23-Ind-A4 Production Management · December 2017
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Technical Examinations — December 2017 — 98-Ind-A4 Production Management. Three-hour, closed-book exam; Casio or Sharp approved calculators only. Format: eight questions, each worth 20 marks (sub-part weights 10/10 as tabulated on the front-page marking scheme); only the first five questions appearing in the answer book are marked, so candidates effectively choose 2 of 3 in Section A and 3 of 5 in Section B. All eight are solved below for completeness. The paper asks for point-form answers wherever possible; the solutions below use full working for clarity.
Reference texts: Nahmias & Olsen, Production and Operations Analysis (7th ed., Waveland/McGraw-Hill) — forecasting, inventory (EOQ/EPQ) and aggregate planning; Sipper & Bulfin, Production: Planning, Control, and Integration — production scheduling, JIT/kanban and shop-floor implementation gaps; Hillier & Lieberman, Introduction to Operations Research (11th ed.) — LP formulation and project scheduling (CPM/PERT); Pinedo, Scheduling: Theory, Algorithms, and Systems (5th ed.) — parallel-machine scheduling and days-off workforce scheduling; Hopp & Spearman, Factory Physics (3rd ed.) — variability, buffering, and production scheduling; Liker, The Toyota Way, and Shingo, A Revolution in Manufacturing: The SMED System — 5S, Five Whys, SMED and lean root-cause analysis.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Consider a single machine feeding a downstream assembly station, where the machine's processing time is not constant but varies randomly around its average (due to tool wear, operator technique, or intermittent minor jams). Queueing theory shows that as this processing-time variability increases — holding average utilization fixed — the average queue of parts waiting in front of the downstream station grows sharply and nonlinearly (the Kingman/VUT relation: waiting time scales with a variability term times a utilization term that explodes as utilization approaches 100%). The effect on productivity is direct and threefold: (1) the downstream station experiences unplanned idle time whenever its input buffer empties between arrivals, so its actual output per hour falls below what its rated capacity could achieve, even though no equipment or labour was added or removed; (2) more work-in-process inventory must be carried to buffer the variability, tying up capital and floor space without adding useful throughput (by Little's law $L=\lambda W$, buffering variability adds to flow time $W$ without adding to throughput $\lambda$); and (3) to protect delivery promises against the resulting unpredictable lead time, the plant typically quotes longer, padded lead times or carries extra finished-goods safety stock, both pure costs with no value added. To reduce or eliminate this variability, implement statistical process control (SPC) on the upstream machine's cycle time and standardize its operating procedure (tooling, changeover method, preventive-maintenance schedule) — converting an erratic, operator-dependent process into one with a tight, predictable distribution of processing times, which directly raises the downstream station's achievable output without adding any capacity.
A useful, general set of principles (synthesizing the standard “factory physics” and lean perspectives) is: