Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
National Technical Examinations — May 2017 — 98-Ind-A4 Production Management. Three-hour, closed-book exam; Casio or Sharp approved calculators only. Format: eight questions, each worth 20 marks (sub-part weights 10/10 as tabulated on the front-page marking scheme); only the first five questions appearing in the answer book are marked, so candidates effectively choose 5 of 8. All eight are solved below for completeness. The paper asks for point-form answers wherever possible; the solutions below use full working for clarity.
Reference texts: Nahmias & Olsen, Production and Operations Analysis (7th ed., Waveland/McGraw-Hill) — forecasting, inventory (EOQ) and aggregate planning; Sipper & Bulfin, Production: Planning, Control, and Integration — production scheduling and shop-floor implementation gaps; Hillier & Lieberman, Introduction to Operations Research (11th ed.) — LP formulation and project scheduling (CPM/PERT); Pinedo, Scheduling: Theory, Algorithms, and Systems (5th ed.) — parallel-machine scheduling, makespan and tardiness; Hopp & Spearman, Factory Physics (3rd ed.) — variability, buffering, and production scheduling; Liker, The Toyota Way, and the Toyota Production System literature — 5S, Five Whys, and lean root-cause analysis.
Find. (a) The order interval, order quantity, and total annual ordering+holding cost at the economic order quantity; (b) using part (a)'s quantity at the true (higher) demand of 15,000/week, the resulting total cost, and its penalty relative to re-optimizing at that demand.
Approach. Apply the classical EOQ model to the forecast demand for part (a); for part (b), hold the order quantity fixed at part (a)'s $Q^{*}$ but evaluate the total-cost function at the true demand, and compare against the total cost of re-optimizing $Q$ at that same true demand.
Economic order quantity and annual cost (part a).
$$Q^{*}=\sqrt{\frac{2DS}{H}}=\sqrt{\frac{2(312{,}000)(12)}{0.005}}=\boxed{Q^{*}\approx38{,}698.8\ \text{fasteners}}.$$
Orders per year $=D/Q^{*}=312{,}000/38{,}698.8\approx8.06$/yr, i.e. an order interval of $52/8.06\approx\boxed{6.45\ \text{weeks}}$ (order roughly every 6–7 weeks). The total annual ordering+holding cost at $Q^{*}$ is
$$TC(Q^{*})=\frac{D}{Q^{*}}S+\frac{Q^{*}}{2}H=\frac{312{,}000}{38{,}698.8}(12)+\frac{38{,}698.8}{2}(0.005)=\boxed{\$193.49/\text{yr}}.$$
Cost of using part-a's quantity at the true 15,000/week demand (part b). The true annual demand is $D_2=15{,}000\times52=780{,}000$/yr. Holding $Q$ fixed at the part-(a) $Q^{*}=38{,}698.8$ but evaluating at $D_2$:
$$TC_{\text{wrong }Q}=\frac{D_2}{Q^{*}}S+\frac{Q^{*}}{2}H=\frac{780{,}000}{38{,}698.8}(12)+\frac{38{,}698.8}{2}(0.005)=\boxed{\$338.61/\text{yr}}.$$
True optimal cost at 15,000/week, and comparison. Re-solving the EOQ formula at the corrected demand:
$$Q_2^{*}=\sqrt{\frac{2D_2S}{H}}=\sqrt{\frac{2(780{,}000)(12)}{0.005}}\approx61{,}188.2\ \text{fasteners},\qquad TC(Q_2^{*})=\boxed{\$305.94/\text{yr}}.$$
Ordering the wrong (part-a) quantity instead of the true optimum costs $338.61-305.94=\boxed{\$32.67/\text{yr}}$ more, a $\boxed{10.7\%}$ penalty. This is a modest penalty despite the demand forecast being wrong by a full 150%, because the $TC(Q)$ curve is shallow near its minimum — the EOQ model is forgiving of moderate-to-large forecast error precisely because ordering and holding costs trade off against each other symmetrically around the optimum.
Quantity
Value
EOQ (part a), demand as forecast
38,698.8 fasteners, every ≈6.45 weeks
Total ordering+holding cost at EOQ (part a)
$193.49/yr
Cost using part-a quantity at true 15,000/wk demand (part b)
$338.61/yr
True optimal EOQ and cost at 15,000/wk (part b)
61,188.2 fasteners; $305.94/yr
Penalty for having used the wrong EOQ
$32.67/yr (10.7% above true optimum)
Check: fastener quantities are treated as continuous for the EOQ formula (standard practice for a high-volume, low-cost item); rounding to a whole fastener count changes the boxed totals by well under 0.01%.