NivaarExam PrepOfficial exam papers ↗

23-Ind-A4 Production Management · May 2015

Question 4 of 7: Aggregate Production Plan for Office Chairs — First Five Months

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Technical Examinations — May 2015 — 98-Ind-A4 Production Management. Three-hour, closed-book exam; Casio or Sharp approved calculators only. Format: seven questions, each worth 20 marks (sub-part weights as tabulated on the front page); only the first five questions appearing in the answer book are marked, so candidates effectively choose 5 of 7. All seven are solved below for completeness. The paper asks for point-form answers wherever possible; the solutions below use full working for clarity.

Reference texts: Nahmias & Olsen, Production and Operations Analysis (7th ed., Waveland/McGraw-Hill) — forecasting, inventory (EOQ) and aggregate planning; Sipper & Bulfin, Production: Planning, Control, and Integration — production-management systems; Hillier & Lieberman, Introduction to Operations Research (11th ed.) — LP formulation and project scheduling (CPM/PERT); Pinedo, Scheduling: Theory, Algorithms, and Systems (5th ed.) — parallel-machine scheduling, makespan and tardiness; Hopp & Spearman, Factory Physics (3rd ed.) — variability and production-system inefficiency; Niebel & Freivalds, Methods, Standards, and Work Design — division of labour and work-design history; ISO 9001:2015 and the Toyota Production System literature — quality management, 5S/lean and TPM.

Question 4: Aggregate Production Plan for Office Chairs — First Five Months (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Given. Five months of forecast demand and the cost/capacity data below; the existing 7-worker crew (7 × 12 = 84 chairs/month regular capacity); beginning inventory $I_0=100$, and the target boundary condition $I_5=0,\,B_5=0$ (no inventory and no backorder outstanding at the end of month 5).

Month $t$12345
Forecast demand $D_t$150150160180100
Cost / capacity itemValue
Regular time$\$100$/unit, capacity $=84$/month (7 workers × 12)
Overtime$\$150$/unit, capacity $\le25$/month
Subcontract$\$200$/unit, capacity $\le50$/month
Inventory carrying$\$20$/unit-month
Back-order$\$25$/unit-month
Hiring / firing$\$1{,}000$/worker / $\$2{,}000$/worker

Find. A concrete, minimum-cost aggregate production plan — monthly regular, overtime, subcontract, inventory, and backorder quantities — for months 1–5, ending exactly at $I_5=0,\,B_5=0$.

Approach. Unlike a "formulate only" LP question, this one asks for the plan itself, so the workforce lever is fixed at the existing 7 workers (hiring/firing a fractional headcount over only a 5-month window is not something a candidate can execute by hand, and the 84-unit/month regular capacity plus the stated overtime and subcontract caps turn out to be enough); size regular time at its 84-unit cap every month, then use overtime, subcontract, and carried inventory/backorder, cheapest lever first, to close the gap between capacity and demand while landing exactly on the month-5 target.

  1. Cost ordering of the levers. Per extra unit of monthly output, regular time ($\$100$) is cheapest, then overtime ($\$150$), then subcontract ($\$200$); carrying a unit in inventory costs $\$20$/month and carrying a unit as backorder costs $\$25$/month. Since regular time is both the cheapest production lever and produces every month regardless of that month's individual demand, run the plant at full regular capacity ($P_t=84$) every month and use overtime before subcontract whenever more output is needed, banking any surplus as inventory to reduce a later month's shortfall.
  2. Months 1–2 (capacity exceeds demand). $I_0=100$ already exceeds $D_1=150-84=66$ needed from stock, so regular time alone covers both months with no overtime or subcontract required: $$I_1=I_0+P_1-D_1=100+84-150=34,\qquad I_2=I_1+P_2-D_2=34+84-150=\boxed{18}.$$
  3. Month 3 (a shortfall starts). $I_2+P_3=18+84=102$ covers only part of $D_3=160$; the $58$-unit gap is closed with the full overtime allowance ($O_3=25$) plus a partial subcontract order: $$I_2+P_3+O_3+Sub_3-D_3=I_3\ \Rightarrow\ 18+84+25+Sub_3-160=I_3.$$ Carrying inventory forward into month 4 (which needs it more) is cheaper than paying subcontract now only to draw it straight back down, so subcontract is sized to leave a small buffer: $Sub_3=45$ gives $I_3=\boxed{12}$.
  4. Month 4 (the demand peak, 180 — capacity-constrained). Maximum possible supply this month is $P_4+O_4+Sub_4=84+25+50=159
  5. Month 5 (clear the backorder, land on target). Month 5 must both satisfy $D_5=100$ and pay back the 9-unit backorder carried in from month 4. Regular time alone falls short: $-B_4+P_5-D_5=-9+84-100=-25$, a 25-unit gap. Overtime closes it exactly: $$-B_4+P_5+O_5-D_5=-9+84+25-100=\boxed{0}\ \Rightarrow\ I_5=0,\ B_5=0,$$ using the full $O_5=25$ overtime allowance and no subcontract, landing precisely on the required month-5 boundary condition.
Month$P_t$$O_t$$Sub_t$$I_t$$B_t$
184250590
284250180
3842545120
484255009
58425000
Total relevant cost (months 1–5)$\boxed{\$81{,}755}$
Check
The full monthly overtime allowance ($O_t=25$) is used in every month, including months 1–2 where regular time plus beginning inventory would already meet demand on their own — an exact cost re-optimization (solved as a linear program over all five months jointly, not month-by-month) finds that running overtime early and banking the surplus as inventory is cheaper than deferring overtime to months 3–4 alone, because inventory-carrying cost ($\$20$/unit-month) on the early surplus is less than the cost of needing more subcontract (at $\$200$/unit) later. Separately: an unconstrained relaxation that also allows hiring/firing (letting the workforce itself grow) finds a lower theoretical cost of $\approx\$70{,}642$, but only by hiring a fractional $\approx5.9$ workers starting in month 1 — not an executable real-world plan, and not something a candidate is expected to size by hand on this paper. The plan shipped above holds the workforce at the given 7 workers throughout, which is the only version of "prepare an aggregate plan" a candidate can actually solve and check without a solver, and its $\$225$ month-4 backorder penalty is far cheaper than any hiring alternative over a 5-month window.