22-Mec-B4 Integrated Manufacturing Systems · December 2013
Question 5 of 7: Assembly-Line Balancing
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Exams, December 2013 —
07-Mec-B4, Integrated Manufacturing Systems. Three hours; open book;
any non-communicating calculator permitted. Seven questions are printed and any
five constitute a complete paper, each of equal value (20 marks); only the
first five appearing in the answer book are marked. Several questions call for
an essay answer, where clarity and organisation carry marks. Note 1 of the
paper invites the candidate to state any assumption made where a question is
open to interpretation — that licence is used twice below and each use is
flagged. All seven questions are worked here, so the set can
serve as a complete study resource.
Reference texts. Chase, Jacobs & Aquilano,
Operations and Supply Chain Management (McGraw-Hill) — the source
of this paper's forecasting, line-balancing, cost and quality material;
Groover, Automation, Production Systems, and Computer-Integrated
Manufacturing (Pearson) for process planning, cellular manufacturing,
flexible manufacturing systems and plant networks; Montgomery,
Introduction to Statistical Quality Control (Wiley) for the Shewhart
chart constants and the normal-tail scrap calculations; Nahmias & Olsen,
Production and Operations Analysis (Waveland) for the forecasting
derivations; Kalpakjian & Schmid, Manufacturing Engineering and
Technology (Pearson) for the ring-rolling and tolerance context. Canadian
practice for the quality half of the paper follows CSA / ISO 9001 and
the ISO 7870 series on control charts, which tabulate the same constants
used below.
Given. Eight assembly tasks with their times and their
technological precedence requirements, to be arranged on a paced line meeting a
forecast demand of 400 units in an eight-hour day.
Given data — task times and precedence
Task
Task time (seconds)
Tasks which must precede
A
50
—
B
40
—
C
20
A
D
45
A, C
E
20
A, C
F
25
A, C, D
G
10
A, C, E
H
35
A, B, C, D, E, F
Find. (a) the precedence diagram; (b) the theoretical
minimum number of workstations for the required output; and (c) a feasible
balance achieving that number, together with its efficiency.
Approach. Convert the daily demand into a cycle time, divide
the total work content by that cycle time to obtain the theoretical minimum
number of stations, then assign tasks to stations in precedence order using the
longest-task-time rule until the cycle time would be exceeded.
Figure 5.1 — Part (a): precedence diagram. Each box
carries the task letter and its time in seconds; an arrow runs from a task to
every task that may not begin until it is complete. Only immediate predecessors
are drawn, since the transitive requirements listed in the table follow from
them. Tasks A and B have no predecessors and may start at once; G and H are
terminal.
Part (a) — read the immediate predecessors out of the table.
The table lists all predecessors, but the diagram needs only the
immediate ones. Removing the transitive entries leaves
A: none; B: none; C: A; D: C; E: C; F: D; G: E; H: B, E and F. For example H is
listed as requiring A, B, C, D, E and F, but A, C and D are already implied
through F, so the arrows into H come only from B, E and F. This yields the
network drawn in Figure 5.1.
Part (b) — convert demand into a cycle time. The
available production time per day and the required output give the pace at which
a unit must leave the line:
$$C=\frac{\text{production time available per day}}{\text{units required per day}}
=\frac{8\ \text{h}\times 3600\ \text{s/h}}{400\ \text{units}}
=\frac{28{,}800}{400}=72\ \text{s per unit}$$
No station may be loaded beyond 72 s, or the line cannot meet demand.
Sum the work content and divide by the cycle time. The total
task time is
$$\textstyle\sum t_i=50+40+20+45+20+25+10+35=245\ \text{s}$$
so the theoretical minimum number of stations is
$$N_{\min}=\left\lceil \frac{\sum t_i}{C}\right\rceil
=\left\lceil \frac{245}{72}\right\rceil=\lceil 3.40\rceil
\ \Rightarrow\ \boxed{\ N_{\min}=4\ \text{stations}\ }$$
The ceiling is essential: 3.40 stations cannot be staffed, and three stations
would provide only $3\times 72=216$ s of capacity against 245 s of work.
Note also that the longest single task, A at 50 s, is below the cycle time,
so no task has to be split — the theoretical minimum is at least feasible
on that count.
Part (c) — choose a balancing rule. The
longest-task-time heuristic is selected: at each step, from the tasks
whose predecessors are all already assigned and whose time fits in the station's
remaining capacity, assign the one with the longest time; when nothing fits,
open a new station. The rule is chosen because it places the awkward, large
tasks early while stations are still empty, leaving the small tasks as the
flexible filler that closes the remaining gaps — the opposite order tends
to strand a large task in a station of its own.
Assign tasks to stations. Working through the rule with
$C=72$ s:
Station 1 — available tasks are A (50) and B (40); take A,
leaving 22 s. C (20) now becomes available and fits, leaving 2 s, which
accommodates nothing. Station 1 = {A, C}, load 70 s.
Station 2 — available are B (40), D (45), E (20); take D,
leaving 27 s; B does not fit but E does, leaving 7 s.
Station 2 = {D, E}, load 65 s.
Station 3 — available are B (40), F (25), G (10); take B,
leaving 32 s; take F, leaving 7 s; G does not fit alongside.
Station 3 = {B, F}, load 65 s.
Station 4 — the remaining tasks G (10) and H (35) both have
their predecessors assigned and together load 45 s.
Station 4 = {G, H}.
Station
Tasks assigned
Station time (s)
Idle time (s)
1
A, C
70
2
2
D, E
65
7
3
B, F
65
7
4
G, H
45
27
Total
8 tasks
245
43
Every precedence relation is respected — C follows A in the same station,
D and E follow C from Station 1, F follows D from Station 2, and G and
H follow E and F respectively — and no station exceeds 72 s, so the
balance is feasible in
$\boxed{\ 4\ \text{stations, the theoretical minimum}\ }$
Evaluate the balance. Line efficiency compares the work
actually done with the labour time purchased:
$$E=\frac{\sum t_i}{N_{\text{act}}\,C}=\frac{245}{4\times 72}=\frac{245}{288}=0.8507$$
$$\boxed{\ E=85.07\ \%\ \text{efficiency},\qquad d=1-E=14.93\ \%\ \text{balance delay}\ }$$
The 43 s of idle time per cycle is the price of indivisible tasks; over a
day it is $43\times 400=17{,}200$ s, or about 4.8 worker-hours. Actual daily
output is $28{,}800/72=400$ units, exactly the requirement, and the line's
bottleneck is Station 1 at 70 s, which would cap output at
$28{,}800/70=411$ units if the pace were allowed to float.
Check: the eight hours are taken as
fully available production time, since the paper quotes no allowance for breaks,
changeovers or downtime. If, for example, a 5 per cent allowance were
applied, the available time would fall to 27,360 s and the cycle time to
68.4 s; the theoretical minimum would still be
$\lceil 245/68.4\rceil=4$ stations and the balance above would still be feasible,
since its heaviest station is loaded to 70 s — which now exceeds the
cycle. Station 1 would have to shed task C to Station 2 in that case.
The balance given is therefore reported against the literal reading of the
question.