NivaarExam PrepOfficial exam papers ↗

24-MMP-B8 Rock Slope Engineering · Undated paper

Question 1 of 5: Mining Stages

Nivaar worked solution (AI-drafted; not reviewed by a licensed engineer)

Notes on this paper

09-MMP-B8, Mine Management & Systems Analysis — May 2019 sitting. 3-hour closed-book exam, answer all 5 questions for a total of 100 marks, Appendix A (discounted cash-flow factor tables) attached.

Reference texts. Hustrulid, Kuchta & Martin, Open Pit Mine Planning and Design (pit optimization, truck/shovel matching, mine scheduling); Hartman & Mutmansky (eds.), SME Mining Engineering Handbook (mine life-cycle, project economics, haulage systems); Blank & Tarquin, Engineering Economy (DCF/NPV/IRR/payback); Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide) (Critical Path Method).

Check: every page of the examination is headed “09-MMP-B8 Mine Management & Systems Analysis”. The content below solves the paper as printed.
Check: the data used below are as printed in the exam. (1) Table 1's LoM totals reconcile exactly against their own row sums (LoM ore 16,497 kt, contained 485.0 koz, recovered 397.7 koz, waste 86,468 kt). (2) The Mining unit cost in Table 3 is $11.75/t. (3) Question 2(a) asks for the gross and net value of ore per tonne. (4) The rolling resistance for Question 3's haul route is 6%. (5) Question 4's task table includes the task “Expand u/g diesel powered equipment fleet”. (6) Question 5's 2-D block model is a 5-row×8-column grid, the net processed mineral value is $2,800/tonne, and a 1.5% cutoff grade is stated.

Question 1: Mining Stages (15 marks)

Question text not reproduced: the examination questions are © Engineers and Geoscientists BC. Open the official past paper (linked at the top of this page) to read the question, then follow the worked solution below.

a) The five stages in the life of a mine

A mining project passes through five broad stages between initial discovery and final walk-away. 1 — Exploration. Regional prospecting followed by progressively more targeted geological mapping, geochemical sampling, geophysical surveys and diamond drilling, aimed at discovering and then delineating a mineralized zone well enough to estimate a resource. 2 — Development (Evaluation and Feasibility). The resource is converted to a mineable reserve through pre-feasibility and feasibility studies (geotechnical, metallurgical, environmental and economic work); permits are obtained and project financing is arranged. 3 — Construction. The bulk of the capital program is spent building mine access, the pit or underground workings, the processing plant, tailings/heap-leach facilities, and power/water infrastructure, and completing pre-production stripping/development. 4 — Operation (Production). Ore is extracted, processed and sold on a sustained basis; this is the only stage that generates revenue, and it is where the capital invested in stages 1–3 is recovered and, if the project is economic, turned into profit. 5 — Closure and Reclamation. Once reserves are exhausted, infrastructure is decommissioned, pit/waste-dump/tailings landforms are re-graded and re-vegetated, water treatment and long-term monitoring commitments are established, and the site is eventually relinquished to a stable, walk-away condition.

b) Typical cash flows through the five stages

Each stage has a characteristic cash-flow signature. Exploration is a small, sustained cash outflow spread over the years it takes to find and delineate a deposit — most exploration projects never reach a discovery, so this spend is high-risk with no assurance of return. Development is a larger outflow: feasibility studies, detailed engineering and permitting are expensive but still produce no revenue. Construction is the single largest cash outflow, concentrated into a relatively short, capital-intensive window as the mine and plant are built (analogous to the Year 0 pre-production capital spend of $80.8 million analyzed for the Gold Bar Mine in Question 2). Operation is the only stage with net cash inflow — revenue less operating cost, sustained for the whole production life — and must be large enough, for long enough, to repay the preceding three stages of outflow and still return a profit. Closure is a final outflow (decommissioning and reclamation cost) with no offsetting revenue. The resulting cash-flow diagram is a deep, widening valley (exploration → development → construction) followed by a sustained plateau of positive cash flow during production, ending in a small terminal dip at closure.

Cumulative cash position (schematic)ExplorationDevelopmentConstructionProductionClosuretime →Exploration/development/construction are cash outflows; production is theonly inflow stage; closure is a final outflow.
Fig. 1.1 — Schematic life-of-mine cash-flow diagram (relative magnitudes only): three outflow stages, a sustained production inflow, and a closure outflow.
← Paper overview