NivaarExam PrepOfficial exam papers ↗

23-Ind-A4 Production Management · May 2018

Question 5 of 8: Li-Ion Battery Production LP Across Four Plants

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

National Technical Examinations — May 2018 — 17-Ind-A4 Production Management. Three-hour, closed-book exam; Casio or Sharp approved calculators only. Format: eight questions, each worth 20 marks (sub-part weights 10/10 as tabulated on the front-page marking scheme); candidates do two questions from Section A and three from Section B, and only the first five questions appearing in the answer book are marked. All eight are solved below for completeness. The paper asks for point-form answers wherever possible; the solutions below use full working for clarity.

Reference texts: Nahmias & Olsen, Production and Operations Analysis (7th ed., Waveland/McGraw-Hill) — forecasting, inventory (EOQ/EPQ) and aggregate planning; Sipper & Bulfin, Production: Planning, Control, and Integration — production scheduling, JIT/kanban and shop-floor implementation gaps; Hillier & Lieberman, Introduction to Operations Research (11th ed.) — LP formulation and project scheduling (CPM/PERT); Pinedo, Scheduling: Theory, Algorithms, and Systems (5th ed.) — parallel-machine scheduling and days-off workforce scheduling; Hopp & Spearman, Factory Physics (3rd ed.) — variability, buffering, and production scheduling; Liker, The Toyota Way, and Shingo, A Revolution in Manufacturing: The SMED System — 5S, Five Whys, SMED and lean root-cause analysis.

Question 5: Li-Ion Battery Production LP Across Four Plants (20 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

Check — Edison Motors contract feasibility
The model has four plants and three battery grades, with a per-grade profit and Li requirement, two constraints per plant, and the Edison Motors 2:1 Heavy:Medium contract. This sitting’s Edison Motors floor (10,000 Heavy $+$ 5,000 Medium $=15{,}000$ units/month) is Li-feasible against the system’s own capacity — confirmed by the direct LP solve below.

Given.

GradeUnit profitMax demand (units/mo)Li requirement (kg/battery)
Heavy (H)$\$12$17,000200
Medium (M)$\$10$19,000150
Light (L)$\$7$14,000100
PlantAssembly cap. (batteries/mo)Max Li production (kg/mo)
Quebec City (QC)15,500850,000
Toronto (TOR)17,500700,000
Vancouver (VAN)12,200500,000
Seattle (SEA)16,0001,000,000

Find. (a) An LP formulation allocating the three grades among the four plants to maximize total monthly profit; (b) the formulation modified so the Edison Motors order (15,000 units/month, Heavy:Medium $=2$:1) is guaranteed met every month.

Approach. Define a decision variable for each (grade, plant) pair; each plant has two independent capacity limits (assembly units, and kg of Li) since Li requirement differs by grade, and each grade has an independent market-demand ceiling summed across all plants.

  1. Decision variables and objective (part a). Let $x_{ig}\ge0$ be the number of grade-$i$ batteries produced at plant $g$, for $i\in\{H,M,L\}$, $g\in\{QC,TOR,VAN,SEA\}$. Maximize total monthly profit: $$\boxed{\max Z=12\sum_g x_{Hg}+10\sum_g x_{Mg}+7\sum_g x_{Lg}}.$$
  2. Constraints (part a). Each plant's total assembled units cannot exceed its assembly capacity; each plant's total Li consumed (grade-specific requirement $\times$ quantity) cannot exceed its Li capacity; and each grade's total production across all four plants cannot exceed its monthly demand ceiling: $$\sum_i x_{ig}\le \text{cap}_g\ \ \forall g,\qquad \sum_i \ell_i\,x_{ig}\le \text{LiMax}_g\ \ \forall g,\qquad \sum_g x_{ig}\le \text{Dem}_i\ \ \forall i,\qquad x_{ig}\ge0,$$ where $\ell_H=200,\ell_M=150,\ell_L=100$ kg/battery. This gives $3\times4=12$ variables, 4 assembly constraints, 4 Li constraints, and 3 demand constraints.
  3. Edison Motors floor (part b). A 2:1 Heavy:Medium mix totalling 15,000 units/month splits as 10,000 Heavy and 5,000 Medium ($\tfrac23\times15{,}000=10{,}000$, $\tfrac13\times15{,}000=5{,}000$). Edison's order is new volume on top of the existing market, and it must be met in full every month. So each of these two grades gets a floor equal to the contract, and its ceiling rises by the contract so existing customers can still be served up to their old limit: $$\boxed{10{,}000\le\sum_g x_{Hg}\le17{,}000+10{,}000=27{,}000}$$ $$\boxed{5{,}000\le\sum_g x_{Mg}\le19{,}000+5{,}000=24{,}000}$$ These replace the part-(a) demand rows for Heavy and Medium; the objective, Light's ceiling and all plant constraints are unchanged. Keeping the old $\le17{,}000$ and $\le19{,}000$ ceilings would wrongly make Edison's batteries displace existing customers.
ItemResult
Variables$x_{ig}$, 3 grades $\times$ 4 plants $=12$
Part (a) constraint count4 assembly + 4 Li + 3 demand $=11$ (+ non-negativity)
Part (b) modified demand rows$10{,}000\le\sum_g x_{Hg}\le27{,}000$, $5{,}000\le\sum_g x_{Mg}\le24{,}000$
Bonus: part-(a) LP solved, optimal profit$\approx\$208{,}000$/mo (Medium+Light only — see callout)
Bonus: part-(b) LP solved with Edison floor, optimal profit$\approx\$191{,}000$/mo (feasible — see callout)
Check — both LPs solved as a bonus check
Solving the part-(a) LP (not required by the question, but a useful validation) shows Li capacity, not assembly floor space, is the binding resource system-wide: since profit-per-kg-of-Li is $\$12/200=\$0.060$ (Heavy), $\$10/150=\$0.067$ (Medium), $\$7/100=\$0.070$ (Light), the unconstrained optimum produces zero Heavy, all of Medium's and Light's demand it can fit (Medium 11,000, Light 14,000 units), for $\approx\$208{,}000$/month.

Adding the Edison contract ($10{,}000\le H\le27{,}000$, $5{,}000\le M\le24{,}000$) and re-solving gives a feasible optimum of $H=10{,}000$, $M=5{,}000$, $L=3{,}000$ (profit $\approx\$191{,}000$/month, lower than the unconstrained optimum since the floor forces low-profit-per-kg Heavy into the mix) — system-wide Li usage in this solution is $3{,}050{,}000$ kg, all of the capacity (Edison needs $2{,}750{,}000$ kg; the remaining $300{,}000$ kg makes 3,000 Light), i.e. the contract is achievable with essentially zero Li to spare.