NivaarExam PrepOfficial exam papers ↗

23-Ind-A4 Production Management · December 2017

Question 4 of 8: WX93 Production Line — Setup/Inventory Trade-off (EPQ)

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Technical Examinations — December 2017 — 98-Ind-A4 Production Management. Three-hour, closed-book exam; Casio or Sharp approved calculators only. Format: eight questions, each worth 20 marks (sub-part weights 10/10 as tabulated on the front-page marking scheme); only the first five questions appearing in the answer book are marked, so candidates effectively choose 2 of 3 in Section A and 3 of 5 in Section B. All eight are solved below for completeness. The paper asks for point-form answers wherever possible; the solutions below use full working for clarity.

Reference texts: Nahmias & Olsen, Production and Operations Analysis (7th ed., Waveland/McGraw-Hill) — forecasting, inventory (EOQ/EPQ) and aggregate planning; Sipper & Bulfin, Production: Planning, Control, and Integration — production scheduling, JIT/kanban and shop-floor implementation gaps; Hillier & Lieberman, Introduction to Operations Research (11th ed.) — LP formulation and project scheduling (CPM/PERT); Pinedo, Scheduling: Theory, Algorithms, and Systems (5th ed.) — parallel-machine scheduling and days-off workforce scheduling; Hopp & Spearman, Factory Physics (3rd ed.) — variability, buffering, and production scheduling; Liker, The Toyota Way, and Shingo, A Revolution in Manufacturing: The SMED System — 5S, Five Whys, SMED and lean root-cause analysis.

Question 4: WX93 Production Line — Setup/Inventory Trade-off (EPQ) (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Check — assumed 5-day production week
Neither the number of production days per week nor the annual calendar (weeks/year) is stated explicitly. This solution assumes a standard 5-day production week (52 weeks/year, 260 production days/year) to convert the given weekly demand into a daily rate consistent with the given hourly production rate and 8-hour production day — a 7-day-week assumption would scale every daily rate by $5/7$ but leave the annual totals (which depend only on annual demand $D=7{,}000\times52$) unchanged.

Given. Multi-product line producing WX93 at $p=600$ units/hour ($=4{,}800$ units/production day); material value $c=\$0.02$/unit; setup time $=3$ h at a $\$50$/h worker wage; annualized holding-cost rate $=25\%$; weekly demand $=7{,}000$ units.

QuantityValue
Production rate, $p$$600$/h $\times\,8$ h/day $=4{,}800$ units/day
Demand rate, $d$ (5-day week)$7{,}000/5=1{,}400$ units/day
Annual demand, $D$$7{,}000\times52=364{,}000$ units/yr
Setup cost, $S$$3\text{ h}\times\$50\text{/h}=\$150$/setup
Holding cost, $H$$0.25\times\$0.02=\$0.005$/unit-yr

Find. (a) A production plan (batch size / cycle) trading off setup and inventory cost, and the resulting total annual setup + holding cost; (b) the considerations needed if demand triples to 20,000/week.

I⁠maxrun: t⁠p≈36.6 dconsume-only (line runs other products)one cycle t⁠c ≈ 125.4 production days (≈25.1 weeks)InventoryTime
Figure 1 — WX93 EPQ inventory profile (two cycles shown). Inventory ramps up at rate $p-d$ while the line is set up and running WX93 (duration $t_p\approx36.6$ production days), then declines at rate $d$ while the line produces other products, over a repeating cycle $t_c\approx125.4$ production days.

Approach. This is a finite-replenishment-rate (Economic Production Quantity) problem, not a simple instantaneous-delivery EOQ, because WX93 is produced at a finite rate $p$ that exceeds but does not vastly outstrip demand $d$: compute the EPQ batch size that minimizes total annual setup + holding cost, then derive the run length, cycle length, and number of setups/year that make up the production plan.

  1. Utilization and EPQ batch size. With demand-to-production ratio $u=d/p=1{,}400/4{,}800=0.2917$, the classic EPQ formula (which reduces holding cost by the fraction of the cycle inventory is actually accumulating, $1-u$) gives $$Q^*=\sqrt{\frac{2DS}{H(1-u)}}=\sqrt{\frac{2(364{,}000)(150)}{0.005(1-0.2917)}}=\boxed{Q^*\approx175{,}600\ \text{units}}.$$
  2. Production plan: run length, cycle length, setups/year. Each batch takes $t_p=Q^*/p=175{,}600/4{,}800\approx36.6$ production days to run, after which the line switches to other products for the rest of the cycle $t_c=Q^*/d=175{,}600/1{,}400\approx125.4$ production days ($\approx$25.1 weeks, $\approx$5.8 months) before WX93 is due again. This gives $D/Q^*\approx\boxed{2.07\ \text{setups per year}}$ — i.e., run a $\approx$175,600-unit batch of WX93 roughly once every 5–6 months, occupying the line for about 7.3 weeks each time.
  3. Total annual setup and inventory cost. At the optimum, annual setup cost equals annual holding cost: $$\text{Setup cost/yr}=\frac{D}{Q^*}S=2.07\times\$150\approx\$311,\qquad \text{Holding cost/yr}=H(1-u)\frac{Q^*}{2}\approx\$311,$$ $$\boxed{\text{Total annual setup}+\text{inventory cost}\approx\$622/\text{yr}}.$$
QuantityValue
EPQ batch size, $Q^*$$\approx175{,}600$ units
Production run length per batch, $t_p$$\approx36.6$ days ($\approx7.3$ weeks)
Cycle length, $t_c$$\approx125.4$ days ($\approx25.1$ weeks)
Setups per year$\approx2.07$
Total annual setup + holding cost$\approx\$622$/yr

(b) Considerations for the demand jump to 20,000/week. At the new demand, $d_2=20{,}000/5=4{,}000$ units/day, so utilization on WX93 alone rises to $d_2/p=4{,}000/4{,}800=83.3\%$ (up from 29.2%). Re-running the EPQ formula with $D_2=1{,}040{,}000$/yr gives $Q_2^*\approx611{,}900$ units, with a run length of $Q_2^*/p\approx127.5$ production days ($\approx25.5$ weeks) inside a cycle of $Q_2^*/d_2\approx153$ production days ($\approx30.6$ weeks) — i.e., the line would need to run WX93 almost continuously (about 83% of every cycle) just to keep up. Because this is a multi-product line that must also serve other products' setups and runs, this leaves very little calendar time for anything else, so the original plan cannot simply continue at a larger batch size. Key considerations: (i) check whether the demand spike is genuinely sustained or a temporary popularity surge before committing capacity, since the EPQ commits the line to a long, capacity-heavy run either way; (ii) if sustained, add capacity — a second shift/overtime on WX93, or a second (possibly dedicated) line, since 83% utilization leaves almost no slack for changeovers or the line's other products; (iii) apply SMED (Question 3) to cut the 3-hour setup time, which both frees real capacity and lowers $S$, pulling $Q^*$ and the run-length fraction back down; and (iv) coordinate with whichever product is driving WX93's new demand, since a demand this close to the line's rated capacity for a single component leaves no margin for normal demand variability.