23-Ind-A4 Production Management · May 2018
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
National Technical Examinations — May 2018 — 17-Ind-A4 Production Management. Three-hour, closed-book exam; Casio or Sharp approved calculators only. Format: eight questions, each worth 20 marks (sub-part weights 10/10 as tabulated on the front-page marking scheme); candidates do two questions from Section A and three from Section B, and only the first five questions appearing in the answer book are marked. All eight are solved below for completeness. The paper asks for point-form answers wherever possible; the solutions below use full working for clarity.
Reference texts: Nahmias & Olsen, Production and Operations Analysis (7th ed., Waveland/McGraw-Hill) — forecasting, inventory (EOQ/EPQ) and aggregate planning; Sipper & Bulfin, Production: Planning, Control, and Integration — production scheduling, JIT/kanban and shop-floor implementation gaps; Hillier & Lieberman, Introduction to Operations Research (11th ed.) — LP formulation and project scheduling (CPM/PERT); Pinedo, Scheduling: Theory, Algorithms, and Systems (5th ed.) — parallel-machine scheduling and days-off workforce scheduling; Hopp & Spearman, Factory Physics (3rd ed.) — variability, buffering, and production scheduling; Liker, The Toyota Way, and Shingo, A Revolution in Manufacturing: The SMED System — 5S, Five Whys, SMED and lean root-cause analysis.
Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.
Given. Multi-product line producing WX93 at $p=600$ units/hour ($=4{,}800$ units/production day); material value $c=\$0.02$/unit; setup time $=3$ h at a $\$50$/h worker wage; annualized holding-cost rate $=25\%$; weekly demand (part a) $=17{,}000$ units.
| Quantity | Value |
|---|---|
| Production rate, $p$ | $600$/h $\times\,8$ h/day $=4{,}800$ units/day |
| Demand rate, $d$ (5-day week) | $17{,}000/5=3{,}400$ units/day |
| Annual demand, $D$ | $17{,}000\times52=884{,}000$ units/yr |
| Setup cost, $S$ | $3\text{ h}\times\$50\text{/h}=\$150$/setup |
| Holding cost, $H$ | $0.25\times\$0.02=\$0.005$/unit-yr |
Find. (a) A production plan (batch size / cycle) trading off setup and inventory cost, and the resulting total annual setup + holding cost; (b) the considerations needed once demand jumps to 25,000/week.
Approach. This is a finite-replenishment-rate (Economic Production Quantity) problem, not a simple instantaneous-delivery EOQ, because WX93 is produced at a finite rate $p$ that exceeds but does not vastly outstrip demand $d$: compute the EPQ batch size that minimizes total annual setup + holding cost, then derive the run length, cycle length, and number of setups/year that make up the production plan; for part (b), first check whether the new demand rate is even physically achievable on this line before re-optimizing.
| Quantity | Value |
|---|---|
| EPQ batch size, $Q^*$ | $\approx426{,}440$ units |
| Production run length per batch, $t_p$ | $\approx88.8$ days ($\approx17.8$ weeks) |
| Cycle length, $t_c$ | $\approx125.4$ days ($\approx25.1$ weeks) |
| Setups per year | $\approx2.07$ |
| Total annual setup + holding cost | $\approx\$622$/yr |
(b) Considerations for the demand jump to 25,000/week. At the new demand, $d_2=25{,}000/5=5{,}000$ units/day — but the line's own maximum output at 600 units/hour over an 8-hour, 5-day week is only $600\times8\times5=24{,}000$ units/week. The requested 25,000/week exceeds the line's physical capacity under the standard schedule used in part (a); no batching strategy, however chosen, can make an EPQ plan feasible when $d>p$, since the $(1-d/p)$ term in the EPQ formula itself goes negative. This is a capacity problem, not an inventory-policy problem, and the considerations are: (i) confirm the new demand is genuinely sustained (a temporary popularity surge does not justify a permanent capacity commitment); (ii) add real capacity — overtime, a second shift, or a longer production week (a 6-day week alone would raise the ceiling to $28{,}800$/week, comfortably above 25,000, at the cost of overtime premium and no idle multi-product capacity); (iii) apply SMED (Question 3) to cut the 3-hour setup time, which frees genuine run-time capacity on this shared multi-product line rather than just shrinking $Q^*$; (iv) use the stock already built: if the part-(a) run began at week 0, after four weeks (20 production days) the line has built up $(4{,}800-3{,}400)\times20=28{,}000$ units, enough to cover a 1,000-unit/week shortfall for about 28 weeks while extra capacity is arranged; and (v) coordinate with whichever product is driving WX93's new demand, since a request this close to (and in this case beyond) the line's rated capacity leaves no margin for ordinary demand variability once any extra capacity is added.