th ed. — schedule and cost management, earned value.
Fraser et al., Global Engineering Economics, 5th Canadian ed. — present
worth, annual worth, repeated lives.
Canadian Construction Documents Committee: CCDC 2 (stipulated price), CCDC 4 (unit price),
CCDC 23 Guide to Calling Bids and Awarding Contracts; CCDC 220/221/222 bond forms.
WorkSafeBC, Occupational Health and Safety Regulation — Parts 8, 11, 12, 13,
18, 20; Hinze, Construction Safety, 2nd ed.
Given. Seven indirect-cost items totalling $60,800, incurred over a project
duration of six months.
Given data — indirect costs incurred on a six-month project
Item
Description
Cost
1
Total cost of permits
$4,500
2
Crane rental
$17,000
3
Office secretary
$14,000
4
Cost of project utilities
$1,200
5
Mobilization cost
$8,300
6
Batch plant on site
$12,000
7
Site preparation for work
$3,800
Total indirect cost
$60,800
Find. A two-way classification of each item — project versus general
overhead, and fixed versus variable — and a linear model $Y = aX + b$ of total indirect cost
as a function of project duration, with the meaning of a and b explained.
Approach. Classify by attribution first (can the cost be charged to
this one project, or does it belong to the company as a whole?), then by behaviour
(does the cost accrue with elapsed time, or is it a one-time charge independent of duration?),
and finally fit the linear model by making b the sum of the time-independent items and
a the time-dependent items divided by the six-month duration.
Separate project overhead from general overhead.
Project (job-site or field) overhead is indirect cost that is caused by and traceable to one
project but not to any single item of permanent work; general (head-office or company)
overhead is the cost of being in business at all, incurred whether or not this particular project
exists, and recovered by distributing it across all projects as a percentage of direct cost or
revenue. Applying that test: the permits are taken out for this project (item 1); the crane is
rented for this site (2); the utilities serve this site (4); mobilization brings plant and
personnel to this site (5); the batch plant is erected on this site (6); and the site preparation
is done on this site (7). All six are project overhead. The office secretary
(item 3) staffs the company office, serving every project and the pursuit of future work, and is
therefore general overhead.
Separate fixed from variable indirect cost.
In construction estimating the relevant independent variable for indirect cost is time,
so “variable” means time-related — the charge continues to accrue for as long as
the project runs — while “fixed” means a lump, one-time charge that does not
change if the project is extended. Permits (item 1) are paid once at a scheduled fee; mobilization
(5) and site preparation (7) are single events at the start; and the batch plant (6) is erected,
used and dismantled, its cost set by the installation rather than by the calendar. These four are
fixed, and they sum to
$$b = 4{,}500 + 8{,}300 + 12{,}000 + 3{,}800 = \$28{,}600$$
The crane is rented by the month (2), the secretary is salaried by the month (3) and the utilities
are metered monthly (4); these three are variable and sum to
$$\text{variable total} = 17{,}000 + 14{,}000 + 1{,}200 = \$32{,}200$$
and the two groups reconcile to the given total, $b + \text{variable} = 28{,}600 + 32{,}200 =
\$60{,}800$.
Convert the variable total into a monthly rate.
The variable group accrued over the full six-month duration, so the rate per month is the group
total divided by the duration:
$$a = \frac{32{,}200}{6}$$
$$\boxed{a = \$5{,}366.67 \text{ per month}}$$
Write the indirect-cost equation.
With X the project duration in months and Y the total indirect cost in dollars,
$$Y = aX + b$$
$$\boxed{Y = 5{,}366.67\,X + 28{,}600}$$
Checking the model at the observed duration reproduces the data, which is the arithmetic proof
that the split is complete and nothing has been double counted:
$$Y(6) = 5{,}366.67 \times 6 + 28{,}600 = 32{,}200 + 28{,}600 = \$60{,}800 \;\checkmark$$
Explain the parameters.Y is the total indirect cost of the project in dollars, the amount that must be recovered
by the mark-up applied to the direct estimate. X is the independent variable, here the
project duration in months; the model is meaningful only over the range in which the same site
establishment is maintained. a is the slope, the time-related indirect cost per
month — the daily-cost or “standing cost” figure of $5,366.67 per month
(about $176 per calendar day) that determines what an extension of time is worth. It is the number
quoted when a delay claim is priced, and it is the number that makes acceleration worth paying
for. b is the intercept, the time-independent indirect cost of $28,600
that is incurred even for a project of vanishing duration: it is the cost of establishing and
removing the site, and it does not shrink if the work is compressed. The practical reading is that
extending this project by one month adds $5,367 of indirect cost and no more, while a decision to
mobilise at all costs $28,600 before a single month of standing time is counted.
Check: the batch plant (item 6) is treated here as a fixed charge,
on the reading that the $12,000 is the cost of erecting and dismantling a plant installed for this
job — the natural contrast with item 2, which the paper explicitly calls a rental.
If instead the $12,000 is read as a monthly hire of the plant, it moves into the variable group
and the model becomes $Y = 7{,}366.67\,X + 16{,}600$, which still reproduces $60,800 at
X = 6 but roughly doubles the value of a month of delay. State the reading before pricing
any extension of time.
Check: if the equation is wanted for project indirect cost only
— that is, with the head-office secretary excluded and recovered instead as a company-wide
percentage mark-up — then $a = (17{,}000 + 1{,}200)/6 = \$3{,}033.33$ per month,
$b = \$28{,}600$, and $Y(6) = \$46{,}800$.
Final results — classification of the seven indirect-cost items