22-Elec-B7 Power Systems Engineering · May 2017
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Paper format. National Exams, May 2017 — 16-Elec-B7 Power Systems Engineering. Open-book, 3 hours, seven problems of equal value (25 points each); any five constitute a complete paper, and only the first five in the answer book are marked. All seven are solved here, because the set is a study resource rather than a sitting.
Reference texts. This exam code follows M. E. El-Hawary, Electrical Power Systems: Design and Analysis (IEEE Press) — the notation is his throughout: the bundle-conductor mean radii and long-line ABCD constants of Problem 1, the round-rotor power-angle relations of Problem 2, the three-winding equivalent circuit of Problem 3, the sequence-network fault reduction of Problem 6 and the equal-area criterion of Problem 7. Corroborating references: J. D. Glover, M. S. Sarma and T. J. Overbye, Power System Analysis and Design, 6th ed. (ch. 4–5 transmission-line parameters, ch. 6 power flow, ch. 7–9 symmetrical components and faults, ch. 11 transient stability); J. J. Grainger and W. D. Stevenson, Power System Analysis; and S. J. Chapman, Electric Machinery Fundamentals, 5th ed., for the synchronous-machine and transformer chapters. Canadian practice references where protection and grounding are discussed: CSA C22.1 Canadian Electrical Code, Part I, CSA C22.3 for overhead systems, and IEEE C37 (protective relaying) and IEEE 142 Green Book (grounding).
Check: four judgement calls carried through the solutions, recorded here rather than hedged inside the answers.
(i) Problem 1 states neither a frequency nor a line length. Parts (a)–(c) need neither. Part (d) needs both, so 60 Hz is used (Canadian national exam) and the ABCD constants are given as closed-form functions of length, evaluated at a representative 400 km with a sensitivity table at 200 km and 600 km. The characteristic impedance and the surge-impedance loading do not depend on either quantity.
(ii) Problem 1 gives “bundle separation S” for a bundle whose figure shows eight sub-conductors on a circle. S is read as the distance between adjacent sub-conductors, so the bundle radius is $A = S/[2\sin(\pi/N)] = 0.6533\ \text{m}$ — the standard El-Hawary reading. If a marker instead reads S as the bundle diameter, every mean radius scales by the same factor and the method is unchanged.
(iii) Problem 5 says “the voltage at both sources is 1 p.u.” above a figure that draws three generators. All three are taken at 1.0 pu, which is the only reading that closes the network; the three internal e.m.f.s then merge into one node.
(iv) Problem 6: the zero-sequence source reactance is printed as $X_{0S}=j0.04$, possibly followed by a fifth digit. The value $j0.04$ is used. Reading it as $j0.045$ moves the zero-sequence Thévenin reactance from 0.19978 to 0.20051 pu and the fault current by 0.1 % — below the resolution of any answer here.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
(a) Bus types in the conventional power-flow formulation. Each bus carries four quantities — voltage magnitude $|V|$, voltage angle $\delta$, net real injection $P$ and net reactive injection $Q$ — and exactly two are specified in advance, the remaining two being computed. Three types are recognised. The slack (swing, reference) bus, of which there is exactly one, specifies $|V|$ and $\delta$ (the latter almost always at zero, to fix the angular reference) and leaves $P$ and $Q$ to be found; it must exist because network losses are unknown until the solution is complete, so one generator has to absorb the mismatch. A load or PQ bus specifies $P$ and $Q$ from the forecast demand and leaves $|V|$ and $\delta$ unknown; the great majority of buses in a real network are of this type, and a bus with no load or generation at all is a PQ bus with both injections zero. A generator, voltage-controlled or PV bus specifies $P$ (from the dispatch) and $|V|$ (from the automatic voltage regulator) and leaves $Q$ and $\delta$ unknown; its reactive output is checked against the machine capability limits at each iteration and, if a limit binds, the bus is converted to PQ at that limit for the remaining iterations. In this problem bus 1 is the slack ($V_1=1.0\angle0^\circ$), bus 2 is a load bus, and bus 3 is voltage-controlled with both its magnitude and angle given, which is what makes the network solvable in closed form.
Given.
| Quantity | Symbol | Value |
|---|---|---|
| Slack-bus voltage | $V_1$ | $1.00\angle 0^\circ$ pu |
| Bus-3 voltage | $V_3$ | $1.05\angle 32^\circ$ pu |
| Real injection at bus 2 (a load) | $P_2$ | $-3.75$ pu |
| Voltage angle at bus 2 (stated) | $\delta_2$ | $-12^\circ$ |
| Line 1–2 series impedance | $z_{12}$ | $j0.10$ pu |
| Line 2–3 series impedance | $z_{23}$ | $j0.08$ pu |
| Line charging / shunts | — | none shown |
Find. $|V_2|$ and $Q_2$ with $\delta_2$ taken as $-12^\circ$, then the complex generation at buses 1 and 3.
Approach. Build the bus admittance matrix, write the injection at bus 2 in polar form and exploit the fact that a purely susceptive $Y_{22}$ contributes nothing to real power, so $P_2$ is linear in $|V_2|$ and one division answers part (b). With all three voltages then known, parts (c) and (d) are direct evaluations of $S_i=V_iI_i^{*}$.
Final Results
| Quantity | Symbol | Result |
|---|---|---|
| (b) Bus-2 voltage magnitude | $|V_2|$ | 0.33493 pu |
| (b) Bus-2 reactive injection | $Q_2$ | $-3.9143$ pu (absorbed) |
| (c) Bus-1 real generation | $P_1$ | 0.6964 pu |
| (c) Bus-1 reactive generation | $Q_1$ | 6.7239 pu |
| (d) Bus-3 real generation | $P_3$ | 3.0536 pu |
| (d) Bus-3 reactive generation | $Q_3$ | 10.6191 pu |
| Real-power balance (lossless check) | $\sum P_i$ | 0.0000 pu |
| Reactive absorbed by the two lines | $\sum |I|^2x$ | 13.42 pu |