22-Mec-B4 Integrated Manufacturing Systems · May 2013
Question 5 of 6: Workforce Sizing for a Fixed-Deadline Contract
Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)
Notes on this paper
Paper format. National Exams, May 2013 — 07-Mec-B4,
Integrated Manufacturing Systems. Three hours; open book; any
non-communicating calculator permitted. Six questions are printed and any five
constitute a complete paper, each of equal value (20 marks); only the first five
appearing in the answer book are marked. Several questions call for an essay
answer, where clarity and organisation carry marks. Note 1 of the paper
invites the candidate to state any assumption made where a question is open to
interpretation — that licence is used twice below and each use is flagged.
All six questions are worked here, so the set can serve as a
complete study resource.
Reference texts. Chase, Jacobs & Aquilano,
Operations and Supply Chain Management (McGraw-Hill) — the source
of this paper's forecasting, scheduling, location and quality material;
Groover, Automation, Production Systems, and Computer-Integrated
Manufacturing (Pearson); Montgomery, Introduction to Statistical
Quality Control (Wiley) for the Shewhart chart constants and operating
characteristics; Nahmias & Olsen, Production and Operations Analysis
(Waveland) for the forecasting derivations; Kalpakjian & Schmid,
Manufacturing Engineering and Technology (Pearson) for the process
context. Canadian practice for the quality half of the paper is
CSA Q / ISO 9001 and the ISO 7870 series on control charts,
which adopt the same constants tabulated below.
Question 5: Workforce Sizing for a Fixed-Deadline Contract (20 marks)
Find. (a) the straight-time head count that just completes
the original contract in 30 working days, and (b) the additional head count
needed over the last 15 days if 300 further A's, in their own batch, are added
at the half-way point.
Approach. Convert the contract into standard hours, inflate
those standard hours to actual clock hours by dividing by the organisational
efficiency, divide by the hours one worker can offer in the available time, and
round up — a fractional worker cannot be hired and the deadline is
contractual.
Check: the data list both a
set-up time per unit and a standard set-up time per batch, and
the answer below treats these as two distinct charges — a per-unit
preparation allowance incurred on every piece, plus a once-per-batch machine
set-up. This is the reading that makes every line of the data table
load-bearing, and it is stated as an assumption in accordance with Note 1
of the paper. If the per-unit set-up were instead read as an alternative
statement of the batch set-up rather than an addition to it, the standard hours
would fall to 20,016 and 10,010 and the answers would become 157 and 60 workers;
the method is identical either way, and the assumption must be declared with the
answer.
Part (a) — total the standard hours for product A.
Each unit carries its run time plus its per-unit set-up allowance, and the batch
carries one machine set-up:
$$H_A = n_A\,(t_A + u_A) + b_A\,B_A = 1000\,(20 + 3) + 1\,(16) = 23{,}000 + 16 = 23{,}016\ \text{h}$$
where $n$ is the quantity, $t$ the standard time per unit, $u$ the set-up time
per unit, $b$ the number of batches and $B$ the standard set-up per batch.
Total the standard hours for product B, and for the contract.
By the same construction,
$$H_B = 2000\,(5 + 2) + 1\,(10) = 14{,}000 + 10 = 14{,}010\ \text{h}$$
so the contract requires
$$H = H_A + H_B = 23{,}016 + 14{,}010 = \boxed{37{,}026\ \text{standard hours}}$$
Note how the batch set-ups, 26 hours between them, are negligible here: with one
batch of each product the contract is overwhelmingly run time, which is why the
batching policy is not the lever on this problem.
Convert standard hours to actual clock hours. Standard
hours are what the work should take; the organisational efficiency of
80 per cent states that a clock hour on site delivers only 0.80 standard hours,
so
$$H_{\text{actual}} = \frac{H}{E} = \frac{37{,}026}{0.80} = \boxed{46{,}282.5\ \text{clock hours}}$$
The efficiency divides rather than multiplies: dividing inflates the requirement,
which is the correct direction, whereas multiplying would shrink it and is the
single commonest error on this type of question.
Convert to a head count. On straight time each worker offers
$$h_w = 30\ \text{days} \times 8\ \text{h/day} = 240\ \text{h}$$
so the requirement is
$$N = \frac{H_{\text{actual}}}{h_w} = \frac{46{,}282.5}{240} = 192.84\ \text{workers}$$
Rounding up, because 192 workers deliver only $192 \times 240 = 46{,}080$ clock
hours and would miss the contractual deadline,
$$\boxed{N = 193\ \text{workers}}$$
The crew is tight: 193 workers offer 46,320 clock hours against 46,282.5
required, a spare capacity of just 37.5 hours over the whole 30 days.
Part (b) — cost the added work. Three hundred more
A's, in a separate batch of A, add
$$H_X = 300\,(20 + 3) + 1\,(16) = 6{,}900 + 16 = \boxed{6{,}916\ \text{standard hours}}$$
and at the same 80 per cent efficiency,
$$H_{X,\text{actual}} = \frac{6{,}916}{0.80} = 8{,}645\ \text{clock hours}$$
Convert the added work to additional workers. Only the
back half of the schedule remains, so each additional worker can offer
$$h_{w,X} = 15\ \text{days} \times 8\ \text{h/day} = 120\ \text{h}$$
giving
$$N_X = \frac{8{,}645}{120} = 72.04 \quad\Rightarrow\quad
\boxed{N_X = 73\ \text{additional workers}}$$
The existing crew cannot absorb any of it: its entire spare capacity is 37.5
hours over 30 days, roughly 19 hours across the remaining 15, which is 0.16 of
one worker. The manufacturing department therefore runs 266 workers over the
last 15 days.
Sanity-check the answer against the deadline. Rounding up
from 72.04 to 73 buys $73 \times 120 = 8{,}760$ clock hours against 8,645
required, a cushion of 115 hours or about 1.3 per cent — thin enough that
management should note the risk. Two further points belong with the answer. The
head count nearly doubles the department for half the contract, so the
"pull workers off other projects instantly" assumption in the question is doing
a great deal of work; in reality the learning curve on a new batch of A would
depress effective efficiency below 80 per cent for the first units. And if the
efficiency figure is itself soft, the sensitivity is direct and linear: at
75 per cent efficiency part (a) becomes 206 workers and part (b) 77.
Final results — Question 5
Quantity
Value
Standard hours, product A (1,000 units, 1 batch)
23,016 h
Standard hours, product B (2,000 units, 1 batch)
14,010 h
Total standard hours, original contract
37,026 h
Actual clock hours at 80 per cent efficiency
46,282.5 h
Hours available per worker (30 days × 8 h)
240 h
(a) Workers required
193 (192.84 exact)
Standard hours, added 300 A's (separate batch)
6,916 h
Actual clock hours for the addition
8,645 h
Hours available per worker (15 days × 8 h)
120 h
(b) Additional workers required
73 (72.04 exact); 266 in total over the last 15 days